Russian Riverkeeper v. City of Ukiah CA1/3

CourtListener 10298448Calctapp20 dic 2024

Testo completo

Filed 12/20/24 Russian Riverkeeper v. City of Ukiah CA1/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or
ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION THREE

RUSSIAN RIVERKEEPER et al.,
Plaintiffs and Appellants, A168090, A169390

v. (Mendocino County
THE CITY OF UKIAH et al., Super. Ct. No.
SKUKCVPT202074612)
Defendants and Respondents.

The City of Ukiah (the City) operated a landfill from 1955 to 2001.
After ceasing operations and considering for many years how to go about
closing the landfill in a manner consistent with regulatory requirements, the
City selected a cover system called ClosureTurf, certified an environmental
impact report (EIR), and approved the proposed closure. Appellants Russian
Riverkeeper, Mateel Environmental Justice Foundation, and Vichy Springs
Resort, Inc. challenge this approval, contending that the project description
in the EIR failed to disclose that the cover system was only an interim
measure and would eventually need to be replaced, that the EIR failed to
analyze potential environmental impacts, that the draft EIR did not
adequately analyze a range of reasonable alternatives, and that the City
should have recirculated a revised draft EIR. Appellants also challenge the
trial court’s award of costs to the City. We affirm.

1
FACTUAL AND PROCEDURAL BACKGROUND
The Ukiah Solid Waste Disposal Site (the landfill) occupies
approximately 40 acres of a 283.5-acre parcel in Mendocino County. The City
ceased operations at the landfill in 2001. The project at issue in this case is
the closure of the landfill in a manner that accords with applicable regulatory
standards. The EIR explained that the necessary components and systems
include “the final cover and grading design” for the purposes of controlling
stormwater and potential infiltration and ensuring slope stability, as well as
systems for drainage and erosion control, landfill-gas control and monitoring,
and groundwater and surface water monitoring.
In anticipation of closing the landfill, the City had extensive
discussions with regulatory agencies, including the North Coast Regional
Water Quality Control Board (Regional Board), the California Department of
Resources Recycling and Recovery (CalRecycle), Mendocino County Public
Health Department (the Local Enforcement Agency), and the Mendocino
County Air Quality Management District, to develop a plan to close it in
accordance with their requirements.
We need not recite in full the lengthy history of these discussions, but
critical to them are the distinctions among different types of landfill covers.
Title 27 of the California Code of Regulations (Title 27) has “prescriptive
standards” for covers, which may be satisfied with a “natural” or compacted
clay liner that meets certain requirements. (Cal. Code Regs., tit. 27, § 21090,
subd. (a)(1)–(3).)1 The prescriptive standards require a foundation layer of at
least two feet made of materials such as compacted soil or incinerator ash,

1 The State Water Resources Control Board has promulgated

regulations to protect water quality in connection landfills. (Cal. Code Regs.,
tit. 27, § 20080 et seq.)

2
beneath a “low-hydraulic-conductivity layer” of at least one foot of compacted
clay soil to protect water quality by minimizing generation of leachate and
landfill gas, overlain by an erosion-resistant layer consisting of soil at least
one foot thick covered with vegetation or of other erosion-resistant materials
such as gravel and cobbles.2 (Ibid.) The landfill must be maintained and
monitored for at least 30 years, which is called the post-closure maintenance
period (Cal. Code Regs., tit. 27, § 21180, subd. (a)), and the discharger must
provide a maintenance plan with an annual cost estimate (Cal. Code Regs.,
tit. 27, § 21090, subds. (a)(3)(B), (a)(4)).
Where using a prescriptive cover is not feasible, either because it is
unreasonably burdensome and costly or because it is impractical and will not
promote the applicable performance standards, a cover with different (or
“engineered”) design may be approved. (Cal. Code Regs., tit. 27, §20080,
subd. (b).) Such an “engineered alternative” must be consistent with the
performance goals addressed by the prescriptive standard and must afford
equivalent protection against water quality impairment. (Id., subd. (b)(2).)
Two types of engineered alternatives are at issue here. The first is the
design the City chose for the landfill, known as ClosureTurf. This closure
design has several components. The first is a structured polyethylene
geomembrane, to protect water quality. (See Cal. Code Regs., tit. 27, § 21090,
subd. (a)(2).) Over it are placed a “specialized tufted geotextile,” or
“[e]ngineered [t]urf,” and 5/8 of an inch of sand infill, to resist wind and
erosion from weather conditions. (See Cal. Code Regs., tit. 27, § 21090,

2 For these purposes, “leachate” is “any liquid formed by the drainage of

liquids from waste or by the percolation or flow of liquid through waste.”
(Cal. Code Regs., tit. 27, § 20164.)

3
subd. (a)(3).) Underlying these three layers is a two-foot-thick soil foundation
layer. (See Cal. Code Regs., tit. 27, § 21090, subd. (a)(1).)
Another engineered alternative—not chosen for the project—is a
geosynthetic clay liner, consisting of a one-foot foundation layer, an artificial
(“geosynthetic”) liner, a polyethylene drainage net, and on top a two-foot-
thick vegetative layer.
As originally contemplated, the landfill closure would be accomplished
with a prescriptive compacted clay layer, and in 1999 the City approved a
Final Closure and Post-Closure Maintenance Plan that proposed a compacted
clay liner. But the Regional Board informed the City in 2000 that its clay
liner design did not satisfy the prescriptive standards because the City
proposed to compact only the top 12 inches of the foundation layer; as a
result, the City’s proposal would be considered an engineered alternative.
After further review, in 2003 the City submitted for the Regional Board’s
approval a design using a geosynthetic clay liner, but ultimately it did not
pursue this design.
In 2015 the City decided instead to proceed with ClosureTurf, based on
its conclusion that this system provided greater slope stability and cost
savings. The City’s engineers considered it important that ClosureTurf
provided more slope stability than other geosynthetic products because the
landfill had steep slopes. ClosureTurf eliminated the potential for “soil creep
and veneer failure” (i.e., mudslides) as a result of saturation of a vegetative
soil cover, which is an advantage over the prescriptive cover and other
geosynthetic cover systems. Also, the drainage system in ClosureTurf, which
allowed rainfall to penetrate rapidly through the sand infill layer and into a
drain liner, meant the cover was less subject to erosional damage, and
stormwater runoff would be cleaner than would be the case with a vegetative

4
soil cover. In addition, ClosureTurf’s rate of water infiltration into the
landfill was substantially lower than that of the prescriptive cover. The City
chose olive green as the color for the engineered turf.
By February 2020, the Regional Board agreed that the City’s Final
Closure and Post Closure Maintenance Plan adequately addressed Title 27’s
regulatory requirements.
As lead agency under the California Environmental Quality Act (Pub.
Resources Code, § 21000 et seq.; CEQA; see id., § 21067),3 the City prepared a
draft EIR, which it circulated in November 2019. Four comment letters were
received during the comment period, and in the final EIR, released in April
2020, the City responded to those comments. Just days before the meeting at
which the City had planned to certify the final EIR, it received comments
from appellants, raising for the first time the concern that the use of
ClosureTurf poses increased risks related to wildfire and water quality. The
City delayed its public hearing while it considered these comments. In the
interim, it arranged for Environmental Science Associates (ESA), an
environmental consulting firm that was not involved in preparing the draft
EIR, to address these new concerns. ESA prepared a memorandum
analyzing the issues raised in the belated comments. Its conclusions were
that the evidence did not support the newly raised concerns and there was no
need to recirculate the EIR.
At a public hearing on August 5, 2020, the City certified the EIR and
approved the landfill closure project.
Appellants brought their petition for writ of mandate on September 8,
2020. The trial court denied the petition and entered judgment in the City’s

3 All undesignated statutory references are to the Public Resources

Code.

5
favor. The City sought the costs it incurred in preparing the administrative
record, and appellants moved to tax costs. The trial court declined to tax
costs and awarded the City $76,056.31. Appellants moved for a new trial on
the issue of costs, and the trial court denied the motion.
In case number A168090, appellants challenge the judgment. In case
number A169390, appellants challenge the post-judgment order awarding
costs. We have consolidated the two appeals for purposes of oral argument
and decision.
DISCUSSION
I. STANDARD OF REVIEW
In reviewing an agency’s compliance with CEQA, our inquiry is
whether there was a prejudicial abuse of discretion. (Save the Hill Group v.
City of Livermore (2022) 76 Cal.App.5th 1092, 1103; Vineyard Area Citizens
for Responsible Growth, Inc. v. City of Rancho Cordova (2007) 40 Cal.4th 412,
426 (Vineyard Area); § 21168.5.) Such abuse is shown if the agency did not
proceed in the manner required by law or if its decision is not supported by
substantial evidence. (Pub. Resources Code, § 21168.5; see § 21168; Code
Civ. Proc., § 1094.5, subd. (b).) Our inquiry is not “ ‘ “whether the EIR’s
ultimate conclusions are correct but only whether they are supported by
substantial evidence in the record and whether the EIR is sufficient as an
informational document.” ’ ” (San Joaquin Raptor Rescue Center v. County of
Merced (2007) 149 Cal.App.4th 645, 653 (San Joaquin Raptor).) It is the
challenging party’s burden to show that the decision to certify the EIR was
incorrect. (Mount Shasta Bioregional Ecology Center v. County of Siskiyou
(2012) 210 Cal.App.4th 184, 195 (Mount Shasta).)
On appeal, we review the City’s actions, not the trial court’s decision.
(Vineyard Area Citizens, supra, 40 Cal.4th at p. 427.) Thus, we determine

