Texas Association of School Boards Risk Management Fund // Southwest Texas Junior College v. Southwest Texas Junior College // Cross-Appellee, Texas Association of School Boards Risk Management Fund

CourtListener 10691066Txctapp152 oct. 2025

Texte intégral

ACCEPTED
15-25-00134-CV
FIFTEENTH COURT OF APPEALS
AUSTIN, TEXAS
10/2/2025 5:01 PM
No. 15-25-00134-CV CHRISTOPHER A. PRINE
CLERK
FILED IN
IN THE FIFTHTEENTH COURT OF APPEALS OF
15thTEXAS
COURT OF APPEALS
AUSTIN, TEXAS
10/2/2025 5:01:21 PM
CHRISTOPHER A. PRINE
TEXAS ASSOCIATION OF SCHOOL BOARDS RISK MANAGEMENT Clerk
FUND
Appellant/Cross-Appellee

vs.

SOUTHWEST TEXAS JUNIOR COLLEGE
Appellee/Cross-Appellant

Appeal from the 38th Judicial District Court
Uvalde County, Texas, No. 2023-11-35269-CV
The Honorable Kelley T. Kimble, Presiding Judge

APPELLEE/CROSS APPELLANT’S BRIEF

Preston J. Dugas III
State Bar No. 24050189
pdugas@dcclawfirm.com
Vincent P. Circelli
State Bar No. 24058804
vcircelli@dcclawfirm.com
Andrew D. Spadoni
State Bar No. 24109198
aspadoni@dcclawfirm.com
DUGAS & CIRCELLI, PLLC
4800 Bryant Irvin Ct.
Fort Worth, Texas 76107
Telephone: (817) 817-7000
Facsimile: (682) 219-0761
ATTORNEYS FOR APPELLEE
IDENTITIES OF PARTIES AND COUNSEL

Appellant: Jack W. Higdon (Trial and
Appellate)
Texas Association of School Boards State Bar No. 24007360
Risk Management Fund jack.higdon@blankrome.com
Barry Abrams (Appellate)
State Bar No. 00822700
barry.abrams@blankrome.com
Joshua A. Huber (Appellate)
State Bar No. 24065457
josh.huber@blankrome.com
Gregory J. Moore (Trial)
State Bar No. 24055999
greg.moore@blankrome.com
Christopher W. Caudill (Trial)
State Bar No. 24104717
christopher.caudill@blankrome.com

BLANK ROME LLP
717 Texas Avenue, Suite 1400
Houston, Texas 77002-2727

Clarissa M. Rodriguez
State Bar No. 24056222
cmrodriguez@rampagelaw.com
Lori Hanson
State Bar No. 21128500
lwhanson@rampagelaw.com

DENTON NAVARRO RODRIGUEZ
BERNAL SANTEE & ZECH, P.C.
2517 N. Main Avenue
San Antonio, Texas 78212

i
Appellee: Counsel:

Southwest Texas Junior College Preston J. Dugas III
State Bar No. 24050189
pdugas@dcclawfirm.com
Vincent P. Circelli
State Bar No. 24058804
vcircelli@dcclawfirm.com
Andrew D. Spadoni
State Bar No. 24109198
aspadoni@dcclawfirm.com

DUGAS & CIRCELLI, PLLC
4800 Bryant Irvin Ct.
Fort Worth, Texas 76107
Telephone: (817) 817-7000
Facsimile: (682) 219-0761

ii
TABLE OF CONTENTS

TABLE OF AUTHORITIES ................................................................................... iv
I. STATEMENT OF THE CASE .............................................................................2

II. THE RECORD .....................................................................................................4

III. ISSUES PRESENTED........................................................................................5
IV. STATEMENT OF FACTS .................................................................................6

V. SUMMARY OF THE ARGUMENTS ..............................................................10

VI. STANDARD OF REVIEW ..............................................................................13
VII. ARGUMENTS & AUTHORITIES ................................................................15

A. The College’s Breach of Contract Claim Falls within the waiver
of Immunity for State Contracts allowing recovery pursuant to
the statute. ..................................................................................................15
B. The College’s sole cause of action before the District Court was
the College’s breach of contract claim for which immunity has
been waived. ..............................................................................................18
C. Delay damages sought by the College are explicitly allowed
under the Act. .............................................................................................20
1. The Statute expressly allows for delay damages. ................................21
2. “Owner-caused delays” encompass TASB’s actions..........................23

D. Zachry only disagreed with City of Mesquite to the extent it
allowed damages not waived under the statute; but Zachry still
permits claims for increased construction costs due to delay. ..................25

CONCLUSON & PRAYER ....................................................................................32

CERTIFICATE OF COMPLIANCE .......................................................................34
CERTIFICATE OF SERVICE ................................................................................35

APPENDIX ..............................................................................................................37

iii
TABLE OF AUTHORITIES

Cases
Alamo Heights Indep. Sch. Dist. v. Clark, 544 S.W.3d 755 (Tex. 2018) ................14

Baylor Cnty. Special Util. Dist. v. City of Seymour, 709 S.W.3d 5 (Tex.
App.—Eastland 2025, pet. filed) ............................................................ 13, 14

Ben Bolt-Palito Blanco Consol. Indep. Sch. Dist. v. Tex. Political Subdivisions
Prop./Casualty Joint Self-Insurance Fund, 212 S.W.3d 320 (Tex. 2006)
................................................................................................................ 16, 17
City of Corpus Christi v. Graham Constr. Services, Inc., No. 13-19-00367-
CV, 2020 WL 3478661 (Tex. App.—Corpus Christi–Edinburg June 25,
2020, pet. denied) ....................................................................... 23, 24, 25, 30

