Questione giuridica chiave
Whether default interest could be added to the burden schedule in the load-rectification action although it had not been entered in the schedule.
Decisione estratta
No. The load-rectification action can only determine burdens already entered in the burden schedule; a missing default-interest claim cannot be added later.
Motivazione estratta
The proceeding is limited to listed and disputed burdens. Since no default interest had been registered when the schedule was drawn up, there was no legal basis to order its later inclusion.