6
independently “whether the administrative record demonstrates any legal
error by the [City] and whether it contains substantial evidence to support
the [City’s] factual determinations.” (Ibid.) On factual questions, we do not
weigh conflicting evidence and do “ ‘not set aside approval of an EIR on the
ground that an opposite conclusion would have been equally or more
reasonable.’ ” (Id. at p. 435.)
II. PROJECT DESCRIPTION
Appellants contend that the project description in the EIR is not
accurate and complete because it does not describe the ClosureTurf as an
interim remedy that will eventually need to be removed and replaced. And,
they argue, the EIR should have discussed the environmental effects of
replacing the cover.
An EIR must include a project description. (South of Market
Community Action Network v. City and County of San Francisco (2019) 33
Cal.App.5th 321, 332.) “Under CEQA, a ‘project’ means ‘the whole of an
action, which has a potential for resulting in either a direct physical change
in the environment, or a reasonably foreseeable indirect physical change in
the environment,’ ” and it “refers to the underlying ‘activity’ for which
approval is being sought. [Citation.] The entirety of the project must be
described, and not some smaller portion of it.” (San Joaquin Raptor, supra,
149 Cal.App.4th at p. 654.) These requirements allow agencies and members
the public to balance the benefits and environmental effects of the project,
consider mitigation measures, and weigh other alternatives. (Ibid.) We
review independently whether an EIR meets these standards. (Banning
Ranch Conservancy v. City of Newport Beach (2012) 211 Cal.App.4th 1209,
1224.)

7
The EIR describes the project as having the overall purpose of “clos[ing]
the Ukiah Landfill in accordance with applicable regulatory standards,” and
it explains that one of the components required for closure is “the final cover.”
Appellants urge that this description is inaccurate because the cover will
“inevitably” have to be removed and replaced, and the EIR failed to analyze
the potential environmental effects of removal and replacement.
During the years the City was considering how best to close the landfill,
it exchanged correspondence and documents with other agencies, including
the Regional Board, about the proper construction of the cover. Appellants
draw our attention particularly to a memorandum prepared in 2017 by a
consultant to the Regional Board, Richard Thiel of Thiel Engineering, which
discussed the design life of ClosureTurf. The memorandum characterized
ClosureTurf as a variant of an exposed geomembrane cover (EGC), and
explained that such cover systems can “be expected to degrade with time, and
eventually fail over time because they are, after all, only thin plastic layers
exposed to the environment.” Although the sand and turf layer proposed for
the project “could be expected to contribute to an extended service life
compared to a standard EGC, it is inevitable that the Closure Turf system
will degrade and need to be replaced as with any EGC concept.”
Based in part on Thiel’s opinions, the Regional Board provided
comments on the City’s proposed cover design. At the time, the City proposed
a foundation layer of 12 inches, rather than 24 inches. The Regional Board
explained that a thicker foundation layer would provide a greater physical
barrier between the waste and the environment. And, the Regional Board
stated, the geosynthetic cover “will inevitably degrade, stress crack, and
expose the underlying cover soils” over the course of “decades (not centuries),”
so “the ultimate closure condition that separates the degraded waste from the

8
open air environment will be the cover soils.” The City proposed to use a
geomembrane layer that was 50-mil thick, with a design life of approximately
40 years, rather than the apparently standard 60-mil thickness.4 The
Regional Board told the City that a 50-mil layer would be acceptable if the
final cover was considered “ ‘long-term temporary’ that will likely need to be
replaced,” if there was a financial mechanism to provide the funds to replace
the ClosureTurf cover, and if a standard 24-inch foundation soil layer
underlay the turf cover.
The manufacturer of ClosureTurf, Watershed Geo, responded with a
letter disputing the characterization of the cover as “ ‘long-term temporary.’ ”
It included a study showing the half-life of such turf fibers to be between 214
and 277 years, and stated that “[i]f the turf is properly maintained with sand
infill, there is no need to replace the pro[t]ective turf cover for at least 100
years.”
The City’s engineering consultant, EBA Engineering, also responded to
the Regional Board’s comments. It disputed the Regional Board’s statement
that the geosynthetic cover would last decades rather than centuries,
explaining that this timeframe was “not consistent with the ClosureTurf
design features, research, and product testing.” Contrary to what appear to
have been the Regional Board’s assumptions, the geomembrane component of
the system was not exposed, but rather fully protected from ultraviolet
degradation and other environmental stresses by the engineered turf and
infill. “[E]xtensive testing” at third party laboratories “shows the protective
turf cover with sand infill will last longer than 100 years,” and when
continually covered, the geomembrane was estimated to have a 450-year
lifespan. These features, EBA Engineering opined, “refute the ‘long-term

4 A “mil” is a thousandth of an inch.

9
temporary’ characterization . . . particularly in light of the projected life span
that is greater than three times the postclosure maintenance period
prescriptive standard of 30 years.” Once the exposed turf blades degraded,
the “grass” and geotextile backing could be replaced. Attached to the letter
was a longevity analysis report prepared by Geosyntec Consultants in 2015.
In these circumstances, we conclude the EIR was not required to
describe the cover as an interim remedy and analyze the environmental
effects of replacing it. An EIR need not discuss “unspecified or uncertain”
future developments, because such a discussion “ ‘would be based on
speculation about future environmental impacts.’ ” (Environmental Council
of Sacramento v. County of Sacramento (2020) 45 Cal.App.5th 1020, 1031.)
There is substantial evidence that the cover design selected by the City—in
which the geomembrane layer is not exposed to the environment—may last
for 100 years or more, which renders the possible environmental
consequences of replacing the synthetic cover generations in the future
“unspecified or uncertain.” (Ibid.; see Citizens’ Committee to Complete the
Refuge v. City of Newark (2021) 74 Cal.App.5th 460, 479 [potential responses
to changed environmental conditions in 50 to 80 years not part of project].)
This time frame is well in excess of the 30-year post-closure maintenance
period required by Title 27. (See Cal. Code Regs., tit. 27, § 21180, subd. (a).)
An agency need not “ ‘dimly guess’ about potential impacts based on
uncertain and nonspecific information and many unknowns.” (Santa Rita
Union School Dist. v. City of Salinas (2023) 94 Cal.App.5th 298, 349.) Here—
where the record supports the conclusion that the cover is likely to function
properly for at least a century—the City was not required to characterize the
proposed project as an interim remedy or analyze the environmental effects
that may occur when the cover, or portions of it, need to be replaced.

10
Appellants point out that the postclosure maintenance plan for the
project provides an estimate of maintenance costs during the 30-year
maintenance period that includes sums for geomembrane replacement,
demonstrating that replacement was reasonably foreseeable. The response to
the Regional Board’s comments in the final EIR explains that the City
provided financial assurances to address a possible replacement during
earlier discussions with the Regional Board about the proper thickness of the
foundation layer and the geomembrane liner, but that nonetheless testing
showed the protective turf cover with sand ballast would last more than 100
years. The response also explained that the City had addressed replacement
costs in the postclosure maintenance plan due to concerns about the
possibility of catastrophic wildfires. But none of this shows that the proposed
cover is an interim remedy likely to need replacing within a few decades, that
the EIR should have addressed the effects of the cover’s uncertain and
unknown future replacement, or that the EIR has failed in its mission as an
informational document.
III. EIR’S ANALYSIS OF ENVIRONMENTAL EFFECTS
Appellants contend the EIR lacked an adequate analysis of
environmental impacts in three respects.
An EIR must discuss in detail all of a project’s significant effects on the
environment. (§ 21100, subd. (b)(1).) When preparing an EIR the lead
agency must “ “consider and resolve every fair argument that can be made
about the possible significant environmental effects of a project.’ ” (Visalia
Retail, LP v. City of Visalia (2018) 20 Cal.App.5th 1, 13 (Visalia Retail).) A
“ ‘fair’ argument” for these purposes must be based on substantial evidence,
including “ ‘fact, a reasonable assumption predicated on fact, or expert
opinion supported by fact.’ ” (Id. at pp. 13–14, quoting § 21080, subd. (e)(1).)