City of Mesquite v. PKG Contracting, Inc., 263 S.W.3d 444 (Tex. App.—
Dallas 2008, pet. denied) ...............................................................................30
Garland Indep. Sch. Dist. v. Reeder Gen. Contractors, Inc., No. 05-22-00855-
CV, 2024 WL 1208304 (Tex. App.—Dallas Mar. 21, 2024, pet. denied)
.......................................................................................................................11

Primestar Constr., Inc. v. City of Dallas, No. 05-17-01447-CV, 2019 WL
1033978 (Tex. App.—Dallas Mar. 5, 2019, pet. denied) ..............................32
San Antonio River Auth. v. Austin Bridge & Rd., L.P., 601 S.W.3d 616 (Tex.
2020) ..............................................................................................................32
Tex. Ass'n of Sch. Boards Risk Mgmt. Fund v. Colorado Indep. Sch. Dist., 660
S.W.3d 767 (Tex. App.—Eastland 2023, no pet.)................................. passim

Tex. Ass'n of Sch. Boards Risk Mgmt. Fund v. Greenville Indep. Sch. Dist.,
No. 05-21-01012-CV, 2022 WL 2816532 (Tex. App.—Dallas July 19,
2022, pet. denied) ..........................................................................................14

Tex. Dep't of Parks & Wildlife v. Miranda, 133 S.W.3d 217 (Tex. 2004) . 13, 15, 25

Tex. Natural Res. Conservation Comm'n v. ITDavy, 74 S.W.3d 849 (Tex.
2002) ..............................................................................................................14

iv
Statutes

Tex. Loc. Gov’t Code § 271.152 .................................................................. 7, 16, 27
Tex. Loc. Gov’t Code § 271.153 .........................................................................9, 21

v
STATEMENT REGARDING ORAL ARGUMENT

Appellee/Cross-Appellant respectfully states oral argument is unnecessary

pursuant to Rule 39.1(b)-(d) and will not aid the Court for the following reasons:

(1) The facts and legal arguments are adequately presented in the briefs and
record.

(2) The decisional process would not be significantly aided by oral
argument given the clear mandate from the Legislature.

1
I.

STATEMENT OF THE CASE

Nature of the Case: This interlocutory appeal arises out of the partial
granting of a partial plea to the jurisdiction presented
by an intergovernmental self-insurance risk pool,
Texas Association of School Boards Risk
Management Fund (hereinafter “TASB” or “the
Fund”). The case concerns TASB’s breach of
contract for failure to pay amounts due to repair
property damage of Southwest Texas Junior College
(“SWTJC” or “the College”) under a property
coverage agreement that functions similar to an
insurance contract. Because of TASB’s failure to
comply with the Policy in paying the amount owed
for covered property damages, the College filed a
breach of contract action against TASB asking for
actual damages, attorney’s fees, and consequential
delay damages for the increased cost of construction
due to the delayed payment due under the Policy.

Procedure of the Case: The College sued TASB on November 17, 2023.
TASB asserted its governmental immunity from suit
in a partial plea to the jurisdiction on June 13, 2025
(“Jurisdictional Plea”). CR 31.

The College responded to TASB’s Jurisdictional
Plea on July 15, 2025. The trial court held a hearing
on TASB’s Jurisdictional Plea and the College’s MSJ
on July 21, 2025. The trial court partially denied and
partially granted TASB’s partial plea to the
jurisdiction in an order signed on July, 30 2025.
Supp. CR 3–4.

2
Trial Court: The 38th Judicial District Court of Uvalde County,
Texas, Honorable Kelley T. Kimble, Presiding
Judge. The underlying cause of cause is docketed by
the District Court as Cause No. 2023-11-35269-CV.

Trial Court Disposition: The trial court partially denied and partially granted
TASB’s plea to the jurisdiction in an order signed on
July 29, 2025. Supp. CR 3–4.

3
II.

THE RECORD

The record consists of two sets of the Clerk’s Record, an original Clerk’s

Record and a Supplemental Clerk’s Record, containing the filings, orders and other

contents of the district court’s docket and a Reporter’s Record containing the

transcript of a hearing, both in .pdf format. Citations to the Original Clerk’s Record

will be in the form “CR{Page(s)}”. Citations to the Supplemental Clerk’s Record

will be in the form of “Supp. CR{Page(s)}”. Finally, citation to the Reporter’s

Record as “RR{Page(s)}”, where the page designations shall be to the electronic

pagination of the .pdf file for record for ease of location.

4
III.

ISSUES PRESENTED

The only issue in Appellee/cross-Appellant’s interlocutory appeal is:

Issue 1: Does the plain language of the TEX. LOC. GOV’T CODE

§§ 271.153(a)(1), (b)(1), (c) permit the College to seek consequential

“delay” damages available under Texas common law breach of contract

claims for “any amount owed as compensation for the increased cost to

perform the work as a direct result of owner-caused delays or

acceleration.”

5
IV.

STATEMENT OF FACTS

This interlocutory appeal is taken from the partial granting of a partial plea to

the jurisdiction based on the pleadings.1 When a plea to the jurisdiction challenges

only the pleadings, this Court determines “if the pleader has alleged facts that

affirmatively demonstrate the trial court’s jurisdiction to hear and decide the cause”

accepting the allegations in the pleadings as true and “liberally constru[ing] the

pleadings, accept as true all factual assertions, and look to the pleader's intent.”2

Those pleaded facts are as follows:

The College owns real property in Uvalde, Uvalde County, Texas that include

multiple buildings (the “Property”). 3 The College’s Property was insured at the time

under a coverage agreement issued by TASB that functions as a policy of insurance. 4

The policy is issued under the auspices of an interlocal agreement by which the

College became a member of TASB originally executed in August 2012.5 TASB is

a risk sharing pool among various local government subdivisions operating under

1
See CR 137–138.
2
Tex. Ass'n of Sch. Boards Risk Mgmt. Fund v. Colorado Indep. Sch. Dist., 660 S.W.3d 767, 771
(Tex. App.—Eastland 2023, no pet.).
3
CR 5.
4
See CR 6 (“TASB and Plaintiff entered into a contract” for insurance coverage for property
damaged); see also CR 9–10.
5
CR 6; see also CR 56–60.

