Questione giuridica chiave
Whether the cantonal court arbitrarily found that the builder had not shown extra orders or unforeseen additional works justifying the claimed lien amount.
Decisione estratta
The cantonal court's factual assessment was arbitrary; testimony showed an agreed CHF 30,000 overrun and other additional costs, so the matter required further examination.
Motivazione estratta
The record contained evidence of agreed cost overruns, owner-requested modifications, and separate scaffold costs; the lower court could not dismiss additional work without fuller analysis.