11
If an agency determines that an effect will not be significant, the EIR need
not discuss it in detail, but may instead include “ ‘a statement briefly
indicating the reasons for determining that various effects on the
environment of a project are not significant and consequently have not been
discussed in detail in the environmental impact report.’ ” (Protect the
Historic Amador Waterways v. Amador Water Agency (2004) 116 Cal.App.4th
1099, 1109, citing § 21100, subd. (c).)
In our review, we bear in mind that an EIR is an informational
document, and the ultimate inquiry we make is “whether the EIR includes
enough detail ‘to enable those who did not participate in its preparation to
understand and to consider meaningfully the issues raised by the proposed
project.’ ” (Sierra Club v. County of Fresno (2018) 6 Cal.5th 502, 516 (Sierra
Club).) We give deference to factual determinations, including the choice of
methodologies to analyze an environmental effect, but we review de novo
whether the EIR satisfies the statutory criteria and serves its purpose as an
informational document. (Ibid.) Where the challenge is to the EIR’s
underlying factual conclusions, we review for substantial evidence, not
setting aside the EIR on the ground that another conclusion would have been
equally or more reasonable. (Id. at p. 512.) It is a project challenger’s burden
to point to substantial evidence supporting a fair argument that a project
may have a significant impact. (Visalia Retail, supra, 20 Cal.App.5th at
p. 17.)
A. Wildfire Risk
1. Additional Background
Appellants contend the EIR was inadequate because it failed to
evaluate the project’s contribution to a range of wildfire risks.

12
The initial study for the project considered whether the project would
expose people or structures to significant risk of loss, injury, or death
involving wildland fires, and concluded it would not. Specifically, the initial
study noted that after the project was completed there would be no long-term
occupancy by workers or others who might contribute to the potential for
wildland fires, although it was possible that fires could be started by
construction vehicles.
The draft EIR stated that the City had identified the appropriate scope
of the EIR by preparing an initial study and obtaining input from appropriate
agencies and the public. The City concluded that in certain areas it had
found no significant impacts or impacts that would require mitigation, and
thus eliminated those areas from consideration. Among the areas not
analyzed in the EIR were risks associated with hazards and hazardous
materials. According to the draft EIR, the project would comply with all
regulatory requirements to eliminate or minimize potential hazards
associated with the landfill, including risks related to fire, and no significant
long-term impacts were anticipated once the final cover was completed.
In its comments on the draft EIR, the Regional Board said that, in light
of California’s recent experiences with catastrophic wildland fires, the
project’s synthetic turf design was “an inherent surface-based vulnerability in
this regard.” For that reason, as well as because of the possibility that the
synthetic turf might degrade, the Regional Board requested a financial
assurance mechanism to address a possible replacement if the liner failed. In
response to this comment, the final EIR noted that the City shared concerns
about the potential of a catastrophic wildfire to affect the landfill cover, and
explained it had a post-closure maintenance plan and would take out
adequate insurance to cover the cost of replacement if necessary.

13
After the final EIR was released, appellants submitted comments
arguing that the synthetic cover was particularly flammable and, unlike a
natural cover, might release dangerous toxic materials if it caught fire. They
attached a report by PANGEA Environmental Services, Inc. (Pangea),
opining that the synthetic cover might decompose under fire conditions,
giving off hazardous products; that it appeared the cover would contain fibers
made of polyethylene, a combustible substance; and that airborne emissions
from the cover during a fire would represent a significant health risk to
nearby residents and firefighters. Pangea based its opinion in part on its
understanding that PFAS chemicals—short for perfluoroalkyl and
polyfluoroalkyl substances—have been found in artificial turf and that
exposure to PFAS chemicals can be detrimental to human and animal health.
The City arranged for the environmental consulting firm ESA to carry
out further analysis in response to these concerns. In a memorandum of July
17, 2020, ESA explained that tests had been conducted on ClosureTurf by
placing a fire source directly on them, using standards prescribed by the
American Society for Testing and Materials (ASTM) for roof coverings. In the
tests, the turf blades under the direct fire were either burned away or melted,
and blades four to six inches from the fire sources also melted. The adjacent
turf did not ignite or spread fire away from the flame sources, and the fire did
not burn through the underlying structured membrane. ESA’s memorandum
attached a report by Richgels Environmental Services, which conducted the
tests, explaining in detail the methods used and the results. ESA concluded,
“there is no basis to [appellants’] allegations that the landfill cover would
constitute a fire hazard or spread fire to adjoining areas if it were to be
exposed to sources of ignition.” On the other hand, ESA explained, “[n]atural
grass cover . . . is easily ignited and carries fire readily. In this respect, the

14
proposed landfill cover would result in an improved condition when compared
with the existing natural vegetation that currently covers the landfill, or the
Compacted Clay/Natural Cover Alternative advocated by [appellants].”
ESA expressly disagreed with Pangea’s assessment of the
combustibility of the synthetic cover. It explained that Pangea had studied
the wrong materials, that is, Pangea had provided material safety data
sheets (MSDS’s) for an unrelated artificial turf product and for high-density
polyethylene in its raw form, “which are not actually representative of the
ClosureTurf product.” Both the tests conducted on ClosureTurf and the
MSDS’s for that product—which stated the material is not flammable or
combustible and not expected to pose a fire hazard—countered appellants’
claim that the product was extremely flammable. And, ESA concluded, there
was only an insubstantial likelihood the landfill cover would burn in
quantities sufficient to cause widespread emissions of airborne toxins. ESA
also stated, and provided evidence, that the proposed landfill cover does not
contain PFAS chemicals.
In addition, the Fire Chief of the Ukiah Valley Fire Authority opined,
based on his many years of experience with firefighting, that the proposed
artificial covering would burn more slowly and with much less intensity than
vegetative fuels, and that although toxic air contaminants could be released,
the extent would be “very limited” given the relatively low fire intensity.
2. Analysis
We reject appellants’ challenge to the EIR’s discussion of wildfire risks.
The EIR explained that the project would comply with all regulatory
requirements to eliminate or minimize potential fire hazards and that no
significant long-term impacts were anticipated. The final EIR responded to
the Regional Board’s comment that the project’s synthetic turf design was

15
vulnerable to damage by acknowledging the concern that a wildfire could
harm the cover and agreeing to financial measures to cover the cost of
replacement if necessary. No concerns about the cover releasing harmful
toxins were raised during the comment period. Only after the final EIR was
released did appellants raise that issue for the first time.
The City was not required to respond in writing to this late comment.
(See Residents Against Specific Plan 380 v. County of Riverside (2017)
9 Cal.App.5th 941, 972 (Residents Against Specific Plan 380); CEQA
Guidelines, § 15088, subd. (a).)5 Nevertheless, after receiving the late
comments, the City had ESA conduct a detailed analysis, which explained
why Pangea’s report was flawed and set forth in detail the reasons that
proposed cover system did not pose any significant fire hazard. In the
circumstances, Pangea’s report does not constitute substantial evidence of a
significant environmental impact that required further discussion in the EIR.
Appellants criticize ESA’s analysis, arguing it does not address
flammability in “real world conditions” such as a parched landscape on a hot
afternoon or with the possible presence of methane gas at the landfill. It
appears that the concern about methane was raised for the first time the day
before the City held its hearing on the proposed project, and it was
unsupported by any analysis. And ESA’s analysis shows the proposed cover
was tested when “nearly ‘bone dry.’ ” Appellants have not shown the City’s
conclusions were unsupported by substantial evidence.
We thus conclude that the EIR was not required to include a further
discussion of fire hazards, and that substantial evidence supports the City’s

5 The CEQA Guidelines are found in title 14, section 15000 et seq. of

the California Code of Regulations. We accord them great weight unless they
are clearly unauthorized or erroneous. (Muzzy Ranch Co. v. Solano County
Airport Land Use Com. (2007) 41 Cal.4th 372, 380, fn. 2.)

16
finding that the project would not cause significant impacts related to
hazards and hazardous materials.
B. Water Quality
Appellants contend the EIR’s discussion of the project’s effects on water
quality was inadequate because it did not address the possible effects on
water quality from runoff of microplastics originating in the landfill’s
synthetic cover.
1. Additional Background
The EIR’s discussion of water quality explained the hydrology of the
project area, set forth the applicable water quality standards found in federal
and state law, and examined whether the project would have a significant
impact by violating water quality standards or waste discharge requirements
or otherwise substantially degrading surface or groundwater quality. It
explained that disturbed soils associated with construction activities could be
a source of water pollution and set forth the measures that would be taken to
ensure any effects would be less than significant. After completion of
construction, consistent with the requirements of the Regional Board’s waste
discharge requirements, there would be a program to monitor leachate,
groundwater, and surface water to ensure the landfill complies with all water
quality standards. The EIR concluded that compliance with regulatory
requirements, including corrective actions if necessary, would prevent
discharge of pollutants to surface waters or groundwater and that the
resulting environmental impact would be less than significant.
In comments after the final EIR was released, appellants for the first
time argued that the artificial turf cover could be a source of water pollution
from microplastics and PFAS that must be analyzed. In support, appellants
pointed to Pangea’s opinion that PFAS chemicals were present in artificial