6
the Texas Interlocal Cooperation Act. 6

The College’s Property was hit by a significant wind and hail-storm on or

about April 28, 2021 during the coverage period with TASB. 7 The College

immediately notified TASB of the loss that same day (the “Claim”). 8 TASB assigned

a staff adjuster with TASB to administer the Claim. 9 TASB then assigned the

investigation of the Claim to a private insurance adjusting company and others to

adjust the claim on TASB’s behalf.10

TASB purported to investigate the Claim but ultimately determined the

majority of the College’s Property was not damaged as a result of the hail storm.11

Following TASB’s decision the College sued TASB on November 17, 2023 solely

for breach of contract alleging the insurance policy was a contract that fell within

the statutory waiver of sovereign immunity that permits the prosecution of breach of

contract actions against governmental entities.12 The College’s Original Petition

asserted factual allegations describing TASB’s actions and conduct that gave rise to

6
CR 56–60; CR 31–32 (admitting the “Fund” or TASB is “a governmental unit formed under the
Texas Interlocal Cooperation Act.”).
7
CR 9–10, 31.
8
CR 10.
9
See CR 10.
10
CR 10.
11
CR 11–12.
12
CR 12–13; see TEX. LOC. GOV’T CODE § 271.152.

7
the College’s breach of contract cause of action. 13

The College also alleged that due to TASB’s actions in failing to pay even

close to the proper amount of owed for damages, that the College was excused from

performing certain conditions under the Policy and that TASB even waived various

other requirements for alleged conditions for payment of the coverage benefits under

the insurance policy. 14 The College also alleged in its Original Petition that “[a]ll

conditions precedent required under the Agreement and law [had] been performed”

or that TASB had “excused [and] waived” conditions precedent in support of the

College’s breach of contract claim, and as a defense to TASB’s likely affirmative

defense of unsatisfied conditions precedent. 15

Ultimately, the College filed suit against TASB asserting breach of contract

as its sole cause of action against TASB.16 The College sought actual damages for

the breach (consisting of unpaid coverage benefits owed under the insurance policy,

attorney’s fees and interest).17 In addition, the College also sought consequential

“delay” damages for the “increased costs of construction and other related

consequential damages” due to TASB’s breach of the contract and delay in paying

13
CR 8–13.
14
See CR 11 at ¶30–31.
15
CR 20 at ¶83.
16
CR 12–13.
17
CR 12–13.

8
the amount of damages owed to the College under the Policy as well as its improper

actions. 18 Specifically, the College alleged that TASB’s conduct in woefully

underestimating the amount of the loss and refusal to recognize and pay the full

amount of the damages owed under the Claim caused a substantial delay that resulted

in the College’s actual damages significantly increasing over time due to the

increased costs of materials and labor.19

As a result of TASB’s delays and breach of its contract with the College, the

College is seeking damages expressly permitted under Section 271.153 of the

Texas Local Government Code (allowing for recovery of consequential damages

“for the increased cost to perform the work as a direct result of owner-caused delays

. . . .”). 20 This is exactly what the College pled and seeks as part of its damages model

— “consequential damages (related to Plaintiff’s inability to make necessary repairs,

increased costs of construction and other related consequential damages)”.21 The

damages the College seeks is directly related to TASB’s delays as the owner and

manager of the Fund and the increase in the cost of construction that was caused by

those delays.22

18
CR 11–12 at ¶¶34, 38–42.
19
CR 11 at ¶¶30–34.
20
See TEX. LOC. GOV’T CODE § 271.153(a)(1).
21
CR 11 at ¶34.
22
See id.

9
The 38th District Court found that the College’s breach of contract claim did

fall within the statute’s waiver of immunity, that the factual allegations and defenses

went to the merits of the College’s breach of contract claim and were encompassed

within the statute’s waiver. 23 However, the trial court denied the College’s right to

consequential damages expressly allowed under Section 271.153 which this Court

should correct and clarify that the consequential damages asserted in this lawsuit and

as recognized as delay damages by statute are permitted under the law.24

V.

SUMMARY OF THE ARGUMENTS

Texas courts repeatedly acknowledge plaintiffs may pursue consequential

damages for owner-caused delays in breach of contract suits against political

subdivisions where the ultimate liability of the entity under the contract is in dispute:

• “Subsections (a)(1) and (b) [of section 271.153] allow recovery of contract
damages, including delay damages… .”

o Zachry Const. Corp. v. Port of Houston Auth. of Harris Cnty., 449 S.W.3d
98, 112 (Tex. 2014) (emphasis added).

• “Reeder requested damages recoverable under § 271.153 because it sought . . .
amounts for increased costs resulting from District-caused delays . . . , at this
stage, Reeder has pleaded damages recoverable under § 271.153, and we do not
here address whether it will be able to recover those damages” against the
ultimate liability arguments.

23
See CR 137–138.
24
See CR 137.

10
o See Garland Indep. Sch. Dist. v. Reeder Gen. Contractors, Inc., No. 05-
22-00855-CV, 2024 WL 1208304, at *7–8 (Tex. App.—Dallas Mar.
21, 2024, pet. denied).

