Questione giuridica chiave
Whether the building project had a legally sufficient access right under § 53 KBR
Decisione estratta
The submitted servitude documents sufficiently showed a legally secured access right for the planned development.
Motivazione estratta
The court held that the wording and context of the easement documents indicated that future development of the benefited land was contemplated and that use of the private road for the planned houses remained within the original servitude purpose; any contrary interpretation was unlikely and not decisive for the permit stage.