17
turf and could be released from turf through exposure to abrasion, such as
maintenance equipment or feral pigs rooting, and could find their way into
nearby water supplies. Appellants also relied on a master’s thesis from
Stockholm University, Tracking Microplastics from Artificial Football Fields
to Stormwater Systems (Ran Li, Department of Physical Geography,
Stockholm University (2019)), which concluded that runoff from rainfall
carried microplastics to stormwater as the artificial turf degraded and broke
down over the course of the turf’s 8- to 15-year life span.
ESA prepared an analysis responding to these contentions. It
explained that testing on the material proposed to be used for the turf fiber
indicated it would retain 75 percent of its original tensile strength—its
resistance to breaking under tension—after 30 years and more than 60
percent after 100 years, when exposed to ultraviolet radiation. This meant
the product would degrade slowly, releasing only a “negligible” amount of
microplastics. And, because a layer of sand would be placed onto and worked
into the engineered turf, exposure to radiation would be reduced, further
reducing degradation of the blades, or tufts of artificial turf. ESA also
pointed out that the product discussed in the Stockholm University thesis
paper was “very different” from ClosureTurf and apparently of lower quality,
since it was expected to last only eight to 15 years, and unlike the proposed
landfill cover, it used as a filler material rubber granulates that were the
greatest contributing element of the microplastics run-off. The thesis paper
also studied active sports fields, which were subject to abrasion during sports
activities and snow removal, activities that would not take place on the

18
landfill cover. Finally, ESA pointed out, ClosureTurf did not contain PFAS
chemicals.
2. Analysis
Based on this and other evidence in the record that the exposed blades
of the landfill cover would eventually degrade when exposed to ultraviolet
light, appellants argue the EIR was inadequate because it did not address
how the activities of animals on the cover might affect the rate of breakage,
or what the consequences would be if microplastics entered the Russian
River, a source of drinking water in the area.
We are unpersuaded. We recognize that an EIR must set forth all
substantial or potentially substantial environmental impacts of a project,
resolving every fair argument that can be made about possible significant
effects (Visalia Retail, supra, 20 Cal.App.5th at p. 13), and that a post-EIR
discussion cannot make up for an inadequate analysis in the EIR itself
(League to Save Lake Tahoe v. County of Placer (2022) 75 Cal.App.5th 63,
107). Here, the EIR analyzed the project’s potential water quality impacts
and concluded they would not be significant. The concern about microplastic
pollution of waterways was raised, not only after the end of the public
comment period for the draft EIR, but after the final EIR was released, and
as we have explained, the City was not required to respond to late comments.
(Residents Against Specific Plan 380, supra, 9 Cal.App.5th at p. 972; CEQA
Guidelines, § 15088, subd. (a).) Nevertheless, the report prepared by ESA
before the project was approved explained why the information appellants
belatedly submitted did not indicate a potentially significant impact on water
quality: the Swedish paper examined a different and inferior product that
used rubber rather than sand as filler, and ClosureTurf does not contain

19
PFAS chemicals. In the circumstances, we cannot fault the City’s finding
that the EIR’s discussion of water quality was adequate.
C. Visual Impacts
Appellants’ final challenge to the adequacy of the EIR’s analysis of
environmental impacts is that it disregarded the “visual eyesore” that will be
caused by a permanently green plastic cover.
1. Additional Background
The draft EIR stated that the project site was at the end of Vichy
Springs Road, which the Mendocino County General Plan did not identify as
a scenic resource; that it would not be visible from the nearby Vichy Springs
Resort or any other sensitive receptor; and that the cover would be designed
to blend into the existing landscape. As a result, according to the draft EIR,
the project would not affect existing views from scenic corridors or roads. Of
three possible colors for the artificial cover—olive green, tan, and a blend of
olive green and tan—olive green was chosen as the preferred color because it
“provides arguably the best color option to blend into the natural and
surrounding environment.” The draft EIR included pictures of views from
“[k]ey [o]bservation [p]oints,” including from Vichy Springs Resort, showing
the landfill was not visible, as well as pictures of other landfills with artificial
covers.
In comments submitted during the public review period on the draft
EIR, Vichy Springs Resort expressed concern about the project’s visual
impacts. It argued that the olive green color chosen to cover the 40-acre
landfill site would be “bright and very ugly” and that it would be in stark
contrast to the surrounding hills, which were brown during the dry season. It
also provided evidence that the project site was visible from local residences
and hiking trails on the resort’s property.

20
The final EIR’s responses to comments explained the City’s continued
position that the artificial cover would not have an adverse visual impact.
Although the turf cover would not change color during the dry season along
with the surrounding natural grasses, contrasting landscape colors are
common in northern California, due to irrigation or natural sources of water
such as rivers or lakes, and any starkness in the green color would be
softened by the sand ballast. The turf is designed to look like natural grass,
so it would not appear artificial from a distance of 500 feet or more. And the
closest building at Vichy Springs Resort is about 1,200 feet from the landfill
site, its view obscured by trees, elevation and distance; the hiking trails are
farther away; and any partial views would not be unharmonious.
Consistent with these responses, the final EIR revised and expanded
the discussion of visual impacts. Among other things, it explained that
although the landfill cover would not be visible from the main lodges and
primary facilities of the Vichy Springs Resort, there are partial distant views
of the landfill site from some vantage points on the 700-acre resort, including
from its hiking trails; that from that distance the artificial turf would be
indistinguishable from natural grass; and that color contrasts on the
landscape are common. To support its conclusions, the final EIR included
pictures of viewpoints of the landfill site, a simulation of the landfill after
construction, artificial turf and natural grass of various colors, including olive
green, and examples of green grass and vegetation next to brown dry hills in
various parts of California.
2. Analysis
Appellants argue that the draft EIR’s assertion that the project would
not be visible from the Vichy Springs Resort or any other sensitive receptor
was inaccurate, and that it provided a misleading description of how visible

21
the landfill cover would be. And, they contend, the final EIR’s revised
analysis “downplayed and disregarded” the landfill cover’s visual impacts.
In considering this challenge, “[t]he question before us is not whether
substantial evidence supports a petitioner’s critique of the EIR; it is whether
substantial evidence supports the agency’s conclusions.” (East Oakland
Stadium Alliance v. City of Oakland (2023) 89 Cal.App.5th 1226, 1242, citing
Sierra Club v. County of Fresno, supra, 6 Cal.5th at p. 512.) Such evidence
exists here, and it was set forth in detail in the EIR. In the final EIR, the
City considered the objections and evidence submitted by Vichy Springs
Resort and explained why, even taking them into account, the project’s
aesthetic effects would not be significant, supporting its discussion with
images. This discussion was ample to allow both the City and members of
the public to understand and consider the aesthetic issues raised by the
landfill cover.6 (See Sierra Club, at pp. 515–516.)
IV. RANGE OF ALTERNATIVES STUDIED IN EIR
A. Additional Background
The draft EIR analyzed in detail only one alternative to the project—
the no-project alternative—and concluded it would not meet any of the
project objectives. With this alternative, the landfill would not be properly
closed, and it would be susceptible to slope instability and detrimental
impacts to water and air quality.

6 Appellants quibble that an illustration in the draft EIR showing how

a human figure appears smaller and less prominent as a viewer moves
progressively farther away is misleading because the 40-acre landfill is far
larger than a human being. Whether or not the illustration is helpful, the
other portions of the EIR we have discussed provide substantial evidence to
support the City’s conclusions.

22
The draft EIR also summarized three alternatives that the City had
considered and eliminated from further consideration. The first, which it
titled “Compacted Clay and/or Geo Synthetic Clay Liners with Natural
Vegetation Closure Alternative” (the clay cover alternative) referred
collectively to two liner types we have already described, the prescriptive
compacted clay liner and an engineered geosynthetic clay liner. (Boldface
omitted.) The draft EIR explained that the compacted clay liner was a 1974
standard that in 1985 was adopted as part of Title 27. But, the EIR went on,
the last 35 years had shown that there are serious disadvantages to clay
layers, particularly on sites with slope stability issues. The project site, with
a steep slope of more than 2:1, carried with it an unreasonably high potential
for failure of a clay alternative. The draft EIR also described other
environmental disadvantages to the clay cover alternative: construction
would cause greater noise, air quality, and traffic impacts because of the need
to import or excavate large volumes of clay and natural vegetation, and there
would be greater maintenance costs to prevent fires and keep rodents from
compromising the clay layer structure.
A second alternative eliminated from further consideration was
relocation of the landfill, an alternative found technically infeasible, cost-
prohibitive, and likely to cause significant and unavoidable traffic and noise
impacts.
The third alternative not carried forward was an alternative color for
the landfill’s turf cover. The draft EIR explained the olive green had been
selected because it would best blend into the surrounding environment; that
the landfill was not accessible to the general public and would not be visible
at any public access point or on the nearby Vichy Springs Resort property;

23
and that a different color for the cover would not avoid any significant
aesthetic impacts.
In comments on the draft EIR, Vichy Springs Resort argued the City
had failed to consider an adequate range of alternatives and, in particular,
that it should have considered an alternative calling for a natural cover
rather than an artificial cover in order to reduce the project’s aesthetic
impacts. The comment letter included photographs showing that the landfill
site was visible from various observation points, including trails on the
resort’s property and nearby residences.
The Regional Board also submitted comments on the draft EIR. It
expressed concerns about the alternatives analysis, pointing out that the sole
alternative studied, the no project alternative, was not viable from a
regulatory point of view. It also suggested the EIR could be improved by
including an economic cost analysis to support the narrative discussions of
the eliminated clay cover alternative.
In response to these comments, the final EIR included an expanded
evaluation of the clay cover alternative, treating it as an alternative to be
analyzed rather than one considered and eliminated. The long-term
aesthetic and visual impacts of the clay cover alternative, it concluded, would
be similar to those of the proposed project. Although the color of the
ClosureTurf cover would not change with the seasons, the final EIR
explained, it is common in northern California to see irrigated green grass
next to dry hills, and from the distance at which any onlooker would see the
project, the ClosureTurf cover would be virtually indistinguishable from a
clay cover with natural vegetation.
As to other environmental impacts, the final EIR concluded the clay
cover alternative would produce slightly greater air quality, greenhouse gas,