• “We cannot say on this record that PKG’s claim for damages is solely for
damages excluded by the statute.”

o City of Mesquite v. PKG Contracting, Inc., 263 S.W.3d 444, 448 (Tex.
App.—Dallas 2008, pet. denied) (emphasis added).
The College has asserted one cause of action against TASB — Breach of

Contract. On this cause of action alone the College seeks to hold TASB accountable

for its failure to comply with its obligations, representations, and promises pursuant

to the Interlocal Participation Agreement and Property Coverage Agreement (the

“Agreements”).25 Pursuant to the Agreements, TASB promised to pay for the

amount of the “Direct Physical Loss (Loss) to Covered Property” that is in excess of

all applicable deductibles and within the limits of coverage.26

TASB purported to investigate the College’s Claim for a lengthy period of

time before ultimately denying the overwhelming majority of the College’s claim

for covered damages, and this massive delay increased the College’s breach of

contract damages.27 As a result, the College was forced to file its lawsuit against

25
CR 6 at ¶3; CR 8–13; see generally CR 56–102 (Coverage Agreements).
26
CR 12 at ¶37; CR 61 (“PROPERTY Risk of Direct Physical Loss to Buildings, Personal
Property, and Other Structures”); CR 67 (“[T]he Fund agrees to pay the Fund Member over any
deductible for Direct Physical Loss (Loss) to Covered Property.”).
27
CR 10–12.

11
TASB for breach of contract to recover the benefits owed pursuant to the Policy.28

In doing so, the College made factual allegations and assertions that TASB’s failure

to pay the amount owed pursuant to the contract has resulted in damages that were

a direct and foreseeable consequences of the breach, such as the increased costs for

construction to repair the covered damages under the Agreement. As a result, the

College plead that it was seeking consequential damages based on TASB’s delays,

including for these “increased costs of construction.” 29

Here, the statutory language clearly allows for the recovery of consequential

damages as “Subsections (a)(1) and (b) [of section 271.153] allow recovery of

contract damages, including delay damages… .” Zachry Const. Corp. v. Port of

Houston Auth. of Harris Cnty., 449 S.W.3d 98, 114–15 (Tex. 2014) (emphasis

added). Plaintiff has made a claim for contract damages, and this necessarily

includes delay damages that immediately precede the statutory grant. It is undisputed

that Plaintiff’s contract damages are viable, and therefore the inclusion of delay

damages is not an expansion of the claim but rather the precise type of remedy the

Legislature contemplated and authorized. At worst Plaintiff has presented clear

evidence that its pleadings seek delay damages that the Texas legislature has

specifically permitted recovery for, and at best, Plaintiff has established that delay

28
CR 12–13.
29
CR 11 at ¶34.

12
damages are inseparable from the contract damages claim itself and thus recoverable

as a matter of law.

In summary, the College has alleged and shown that the College is seeking

delay damages due to Defendant’s failure to abide by the contract and failure to

timely pay the College’s damages claims. The Texas legislature included explicit

language allowing for the recovery of delay damages under the Act and as such, the

College is entitled to present evidence and recover these damages as permitted under

the Act.

VI.

STANDARD OF REVIEW

Sovereign immunity from suit defeats a trial court’s subject matter jurisdiction

and thus is properly asserted in a plea to the jurisdiction.30 “The purpose of a plea to

the jurisdiction is to defeat a pleaded cause of action without reaching the merits.”31

“A plea to the jurisdiction can take two forms: (1) a challenge to the plaintiff's

pleadings regarding the allegations of jurisdictional facts or (2) an evidentiary

challenge to the existence of jurisdictional facts.”32

“When the plea only challenges the plaintiff’s pleadings, as in the case [here],

30
See Tex. Dep’t of Parks & Wildlife v. Miranda, 133 S.W.3d 217, 225–226 (Tex. 2004).
31
See Colorado ISD, 660 S.W.3d 767, 771 (Tex. App.—Eastland 2023, no pet.) (emphasis added).
32
See Baylor Cnty. Special Util. Dist. v. City of Seymour, 709 S.W.3d 5, 12 (Tex. App.—Eastland
2025, pet. filed).

13
[the Court] must determine if the pleader has alleged facts that affirmatively

demonstrate the trial court’s jurisdiction to hear and decide the case.”33 Courts

review “liberally constru[ing] the pleadings, accept[ing] as true all factual assertions,

and look[ing] to the pleader’s intent.”34 If the allegations raise a fact issue then “a

trial court may not grant the plea because the fact finder must resolve the fact

issue.” 35 However, if there is no fact issue, then the trial court “will rule on the plea

as a matter of law.”36 Ultimately, whether a court has subject matter jurisdiction is a

question of law that is reviewed de novo.37

Here, TASB’s jurisdictional plea does not challenge the existence of

“jurisdictional facts” but instead challenged certain defenses and the availability of

certain breach of contract damages plead in the face of the College’s Petition.38

Because TASB did not raise an evidentiary challenge to the existence of

jurisdictional facts in its Partial Plea to the Jurisdiction, all that is before and to be

33
See Baylor Cnty. Special Util. Dist. v. City of Seymour, 709 S.W.3d 5, 12 (Tex. App.—Eastland
2025, pet. filed); see also Colorado Indep. Sch. Dist., 660 S.W.3d at 770–771 (noting TASB’s plea
to the jurisdiction was non-evidentiary challenge); Greenville ISD, 2022 WL 2816532, at *2
(same); cf. Alamo Heights Indep. Sch. Dist. v. Clark, 544 S.W.3d 755, 783 (Tex. 2018) (noting
Alamo Heights’ plea challenged jurisdictional facts by “producing evidence” challenging specific
claims by plaintiff).
34
See Colorado Indep. Sch. Dist., 660 S.W.3d at 771.
35
Id.
36
Id.
37
See Tex. Natural Res. Conservation Comm’n v. ITDavy, 74 S.W.3d 849, 855 (Tex. 2002).
38
CR 37–45 (challenging the College’s extracontractual claims, extra-contractual damages claims,
and equitable relief claims allegedly made in the College’s petition).

