Questione giuridica chiave
Whether the fax of 6 October 1995 was superseded by later agreements or conduct
Decisione estratta
The alleged later agreements were not established; the fax remained binding.
Motivazione estratta
The appellant's arguments attacked factual findings and were inadmissible in reform proceedings; no later agreement proven, and the advance payment through the general contractor did not discharge the original commitment.