24
and noise impacts than the proposed project, both during and after
construction; and that it would involve increased disruption to biological
resources during construction and an increased water quality impacts from
erosion due to the steep slopes of the landfill. The final EIR concluded the
proposed project was the environmentally superior alternative. It included a
chart comparing the potential environmental impacts of the project, the clay
cover alternative, and the no project alternative, and concluded that with
mitigation, the project would have no significant environmental effects and
that the effects of the clay cover alternative would be either equal or
potentially greater.
B. Analysis
CEQA requires an EIR to consider and analyze alternatives to a project
that would reduce adverse environmental effects. (In re Bay-Delta etc. (2008)
43 Cal.4th 1143, 1163 (Bay-Delta); Pub. Resources Code, § 21061.) The
CEQA Guidelines provide that an EIR shall “describe a range of reasonable
alternatives to the project, or to the location of the project, which would
feasibly attain most of the basic objectives of the project but would avoid or
substantially lessen any of the significant effects of the project, and evaluate
the comparative merits of the alternatives.” (CEQA Guidelines, § 15126.6,
subd. (a).) The EIR must also identify alternatives that were considered but
eliminated from detailed consideration, for either failure to meet most of the
basic project objectives, infeasibility, or inability to avoid significant
environmental impacts. (CEQA Guidelines, § 15126.6, subd. (c).) It must
also discuss and analyze a “ ‘no project’ ” alternative. (CEQA Guidelines,
§ 15126.6, subd. (e)(1).)
“ ‘There is no ironclad rule governing the nature or scope of the
alternatives to be discussed other than the rule of reason,’ ” a rule that

25
requires the EIR to “ ‘set forth only those alternatives necessary to permit a
reasoned choice’ and to ‘examine in detail only the ones that the lead agency
determines could feasibly attain most of the basic objectives of the project.’ ”
(Bay-Delta, supra, 43 Cal.4th at p. 1163.) It is the appellant’s burden to
demonstrate that the range of alternatives chosen was inadequate. (Mount
Shasta, supra, 210 Cal.App.4th at p. 199.)
Although EIR’s commonly examine alternatives in addition to the no-
project alternative, there may be circumstances in which no other alternative
need be examined. For instance, in Save Our Access etc. v. Watershed
Conservation Authority (2021) 68 Cal.App.5th 8 (Save Our Access), the court
considered the adequacy of an EIR for an improvement project in a national
forest. (Id. at p. 14.) The EIR explained why it eliminated several
alternatives and examined no alternative to the project other than the no-
project alternative. (Id. at pp. 30–31.) On appeal, a challenger argued this
analysis was inadequate, pointing to several alternatives he had proposed in
comments on the draft EIR. (Id. at p. 32.) The appellate court rejected this
argument. It explained, first, that there is no categorical rule that an EIR
analyze multiple project alternatives (id. at p. 31) and that courts generally
defer to an agency’s selection of alternatives unless the petitioners
“ ‘(1) demonstrate that the chosen alternatives are “ ‘ “manifestly
unreasonable and . . . do not contribute to a reasonable range of
alternatives” ’ ” and (2) submit evidence showing the rejected alternative was
both “feasible” and “adequate,” because it was capable of attaining most of
the basic objectives of the project’ ” (id. at p. 32). The petitioner, the court
concluded, had not made this showing. Nor had it explained how any other
alternative would avoid or lessen one or more of the significant effects of the
project. (Id. at p. 33.) In fact, the agency had found the project had no

26
significant impacts that could not be avoided or reduced to a less than
significant level. (Ibid.) In the circumstances, the appellate court rejected
the plaintiff’s challenge to the adequacy of the range of alternatives analyzed
in the EIR. (Ibid.)
The court in Save Our Access relied in part on an earlier case upholding
an EIR that considered only a no-project alternative. (Save Our Access,
supra, 68 Cal.App.5th at p. 31.) In that case, Mount Shasta, the EIR for a
project to expand a manufacturing facility explained that it had considered
but rejected from consideration several alternatives that either would not
meet the project objectives or would result in increased environmental
impacts. (Mount Shasta, supra, 210 Cal.App.4th at pp. 189, 197–198.) In the
absence of a showing that the EIR failed to include a particular alternative
that was potentially feasible or that the range of alternatives was not
reasonable under the circumstances, the appellate court rejected the
plaintiffs’ challenge to the adequacy of the alternatives analysis. (Id. at
p. 199; see also San Franciscans for Livable Neighborhoods v. City and
County of San Francisco (2018) 26 Cal.App.5th 596, 633 [rejecting contention
that, as a matter of law, an EIR that considers only the proposed project and
a no-project alternative is inadequate].)
Appellants argue that the draft EIR fell short of CEQA’s requirements
that it study a range of alternatives by eliminating from consideration a
feasible alternative—the clay cover alternative, and that the added
discussion in the final EIR did not remedy this omission.
We are unpersuaded. An EIR need discuss only alternatives that
would avoid or substantially lessen any of the project’s significant effects.
(CEQA Guidelines, § 15126.6, subd. (a); Save our Capitol! v. Department of
General Services (2023) 87 Cal.App.5th 655, 703 (Save our Capitol).) The

27
draft EIR explained that each of the alternatives the City initially
considered—including the clay cover alternative—would be infeasible, would
have greater environmental effects (due in part to the steep slope of the
landfill and the greater risk that a clay cover would fail), or would not reduce
any significant effects. We have already rejected appellants’ challenges to
the EIR’s analysis of the project’s environmental effects, and we see no
grounds to conclude that the project will have significant effects that an
alternative would avoid or reduce.
We acknowledge that the range of alternatives analyzed in the draft
EIR was provocatively narrow, especially because the no-project alternative
was not viable from a regulatory standpoint. But even if this initial
discussion was inadequate, the final EIR did examine a clay cover alternative
in detail. Appellants argue that a defective draft EIR may not be remedied
by addition of required material in a final EIR after public review and
comment is complete. For this, they rely on Joy Road Area Forest &
Watershed Assn. v. California Dept. of Forestry & Fire Protection (2006) 142
Cal.App.4th 656, 674–678, 683–684 (Joy Road), but that case does not assist
them. In Joy Road, a state agency approved a planning document subject to
CEQA (a timber harvest plan) that lacked an adequate analysis of one of the
project’s environmental effects and was thus insufficient as an informational
document. (Id. at pp. 666, 676, 678.) Here, the EIR certified by the City did
analyze a clay cover alternative in addition to the no-project alternative.7

7 The timber harvest plan in Joy Road also added significant

information about a different environmental effect after a draft had been
made available for public review and comment, which triggered a need for
recirculation. (Joy Road, supra, 142 Cal.App.4th at pp. 664, 683.) We will
consider below whether the final EIR’s expanded discussion of alternatives
likewise mandated recirculation.

28
And the analysis added in the final EIR provided substantial evidence,
consistent with the draft EIR, that a clay cover had no environmental
advantages over the proposed project.
Appellants challenge the final EIR’s analysis on the ground it
“assumed,” without supporting evidence, that clay would need to be imported
to the project site; that the proposed artificial turf cover would be
indistinguishable from natural grass; and that a clay cover would require
more maintenance than the proposed cover. Not so. The final EIR did not
make the assumption that clay would be imported; rather, it also
contemplated that the necessary clay might come from on-site and thus
increase the project’s construction footprint. As we have explained, the final
EIR includes a detailed discussion, supported by substantial evidence, of the
aesthetic impacts of the artificial cover. And the final EIR explains that the
landfill has “very steep, 2:1, slopes,” and a clay cover would be more likely to
fail and would require additional maintenance. It also explains that,
although a natural or clay closure option was officially adopted in 1985 as
part of Subchapter 15 of Title 27 of the California Code of Regulations, the
ensuing 35 years of experience had shown “serious short-falls with compacted
clay layers from both a performance and cost perspective—especially on sites
with slope stability issues.” And the responses to the Regional Board’s
comments, included in the final EIR, provide more supporting detail,
explaining that vegetative soil covers require regular maintenance and that
an economic analysis showed the 30-year post-closure maintenance costs for
ClosureTurf would be approximately $277,000 less than for vegetative soil
cover.
Appellants contend, however, that the economic analysis the City
provided in response to the Regional Board’s request is flawed and was thus