14
considered by this Court is to “determine if the [College] has alleged facts that

affirmatively demonstrate the trial court’s jurisdiction to hear and decide the

cause.”39

However, to the extent the trial Court’s Order granting the College’s Partial

Motion for Summary Judgment raised a jurisdictional fact issue that Appellant has

now appealed, then the proper standard for review mirrors that of a traditional

summary judgment. 40

VII.

ARGUMENTS & AUTHORITIES

A. The College’s Breach of Contract Claim Falls within the waiver of
Immunity for State Contracts allowing recovery of delay damages.

As an initial matter, the interlocal risk sharing pools like the one operated by

TASB that controls here41, and the trial court’s jurisdiction for claims by a Fund

Member of the agreement for non-payment of coverage benefits has already been

addressed by the Texas Supreme Court in Ben Bolt-Palito Blanco Consolidated

Independent School District v. Texas Political Subdivisions Property/Casualty Joint

39
See Colorado ISD, 660 S.W.3d at 771.
40
See Miranda, 133 S.W.3d at 225–26 (“[I]f the plaintiffs' factual allegations are challenged with
supporting evidence necessary to consideration of the plea to the jurisdiction, to avoid dismissal
plaintiffs must raise at least a genuine issue of material fact to overcome the challenge to the trial
court's subject matter jurisdiction.”).
41
See CR 56–66.

15
Self-Insurance Fund.42 In Ben Bolt-Palito Blanco CISD, the court held that a breach

of contract claim for payment of insurance proceeds against a self-insured interlocal

risk pool — like the one in this case — fall within the statutory waiver of sovereign

immunity at Section 271.152. 43

TASB concedes, as it now must, that immunity to the College’s breach of

contract claim and claim for actual damages are waived under Section 271.152 of

the Texas Local Government Code because the text provides a clear and

unambiguous waiver of TASB’s immunity for such claims. Id. The statute provides:

A local governmental entity that is authorized by statute or
the constitution to enter into a contract and that enters into
a contract subject to this subchapter waives sovereign
immunity to suit for the purpose of adjudicating a claim
for breach of the contract, subject to the terms and
conditions of this subchapter. 44

The Texas Supreme Court has concluded: “The statute’s plain language

allows for enforcement of contracts against local governmental entities by waiving

their immunity from suit.”45 TASB in that case tried to argue that the waiver in

Section 271.152 did not apply to self-insurance funds, but the court squarely rejected

that contention by holding:

42
See Ben Bolt-Palito Blanco Consol. Indep. Sch. Dist. v. Tex. Political Subdivisions
Prop./Casualty Joint Self-Insurance Fund, 212 S.W.3d 320 (Tex. 2006).
43
See Ben Bolt-Palito Blanco CISD, 212 S.W.3d at 323.
44
See Tex. Loc. Gov’t Code § 271.152.
45
Ben Bolt-Palito CISD, 212 S.W.3d at 327.

16
There is no indication that the Legislature intended to
exclude self-insurance fund agreements from
enforcement. While the mere act of self-insuring does not
itself constitute a waiver of immunity, see Tex. Gov’t
Code §2259.031, entering into ‘a written contract stating
the essential terms of [an] agreement for providing goods
or [insurance] services to [a] local governmental entity’
clearly does. 46

There is no doubt that this case as pled against TASB on the basis of a breach

of a written contract contains the essential terms of an agreement for providing

insurance services to a local governmental entity and is clearly stated in Plaintiff’s

Original Petition.47 Thus, without question, TASB’s immunity is waived for the

College’s breach of contract action seeking contractual damages and attorneys’ fees

under Subchapter I of Chapter 271 of the Texas Local Government Code as a matter

of law.48 TASB concedes, in an obtuse manner, that the College’s breach of contract

claim falls within the statutory waiver of sovereign immunity. 49 TASB further

confirms this by only filing a partial plea to the jurisdiction and not challenging the

College’s breach of contract claim. 50

46
Ben Bolt-Palito CISD, 212 S.W.3d at 327.
47
CR 6, at ¶3; CR at 9:¶18–10:¶20; CR 12 at ¶¶35–42; see also CR 56–66 (Interlocal Participation
Agreement); CR 67–102 (Property Coverage Agreement).
48
Colorado ISD, 660 S.W.3d at 771 (“[I]t is undisputed that the Fund is a local governmental
entity subject to the provisions of the Act, and that the self-insurance policy held by CISD as a
member of the Fund is a contract that falls under the Act’s waiver of governmental immunity.”).
See Ben Bolt-Palito Blanco CISD, 212 S.W.3d at 322–323.
49
Appellant/Cross-Appellee’s Brief at 23–24, 28.
50
See generally CR 35–43 (leaving out any challenge to the College’s breach of contract claim).

17
Therefore, to the extent that the College’s factual allegations and defenses are

in support of the College’s breach of contract claim and do not seek separate relief,

immunity has been waived.51

B. The College’s sole cause of action before the District Court was the
College’s breach of contract claim for which immunity has been waived.