29
insufficient to allow not only the City but also the Regional Board and other
agencies to determine whether to permit the project. Appellants point out
that an estimate of closure and post-closure maintenance costs for a clay
cover, prepared in 1999, showed lower costs than an estimate for the
ClosureTurf prepared 17 years later, in 2016. As a result, they argue, the
proposed project will not satisfy a regulation of the State Water Resources
Control Board authorizing alternative covers only if a prescriptive cover
would be “unreasonably and unnecessarily burdensome and will cost
substantially more than alternatives” that meet the relevant criteria. (Cal.
Code Regs., tit. 27, § 20080, subds. (b), (c).) Again, we are unpersuaded. It is
not surprising that costs might have increased over the intervening period of
almost two decades, and the differing estimates do not undermine the final
EIR’s economic analysis of alternatives.
In their reply brief, appellants rely upon different costs of two types of
earthen covers, a compacted clay layer and a geosynthetic clay layer. In
2003, EBA Engineering prepared a report for the Regional Board that
concluded final closure costs for geosynthetic clay liners were lower than for
compacted clay liners covers. Based on this report, the final EIR compared
the costs of the proposed product only to the geosynthetic clay liner. But
appellants point out that in 2008, EBA Engineering revisited its analysis
because of an increase in petroleum costs and concluded that at that time
compacted clay liners were less costly then geosynthetic clay liners.
The parties point us to nothing in this record that explains why the
final EIR relied on the 2003 comparison rather than the 2008 comparison.
But we must resolve conflicts in the evidence in favor of the City’s decision
(California Native Plant Society v. City of Santa Cruz (2009) 177 Cal.App.4th
957, 984–985), and it does not appear the Regional Board expressed any

30
concerns about this aspect of the analysis. And this question about the costs
of the project tells us nothing about whether either of the possible clay liner
approaches would avoid or reduce any significant environmental effects. (See
Save our Capitol, supra, 87 Cal.App.5th at p. 703.)8
We therefore conclude that appellants have not shown that the EIR’s
discussion of alternatives was inadequate.
V. RECIRCULATION
Appellants argue the final EIR includes significant new information
that required it to be recirculated for comment from agencies and members of
the public.9
If “significant new information” is added to an EIR after the draft EIR
has been made available for public review but before certification, the lead
agency must recirculate the EIR. (CEQA Guidelines, § 15088.5, subd. (a).)
New information added to an EIR is significant only if “the EIR is changed in
a way that deprives the public of a meaningful opportunity to comment upon

8 In responses to comments, the final EIR stated that a ClosureTurf

cover “is conditionally approved by all of the necessary regulatory agencies,
including Cal Recycle,” and it drew attention to examples of other successful
uses of artificial turf covers. Appellants argue this statement is inaccurate
because no responsible agency had approved use of ClosureTurf for this
project. The City in turn points to communications with agencies that it
argues show they acknowledged the City’s closure plans met their
requirements. Regardless of whether the wording of this response to a
comment was inartful, appellants do not show that it undermined the
adequacy of the EIR.

9 The City argues in a footnote that appellants forfeited this argument

by failing to raise it properly below. (See Nordstrom Com. Cases (2010) 186
Cal.App.4th 576, 583.) But appellants argued both before the City and in the
trial court that recirculation was required, and the trial court addressed the
issue in its statement of decision. We will consider this argument on the
merits.

31
a substantial adverse environmental effect of the project or a feasible way to
mitigate or avoid such an effect (including a feasible project alternative).”
(Ibid.; Southwest Regional Council of Carpenters v. City of Los Angeles (2022)
76 Cal.App.5th 1154, 1183.) For example, the CEQA Guidelines explain, new
information is significant when (1) “[a] new significant environmental impact
would result from the project or from a new mitigation measure proposed to
be implemented”; (2) there is a substantial increase to the severity of an
environmental impact unless mitigated; (3) “[a] feasible project alternative or
mitigation measure considerably different from others previously analyzed
would clearly lessen the significant environmental impacts of the project, but
the project’s proponents decline to adopt it”; and (4) the draft EIR was too
“fundamentally and basically inadequate and conclusory” to allow
meaningful public review and comment. (CEQA Guidelines, § 15088.5,
subd. (a).) Where, however, the new information added to the EIR “merely
clarifies or amplifies or makes insignificant modifications in an adequate
EIR,” recirculation is not necessary. (CEQA Guidelines, § 15088.5, subd. (b).)
Recirculation is intended to be the exception, not the rule. (Southwest
Regional Council, at p. 1184.) We review an agency’s decision not to
recirculate an EIR for substantial evidence, resolving doubts in favor of
upholding the administrative decision. (Ibid.; CEQA Guidelines, § 15088.5,
subd. (e).)
Appellants contend the final EIR meets the standard for recirculation
in two respects: it added a discussion of a clay cover alternative; and it
contained new information about ClosureTurf’s susceptibility to wildfire
damage. Both of these arguments fail.
Appellants argue that the draft EIR treated a clay cover alternative as
not feasible but the final EIR “revers[ed]” that determination when it

32
analyzed such an alternative, which appellants treats as significant new
information requiring recirculation. But new information is not
“ ‘significant’ ” unless it changes the EIR in a way that prevents meaningful
comment on “a substantial adverse environmental effect of the project or a
feasible way to mitigate or avoid such an effect.” (CEQA Guidelines,
§ 15088.5, subd. (a), italics added.) The final EIR’s analysis of a clay cover
alternative found no respect in which it would avoid or lessen a significant
environmental effect. This conclusion was consistent with the draft EIR’s
discussion of the reasons the clay cover alternative was initially eliminated
from consideration, including that it would increase the project’s adverse
effects. Appellants have not shown these findings to be unsupported by
substantial evidence. The final EIR’s discussion of the clay cover alternative
thus did not trigger a need for recirculation.
The same is true of the final EIR’s discussion of wildfire risk.
Appellants rely on the final EIR’s statement, made in response to the
Regional Board’s comment letter, that the City “shares concerns about
catastrophic wildfires and [their] potential to adversely impact the landfill
cover,” as a result of which it would take out insurance to cover replacement
costs in the event of a catastrophic wildfire. This response does not show a
“new significant environmental impact” triggering a need for recirculation.
(CEQA Guidelines, § 15088.5, subd. (a)(1).) Rather, the City found the
project would not cause a significant environmental effect relating to
wildfires, a finding we have upheld. We thus conclude the City was not
required to recirculate the EIR.10

10 As it did in the trial court, the City has requested judicial notice of

three documents: a June 2021 waste discharge order of the Regional Board
for a closure of a different solid waste disposal site in Mendocino County; a
resolution of the State Water Resources Control Board dated June 16, 2020,

33
VI. AWARD OF COSTS
A. Additional Procedural Background
After filing their petition for writ of mandate, appellants elected to
prepare the record, and on September 18, 2020, they requested documents
from the City under the California Public Records Act. (Former Gov. Code,
§ 6250 et seq.; see Gov. Code, § 7920.000 et seq.) City staff gathered
documents and produced them on December 2, 2020.
Over the next 14 months, appellants sent seven meet and confer letters
to the City requesting additional documents. In the first, they pointed out
that the documents the City had produced did not include the initial studies
or other documents associated with mitigated negative declarations prepared
for the 1999 and 2016 versions of the Final Closure and Post-Closure
Maintenance Plan (FCPMP); that the City had not produced any emails; and
that the production lacked internal agency communications or documents
from the City’s consultants. The letter included a long list of allegedly
omitted documents, beginning with a complaint about CEQA violations in
1989 and ending with documents created in 2020. Attorneys at the law firm
representing the City identified individuals at the City and at its engineering
consultants who might have responsive documents, gathered 750 additional
documents, some dating back to the 1980’s and 1990’s and many of which had
to be manually scanned into electronic format, and produced them on

adopting a definition of microplastics in drinking water; and the State Water
Resources Control Board’s notice of a November 2021 public workshop and
invitation to comment on proposed standardized methods for testing
microplastics in drinking water. None of these materials was before the City
when it made its decision so, like the trial court, we deny the request for
judicial notice. (See Porterville Citizens for Responsible Hillside Development
v. City of Porterville (2007) 157 Cal.App.4th 885, 890.)

34
January 29, 2021. In its memorandum of costs, the City did not seek the
costs it incurred through January 2021.
Unsatisfied, appellants wrote again on February 19, 2021, asking that
some of the documents be produced again in a different electronic format and
asserting that the production of correspondence and internal communications
was incomplete. They provided a list of more than 200 omitted documents,
comprised of a letter from 1992, a few letters from 2000, and email
correspondence from 2009 to 2020 (some of which were equally available to
appellants, for instance because their counsel was the recipient of a requested
email). Appellants also included a list of further categories of documents to
be produced, including comments on environmental documents from 2000
and 2016, and correspondence related to a 2013 grand jury report on the
delay in closing the landfill.
Attorney Kathryn Patterson, an associate with the law firm retained by
the City, worked with City employees and EBA engineering to gather as
many of the requested documents as possible, including attachments to
emails, then requested further documents from the Regional Board,
CalRecycle, and the County of Mendocino Local Enforcement Agency. Where
these agencies had large volumes of paper records, Patterson or a city
attorney travelled to the agency to review files in person. Some of these
agencies indicated that appellants had already requested and obtained from
them records related to the landfill, including more than 100 attachments to
emails included in appellants’ document request to the City.
The City produced additional documents on June 2, 2021, explaining as
it did so that its initial production had been guided by two general principles:
first, that the “[r]elevant [t]imeframe” for the project was the time falling
between the issuance of the notice of preparation of the EIR in February 2017

35
and the date it filed its notice of determination in August 2020; and second,
that documents outside that timeframe should be related to the subject
matter of the complaint. It took the position that many of the documents
appellants sought were irrelevant to the action, and it reminded appellants of
their statutory duty to prepare the record at a reasonable cost. (§ 21167.6,
subd. (f).) Nevertheless, the City explained, it was complying with the
requests in appellants’ meet and confer letter.
This process was repeated several more times before the administrative
record was finally complete, as Patterson explained in declarations filed in
support of the memorandum of costs. Patterson and City staff expended
considerable time trying to locate the documents appellants requested in
their successive meet and confer letters, sometimes finding that the
documents had already been produced. Appellants had requested that the
City produce attachments to emails already produced, apparently because
they had not acquired software that would allow them to open the
attachments as originally produced. To facilitate the search for these
attachments within its system, the City asked appellants to provide the
underlying emails, but appellants long failed to do so.
In March 2022, counsel for appellants provided a draft administrative
record, but only some of the documents had hyperlinks and none of the
hyperlinks worked, so the City engaged a vendor to hyperlink the documents
itself. The administrative record was certified on May 4, 2022.
After the trial court denied the petition for writ of mandate, the City
filed a memorandum of costs seeking to recover $76,056.31. The bulk of that
amount—more than $73,000—represented legal fees for the time Patterson
spent responding to appellants’ requests, coordinating with other agencies,
seeking documents, and compiling them for the administrative record.

36
Appellants moved to tax costs, contending the City was not entitled to
recover for the time its attorneys spent on record preparation activities, and
arguing the reason for the prolonged meet and confer process was that the
City had not kept organized and comprehensive records about the landfill
closure and its document productions were incomplete and unorganized. In
response, the City provided a supplemental declaration by Patterson,
accompanied by a thumb drive showing the format in which the documents
had been provided to appellants throughout the process.
The trial court denied the motion to tax costs. In doing so, it expressly
accepted Patterson’s summary of events. The court found that appellants
“essentially shifted to the City the responsibility to assemble the record and
violated their duty to keep record preparation to a reasonable cost,” for
instance by asking the City to produce documents in the possession of third
parties, although appellants had already requested the documents from the
same third parties; by refusing to acquire and use software that would give
them electronic access to records provided; by demanding documents that had
already been produced; and by making requests that were overbroad, vague,
and non-specific. After reviewing the billing records and meet and confer
letters, the trial court concluded that the amount the City sought was
reasonable and that the work required the involvement of someone with
Patterson’s background and experience.
Ruling on appellants’ motion for a new trial on costs, the trial court
expanded on this reasoning. The court clarified that its decision was not
based on a finding that certain documents should not have been included in
the record, but on its finding that the City was entitled to recover reasonable
and necessary costs for record preparation, since appellants had
“substantially failed in their duty to control the costs of record preparation”

37
by insisting that the City locate and retrieve documents that “were decades
old,” “of attenuated relevance,” and/or previously produced to appellants. The
court also found that Patterson’s costs declaration (and the court’s order) had
“separated record preparation tasks and associated costs from other aspects
of representing the City” and did not include reimbursement for “time related
to ‘research and analysis of legal issues’ and other entries.”
B. General Legal Standards
CEQA normally requires a plaintiff to ask the respondent public agency
to prepare the administrative record (§ 21167.6, subd. (a)), and provides that
“[t]he parties shall pay any reasonable costs or fees” connected to record
preparation “in conformance with any law or rule of court” (§ 21167.6,
subd. (b)(1)(A)). However, the plaintiff has the option to prepare the
administrative record itself. (§ 21167.6, subd. (b)(2).) The party preparing
the record “shall strive to do so at reasonable cost in light of the scope of the
record of proceedings.” (§ 21167.6, subd. (f).)
Under CEQA, the administrative record must include certain items.
(§ 21167.6, subd. (e).) Among them are project application materials; staff
reports prepared by the agency with respect to its compliance with CEQA and
“the action on the project”; written comments received in connection with
environmental documents prepared for the project; written evidence or
correspondence to and from the agency with respect to the project and CEQA
compliance; documentation of the agency’s final decision (such as the final
EIR) and all documents cited or relied on in the findings; and any other
written materials relevant to the agency’s compliance with CEQA or to its
decision on the merits of the project, including copies of studies or other
documents relied upon in any environmental document prepared for the
project that was either available to the public or included in the agency’s files

38
on the project, and “all internal agency communications, including staff notes
and memoranda related to the project or to compliance with [CEQA],” with
certain exceptions. (§ 21167.6, subd. (e).) However, the parties may agree to
use “a partial record of proceedings that does not contain all the documents
listed in subdivision (e) if approved by the court.” (§ 21167.6, subd. (b)(1)(B).)
As a general rule in civil litigation, the prevailing party may recover
reasonable costs. (St. Vincent’s School for Boys, Catholic Charities CYO v.
City of San Rafael (2008) 161 Cal.App.4th 989, 1013–1014 (St. Vincent’s
School), citing Code Civ. Proc., § 1032, subd. (b).)11 In a CEQA action, those
costs may include reasonable labor costs to compile the record. (California
Oak Foundation v. Regents of University of California (2010) 188 Cal.App.4th
227, 293–295 (California Oak) [paralegal time]; River Valley Preservation
Project v. Metropolitan Transit Development Bd. (1995) 37 Cal.App.4th 154,
180–182 [paralegal and engineer with specialized knowledge].) An agency
may be entitled to recover its costs even when the petitioner elected to
prepare the administrative record, if its costs were incurred due to the
petitioner’s failure to comply with the statutory obligation to prepare the
record at a reasonable cost. (St. Vincent’s School, at pp. 1017, 1019.)
However, it may not recover for such routine items as the time to review for
completeness an administrative record prepared by a petitioner. (Coalition

11 The petition for writ of mandate refers to both section 1085

(traditional mandate) and 1094.5 (administrative mandamus) of the Code of
Civil Procedure. In a traditional mandate action, the prevailing party is
entitled to its costs. (Wagner Farms, Inc. v. Modesto Irrigation Dist. (2006)
145 Cal.App.4th 765, 773 (Wagner Farms), citing Code Civ. Proc., § 1032,
subd. (b).) In an administrative mandamus action, “[e]xcept when otherwise
prescribed by statute, the cost of preparing the record shall be borne by the
petitioner.” (See Code of Civil Proc. §§ 1094.5, subd. (a); 1094.6, subd. (c).)
Regardless of the appropriate form of this action, there is no dispute that the
City is entitled to its reasonable costs.

39
for Adequate Review v. City and County of San Francisco (2014) 229
Cal.App.4th 1043, 1059 (Coalition for Adequate Review).)
When we review a cost order, our standard of review varies according
to the issue. If the question is whether a claimed cost falls within the general
cost statutes and is recoverable at all, our review is de novo. (Coalition for
Adequate Review, supra, 229 Cal.App.4th at pp. 1050–1051.) Likewise, we
review de novo the interpretation of CEQA’s record preparation provisions.
(Ibid.; Yolo Land & Water Defense v. County of Yolo (2024) 105 Cal.App.5th
710, 715 (Yolo Land & Water Defense).) However, we review for abuse of
discretion whether a claimed cost to prepare the administrative was
necessary and reasonable. (Coalition for Adequate Review, at pp. 1050–
1051.) We find an abuse of discretion only if the court “ ‘ “exceeds the bounds
of reason, all of the circumstances being considered.” ’ ” (California Oak,
supra, 188 Cal.App.4th at p. 294.)
C. Analysis
Appellants contend the trial court erred in awarding fees for
Patterson’s time as an item of costs.
In certain circumstances, an agency may recover the costs of time spent
responding to the demands of a petitioner that elected to prepare the record.
This principle was explained in St. Vincent’s School. There, the petitioner
elected to prepare the administrative record, and in the course of doing so
imposed “extraordinary costs” on the respondent city. (St. Vincent’s School,
supra, 161 Cal.App.4th at p. 1014.) The city initially turned over 20 boxes of
documents to the petitioner. Noting that the production included only a few
emails, the petitioner submitted a Public Records Act request for all writings
stored electronically that reflected communications regarding the two
properties at issue in the CEQA action. (Id. at p. 1017.) The city was forced

40
to review nine boxes’ worth of emails for responsiveness. (Ibid.) Dissatisfied
with the small size of the resulting production of responsive, nonprivileged
emails, the petitioner served a demand for inspection listing 15 further
demands for documents. (Id. at p. 1018.)
This record, the appellate court concluded, “reflect[ed] a total disregard
for cost containment on [the petitioner’s] part, and a complete abandonment
of its statutory duty to ‘strive to [prepare the record] at reasonable cost.’ ”
(St. Vincent’s School, supra, 161 Cal.App.4th at p. 1018.) That is, after the
city produced 20 boxes of documents, the plaintiff “subjected [it] to a costly
and lengthy process of trawling through its entire computer system in
response to an extremely broad and unbounded search,” not because it had
identified any gaps in the initial production but because it was not satisfied
with the number of emails therein. (Ibid.) And the petitioner did not
mention even a single later-provided email that bolstered any of its claims;
indeed, it filed its brief before the issue of the emails was resolved. (Id. at
p. 1019.) The trial court thus did not abuse its discretion in awarding
information technology fees of more than $26,000. (Ibid.)12

12 Recently, the court in Yolo Land & Water Defense applied the same

rule to affirm an order awarding costs that included staff and consultant
time. The petitioner there elected to prepare the administrative record and
asked respondent county to produce the necessary documents. (Yolo Land &
Water Defense, supra, 105 Cal.App.5th at p. 715.) After the county prevailed
in the writ proceeding, it sought and was awarded its costs associated with
preparing the voluminous record. (Id. at pp. 714, 716.) The appellate court
explained, in upholding the order awarding costs, “That appellants elected to
prepare the record under section 21167.6, subdivision (b)(2) did not mean the
County had no costs associated with preparation of the administrative record,
and it did not preclude an award of record preparation costs to the County.”
(Id. at p. 715.)