The College’s sole cause of action in this lawsuit that was before the District

Court was its claim for breach of contract and the damages sought under this sole

cause of action is the College’s actual damages, attorney’s fees, allowable interest

under the law, and finally, the consequential damages allowed under section 271 for

the increased costs of construction as a result of “owner-caused delays”.

The College has never asserted a claim for non-contractual damages that

TASB complains of other than for attorney’s fees, interest allowed under the law,

and the consequential damages of the increased cost of construction that are the

result of TASB’s delay in fulfilling its obligation under the Agreement.52 For

example, the College never pled as a separate claim or sought relief for fraud and

has never sought “exemplary, and treble damages” despite TASB’s assertions.53

Many of the “claims” TASB complains of are merely factual allegations or theories

51
Colorado ISD, 660 S.W.3d at 773.
52
See, e.g., CR 44 at ¶26 (claiming the College seeks to recover based on tortious allegations of
fraud).
53
Compare CR 43, with CR 12–13.

18
asserted by the College to support its breach of contract claim. 54 Further, to the extent

the College has asserted a right to relief for extracontractual consequential damages,

the College immediately noted that the consequential damages being sought were

only those linked to delay by TASB for benefits owed under the Agreement that has

resulted in an increase in the costs of construction. 55

The crux of TASB’s Partial Plea to the Jurisdiction actually challenged

whether the College may (1) assert any other defensive claims in support of its

breach of contract cause of action, such as to rebut Appellant’s affirmative defenses,

and (2) whether the College may recover certain consequential damages related to

the increased cost of materials and labor due to TASB’s breach of the contract and

delay in timely paying the College for the covered damages.

At the hearing TASB focused on lumping the College’s claim for delay

damages that have resulted in an increase of the costs of construction as part of other

impermissible damages, such as treble and exemplary damages, which the College

has never asserted a claim for in this lawsuit. 56 However, as addressed below, the

only type of consequential damages the College seeks to recover at trial, after

presenting evidence, is the increased costs of construction to repair and replace

54
CR 8–13 at ¶¶12–42; see also CR 20 at ¶83.
55
CR 11 at ¶34.
56
RR 6:13–20

19
damaged property as a result of TASB’s improper denial and delay. 57

These types of damages are explicitly allowed to be recovered pursuant to the

statute passed by the Texas Legislature. Defendant’s attempt to narrow the

construction of the statute is both illogical and ignores the fact that at a minimum

the College’s pleadings present a fact issue that asserts a right to at least some type

of consequential damages that is recoverable under the statute due to TASB’s

“owner-caused delays”.

C. Delay damages sought by the College are explicitly allowed under the Act.

Section §271.152–153 allows certain remedies to be subject to the waiver of

immunity. Under the statute, a claimant pursuing a breach of contract action against

a governmental subdivision can seek the following enumerated remedies:

(1) the balance due and owed by the local governmental
entity under the contract as it may have been amended,
including any amount owed as compensation for the
increased cost to perform the work as a direct result of
owner-caused delays or acceleration;

(2) the amount owed for change orders or additional work
the contractor is directed to perform by a local
governmental entity in connection with the contract;

(3) reasonable and necessary attorney's fees that are
equitable and just; and

(4) interest as allowed by law, including interest as

57
Infra Section VII.C.

20
calculated under Chapter 2251, Government Code. 58

The balance “due and owed” means damages resulting from the breach of the

contract – that is damages measured as “the necessary and usual result of the

Appellant’s wrongful act” in violation of the terms of the contract.59 The statute

generally excludes “consequential damages,” or exemplary damages. 60

1. The Statute expressly allows for delay damages.

Despite generally excluding “consequential” damages, the legislature

explicitly allowed for a claimant to claim consequential damages for “the increased

cost to perform the word as a direct result of owner-caused delays.”61 Therefore,

“[s]ubsections (a)(1) and (b) allow recovery of contract damages, including delay

damages, but excluding other consequential damages.” 62 “We conclude that the

Local Government Contract Claims Act waives immunity for a contract claim for

delay damages not expressly provided for in the contract.” 63

The Court in City of Mesquite noted that because of this, the question of what

damages are being claimed is a matter that generally is best for a trial court to address

58
TEX. LOC. GOV’T CODE § 271.153 (emphasis added).
59
Zachry, 449 S.W.3d at 111.
60
Id.
61
TEX. LOC. GOV’T CODE § 271.153(1).
62
See Zachry, 449 S.W.3d at 112.
63
Id. at 114.

21
at the later stages of litigation with a full record. 64

The College’s Original Petition states that the College seeks to recover, in

addition to its actual damages from TASB’s breach of the contract and delay of

payment of owed for benefit, damages “related to Plaintiff’s inability to make

necessary repairs, increased costs of construction . . . .” 65 While the College may

have used the common legal phrase “consequential damages” to help explain these

additional costs which were distinguished from direct damages owed under the

contract, this classification does not by itself exclude the College from recovering

these additional costs. 66 The College seeks damages related to the increased costs

of construction from delay pursuant to Section 271.153. 67 Specifically, the

College’s claim for such delay damages is supported by the College’s allegations

that it was TASB’s conduct in acting arbitrary and capricious, wrongful interference,

and bad faith actions 68

64
City of Mesquite v. PKG Contracting, Inc., 263 S.W.3d 444, 448 (Tex. App.—Dallas 2008, pet.
denied) (“The trial court is in the best position following further proceedings to determine whether
PKG is able to recover some, all, or none of the damages and remedies it claims.”).
65
CR 11 at ¶34.
66
See Tooke v. City of Mexia, 197 S.W.3d 325, 344–46 (Tex.2006) (concluding Tooke’s claim
was only for lost profits, which are consequential damages excluded from recovery under the
statute).
67
See CR 11 at ¶ 34; see also TEX. LOC. GOV’T CODE § 271.153(1). “[T]he increased cost to
perform the word as a direct result of owner-caused delays.”) (emphasis added).
68
It is important to note that the College is not making separate claims of fraud or bad faith against
TASB based on these factual allegations, but is alleging TASB’s wrongful conduct that caused the
delay damages recoverable under the Act in addition to TASB’s failure to perform under the

22
The College’s pleading clearly does not seek damages related to “lost profits”

but rather for increased costs of construction which is nearly identical to what the

legislature has expressly allowed a claimant to recover in a breach of contract case

against a governmental entity like TASB.69

2. “Owner-caused delays” encompass TASB’s actions.