41
Allowable “costs or fees” in a CEQA case (§ 21167.6, subd. (b)(1)) may
also include reasonable attorney time spent on record preparation. For
example, in The Otay Ranch, L.P. v. County of San Diego (2014) 230
Cal.App.4th 60 (Otay Ranch), the court upheld an award that included
compensation for the time a county’s retained counsel and paralegals spent to
prepare the administrative record. (Id. at p. 67.) The petitioner there elected
to prepare the record, but after months of inaction the county undertook to do
so itself. (Id. at p. 70.) The appellate court explained that, “[g]iven the
history and complexity of the project and how the documents were
maintained, we cannot conclude the trial court exceeded the bounds of reason
in determining it was ‘reasonably necessary’ for the County’s retained
counsel and paralegals to prepare the administrative record since the County
‘did not have the resources or experienced personnel to prepare the [r]ecord.’ ”
(Ibid.)
The court rejected a contention that this was an improper award of
attorney fees, concluding, “Under the particular circumstances of this case
where the trial court found it was reasonably necessary for the County to
incur attorney and paralegal labor costs to prepare the administrative record
within a short window of time, we see no reason to differentiate between
those actual labor costs and actual labor costs for agency staff and document
clerks to prepare an administrative record. Nor do we see a reason to
differentiate between labor costs incurred by individuals directly employed by
a public agency and those incurred by individuals employed by a private law
firm retained by the agency, so long as the trial court determines, as it did
here, the labor costs were reasonably and necessarily incurred for
preparation of the administrative record.” (Otay Ranch, supra, 230
Cal.App.4th at p. 70.) The county in that case was not seeking its attorney

42
fees for defending the action, but merely to recover the costs it actually
incurred in preparing the record, which were properly recoverable. (Id. at
p. 71.)
Two years later, the court in No Toxic Air, Inc. v. Lehigh Southwest
Cement Co. (2016) 1 Cal.App.5th 1136, followed Otay Ranch to uphold an
award of costs that included fees for paralegal and attorney time. The
plaintiff there brought a petition for writ of mandate challenging a county’s
resolution finding that a surface mining operation owned by Lehigh
Southwest Cement Co. (Lehigh) was a legal nonconforming use. (Id. at
pp. 1137–1138.) After the trial court denied the writ petition and entered
judgment in favor of the county and Lehigh, Lehigh sought the costs it
incurred in preparing the administrative record, including labor costs of
attorneys and paralegals. (Id. at pp. 1139–1140.) The trial court granted the
plaintiff’s motion to tax those costs (id. at p. 1140), and the appellate court
reversed (id. at p. 1143). Looking to what it described as “parallel [CEQA]
case law,” the court explained that the rationale of Otay Ranch was equally
applicable to the case before it. (Id. at pp. 1141–1142.) It concluded the labor
costs for attorneys and paralegals should be treated no differently from other
labor costs to create an administrative record, and it also noted that the trial
court had found those costs reasonable and appropriate to the size and
complexity of the record. (Id. at p. 1142.)
Faced with this authority, appellants make two primary contentions:
that the time Patterson spent on unearthing documents and other tasks
related to the administrative record does not fall within the scope of
allowable costs as a matter of law; and that the costs awarded were not
reasonably necessary to the litigation.

43
For their first argument, appellants rely in part on two
unexceptionable principles: that a public agency may not seek costs for
reviewing an administrative record prepared by a petitioner “ ‘for
completeness’ ” in connection with certification (see Coalition for Adequate
Review, supra, 229 Cal.App.4th at p. 1059), and that there is no basis in this
case for an award of attorney fees incurred in defending an action (see Code
Civ. Proc., §§ 1021, 1033.5, subd. (a)(10); see also Wagner Farms, supra, 145
Cal.App.4th at p. 779 [costs not recoverable for time that went beyond scope
of record preparation]). But Patterson’s declaration states that the only fees
the City sought to recover for her time were based on her record preparation
efforts, and the costs the City sought excluded the time she spent in her
review of the draft administrative record for completeness.
Appellants argue that certain specific items on Patterson’s invoices,
such as drafting meet and confer letters, researching legal requirements for
document production, and reviewing documents, constituted normal attorney
activities to defend the case and were not recoverable. These specific
challenges, which appellants make for the first time on appeal and to which
the City had no opportunity to respond in the trial court, are forfeited.13 (See
Thompson v. County of Los Angeles (2022) 85 Cal.App.5th 376, 379, 382
[party who moved to tax expert witness fees as cost could not raise on appeal
new ground to challenge that cost]; Staples v. Hoefke (1987) 189 Cal.App.3d
1397, 1409 [grounds not stated in motion to tax costs are waived]; see also
Premier Medical Management Systems, Inc. v. California Ins. Guarantee

13 The trial court explained that appellants’ moving papers included no

specific challenges to cost items. In their reply brief below, they made
references to a few of Patterson’s billing entries to show the delay in
certifying the record was not due to their “ ‘fishing expeditions,’ ” but they did
not raise the challenges they now make on appeal.

44
Assn. (2008) 163 Cal.App.4th 550, 564 [forfeiture of specific challenges to
attorney fee award where challenger did not make claims about specific
charges].) For the same reason, we reject appellants’ more general claim that
the trial court erred in failing to comb the record to distinguish attorney time
for record preparation and time spent on normal defense activities. In any
event, appellants have not shown the claimed costs exceeded permissible
boundaries.
Appellants also argue that the cost order violates the rule that an
agency may generally not claim costs for the time spent reviewing and
producing documents for an administrative record. (See Coalition for
Adequate Review, supra, 229 Cal.App.4th at pp. 1060–1061 [upholding trial
court’s denial of recovery for staff time based on finding petitioners did not
abandon duty to contain costs].) This argument might have more force if the
City had sought its costs for Patterson’s time preparing the first two
document productions, but it did not. It claimed costs for her time only after
the second meet and confer letter in February 2019, when appellants asked
the City to procure documents previously made available to them, of
attenuated relevance, or in the possession of other public agencies. Patterson
detailed the extensive efforts she made to respond to appellants’ requests,
and the trial court expressly accepted her version of events. The trial court
found that by these events, appellants “essentially shifted to the City the
responsibility to assemble the record and violated their duty to keep record
preparation to a reasonable cost.” We understand that appellants disagree,
but on the record before us we cannot say this finding was outside the court’s
discretion.
Appellants protest that the City’s initial productions were incomplete,
that some of the older documents they sought were relevant to the feasibility

45
of a clay cover alternative, and that the communications they sought between
the City and other agencies were properly part of the record. They also argue
that the City relied on (and the trial court accepted) an artificially constricted
view of the scope of an administrative record as limited to materials
postdating the February 2017 notice of preparation of the EIR. (See County
of Orange v. Superior Court (2003) 113 Cal.App.4th 1, 7–8 [administrative
record includes “pretty much everything that ever came near a proposed
development” or to CEQA compliance]; accord, Madera Oversight Coalition,
Inc. v. County of Madera (2011) 199 Cal.App.4th 48, 63–64, overruled on
another ground in Neighbors for Smart Rail v. Exposition Metro Line
Construction Authority (2013) 57 Cal.4th 439, 457; § 21167.6, subd. (e)(10).)
We are not persuaded. Although the City took the position that the
“[r]elevant [t]imeframe” for the production generally began with the notice of
preparation, it also recognized that documents outside that period were
properly part of the record if related to the subject matter of the complaint.
And in spite of its expressed concern that appellants were not preparing the
record at reasonable cost, the City complied with appellants’ requests, and it
in fact produced many documents predating the notice of preparation in
response to appellants’ original meet and confer letter. And none of this
undermines the trial court’s finding that appellants abrogated their duty to
keep record preparation to a reasonable cost, demanded documents to which
it already had access through other agencies, and made duplicative document
requests.
DISPOSITION
The judgment and the order denying appellants’ motion to tax costs are
affirmed.

46
TUCHER, P.J.

WE CONCUR:

PETROU, J.
RODRÍGUEZ, J.

Russian Riverkeeper et al. v. City of Ukiah et al. (A168090/A169390)

47