During a hearing on this issue TASB improperly attempted to narrow the

statute by claiming the College’s right to such consequential delay damages was

precluded due to the phrase “owner-caused delays”.70 TASB asserted that in this

case the College is the owner of the Property and that TASB could therefore not be

the “owner” causing the delays.71 However, as noted in City of Corpus Christi v.

Graham Construction Services, Inc., “§ 271.153(a) does not define ‘owner-caused

delays’” and therefore does not only refer to delays caused by property owners. 72

Further, TASB presents no case law or statute that “owner” under the statute

contract. Such allegations therefore are not subject to immunity as they merely go to the ultimately
liability of TASB on the College’s breach of contract claim. See Zachry Const. Corp. v. Port of
Houston Auth. of Harris Cnty., 449 S.W.3d 98, 115 (Tex. 2014) (noting the jury found “delay
damages resulted from the Port’s ‘arbitrary and capricious conduct, active interference, bad faith
and/or fraud’ as those terms were defined in the charge.”); Zachry, 449 S.W.3d at 109 (“We
disagree . . . the Act makes its waiver of immunity dependent on ultimate liability.”).
69
CR 11 at ¶ 34; see also Tex. Loc. Gov’t Code § 271.153(a)(1). “[T]he increased cost to perform
the work as a direct result of owner-caused delays.”)
70
RR 9:11.
71
RR 9:11.
72
City of Corpus Christi v. Graham Constr. Services, Inc., No. 13-19-00367-CV, 2020 WL
3478661, at *3 (Tex. App.—Corpus Christi–Edinburg June 25, 2020, pet. denied).

23
is defined as the owner of property as opposed to an owner of a program. In fact, the

City of Corpus Christi Court rejected a similar argument from a governmental entity

that attempted to cast a plaintiff contractor suing for delay damages pursuant to

Section 271.153(a) as the cause of the delay instead of the City of Corpus Christi.73

The Court in City of Corpus Christi disagreed that it must mean property owner and

further noted that the contract that was the basis of the lawsuit identified another

party as the owner precluding the trial court from granting the City’s plea to the

jurisdiction due to a “genuine issue of material fact regarding this jurisdictional

issue.” 74

The legislative history also further proves that the legislature did intend to

limit this to a property owner specifically.75 The legislative history clearly shows the

“delay” language was intended to allow a plaintiff to recover additional damages

against an “entity” for increased costs “caused by the entity . . . delaying the

plaintiff’s performance.” 76 This is the exact scenario pled by the College here where

the College alleges TASB’s failure to timely determine the full amount of damages

and pay the full costs of the damages owed under the Agreement that the College

73
Id.
74
Id.
75
See App. A at p. 3 (“The bill would limit a judgment against the entity . . . including [for] any
amount owed for increased costs borne by the plaintiff to perform the contract caused by the entity
either delaying the plaintiff’s performance or accelerating the contract.”) (emphasis added).
76
See id.

24
was unable to perform its obligations under the Agreement.77

Here, TASB is the owner of TASB’s risk management programs, including

for property coverage. 78 The College has sued TASB as the owner of the property

coverage service program for its failure to provide the agreed-to service thus

breaching the contract and causing delays. 79 Therefore, similar to City of Corpus

Christi, there is evidence in the contract that it is actually TASB who is the owner

of the fund program which caused the delays in timely paying benefits owed to the

College under the Agreements which has now led to the increase in the costs of

construction.80 At a minimum, TASB’s own exhibits have raised a genuine issue of

material fact regarding this jurisdictional issue.81

D. Zachry only disagreed with City of Mesquite to the extent it allowed
damages not waived under the statute; but Zachry still permits claims for
increased construction costs due to delay.

Supporting the fact that the specific consequential damages the College is

seeking in this case is the Texas Supreme Court’s opinion in Zachry where the Court

77
CR 11 at ¶¶30–34
78
CR 56 (“This Agreement enables Fund Member to participate in one or more of the Fund’s
available programs, including . . . property . . . .”) (emphasis added); see RR 16:15–17:8
(discussing TASB’s ownership of financial assets including contributions from fund members and
“realized investment income”).
79
CR 6 at ¶3; CR 10 at¶21 (“TASB provided risk coverage for the Campus that is the subject of
this lawsuit.”).
80
See City of Corpus Christi, 2020 WL 3478661, at *3 (“However, § 271.153(a) does not define
‘owner-caused delays.’ And the contract identified Carollo as the ‘Owner's Representative.’”).
81
See Miranda, 133 S.W.3d at 228; Roma ISD, 2012 WL 3025927, at *2 (concluding immunity
was waived based on fact issue concerning jurisdiction).

25
only denounced consequential damages other than damages for “owner-caused

delay”. 82 As a result, the Texas Supreme Court specifically acknowledges that the

Act does not prohibit all consequential damages as TASB suggests.

In Zachry, a contractor sought approximately $30 million in damages for

delays caused by the Port Authority of Houston during the construction of a wharf

and retaining walls on the Bayport Ship Channel.83 The suit was filed despite a “no-

damages-for-delay clause” specifying that the Port Authority would never be liable

for delay damages to Zachry or its subcontractors even if the delays were caused by

the Port Authority’s “negligence, breach of contract or other fault.” 84 Zachry argued

that this clause could not be enforced to preclude a claim for delay resulting from

“intentional” conduct by the Port Authority and the district court and court of appeals

agreed with Zachry. 85

In response, the Port Authority argued that even if the no-damages-for delay

clause was unenforceable as against intentional conduct, the contract was still

otherwise silent on the recovery of delay damages sought by Zachry and, thus,

Zachry sought damages beyond those expressly provided by the contract. 86 The

82
Zachry, 449 S.W.3d at 110–11 (“Section 271.153(b) precludes recovery of consequential
damages, ‘except as expressly allowed under Subsection (a)(1)’”.).
83
Zachry, 449 S.W.3d at 102–103.
84
Id. at 103.
85
Id.
86
Id.

26
Supreme Court of Texas granted review and addressed the question of whether

§271.152 “waives a local governmental entity’s immunity from suit on a contract

claim for delay damages the contact does not call for.”87 The analysis of this question

was then broken down further into two separate parts: (1) whether the Act’s

limitations on recovery help define and restrict the scope of the waiver of immunity

(it does, the court held), and (2) whether the delay damages sought are permitted by

the Act (they were, the court held). 88 The Court’s answer in the affirmative to both

of these questions makes clear that the College’s recovery of these damages as plead

are allowed.

By concluding that §271.152-153 only allowed certain categories of damages

to be subject to the waiver of immunity, including claims seeking amounts “due and

owed/owing,” the court generally construed this to mean that either section 271.153

must expressly provide for the type of damages sought against the governmental

entity for immunity to be waived or else the damages must be direct damages

provided for under the contract.89

Of course, on the facts of Zachry, the court needed to look no further than the

terms of the statute itself, which had been amended to expressly allow “any amount

87
Id. at 104.
88
Id.
89
Id. at 110-112.

27
owed as compensation . . . . for owner-caused delays.”90 The court concluded that

this provision expressly waived immunity from claims for owner-caused delay

damages even if such damages are “not expressly provided for in the contract.”91

The Texas Supreme Court in Zachry did note in its footnote 54 that it “disapprove[d]

. . . cases to the extent they are to the contrary” in permitting damages not permitted

under Section 271.153, 92 however, the Court still clearly stated that “Subsections

(a)(1) and (b) [of the Act] allow recovery of contract damages, including delay

damages, but excluding other consequential damages.”93

For example, one such case that the Zachry Court referenced in slight

disapproval was City of Mesquite v. PPKG Contracting, Inc., 263 S.W.3d 444, 447

(Tex. App.—Dallas 2008, pet. denied) which the College also relies on. 94 But it is

important to note that the reason the Zachry Court pointed to the City of Mesquite

was not to reverse the opinion but to explain and clarify the type of consequential

damages that are permitted under section 271.153 of the Act.95 In fact, the Zachry

Court actually appeared to approve of the City of Mesquite opinion regarding

consequential damages due to the fact that the City of Mesquite court specifically

90
Id.; TEX. LOC. GOV’T CODE § 271.152(a)(1).
91
Zachry, 449 S.W.3d at 114.
92
Id at 110.
93
Id. at 112.
94
Zachry, 449 S.W.3d at 110, n.54.
95
See id.

28
“pointed out that the record did not establish that the claim was solely for damages

excluded by the statute, and cited Tooke.”96

The Texas Supreme Court noted this important fact because the statute

expressly allows suit for recovery of damages due and owed/owing under a contract

with a governmental subdivision and this contract expressly provides for the

recovery of the damages sought by the College – i.e., the amount of the loss

measured as Replacement Cost Value. 97 Further, the statute explicitly permits the

recovery of consequential damages that are being sought by the College — the

amount for the increased costs of construction due to TASB’s delay in paying for

the covered damages. 98

The only aspect of the City of Mesquite case and the other cases with which

the Supreme Court specifically disagreed was where those appellate courts did not

grant a plea to the jurisdiction where the claimants sought a measure of damages that

was not either expressly provided for either in the Act or direct damages from breach

of the contract in question.99 For example, in City of Mesquite, the claimant sought

recovery of consequential damages stemming from “implied” duties in the contract

96
Id. (emphasis added).
97
CR 61; see also CR 69–70 (Agreement subsection 4.2).
98
Tex. Loc. Gov. Code § 271.153(a)(1); § 271.153(b); Zachry, 449 S.W.3d at 112 (“Subsections
(a)(1) and (b) allow recovery of contract damages, including delay damages, but excluding other
consequential damages.”).
99
Zachry, 449 S.W.3d at 110.

29
and not direct damages under the contract’s terms or damages authorized by the

statute.100 The court in City of Mesquite did not authorize these additional damages,

but instead noted that the suit was not solely limited to damages that were

unavailable under the statute, and therefore denied the plea to the jurisdiction. 101

The College’s claim is readily distinguishable because there is no reasonable

dispute that the insurance contract expressly provides for the RCV damages pled by

the College102; such damages would be direct damages from the breach of the

contract and thus “due and owed” under §271.153.103 This is precisely how footnote

54 was recently understood by another Texas court examining a similar issue – the

Zachry court only disapproved with a specific aspect of Roma ISD. 104

With that in mind, it is also clear what specifically the Zachry court disagreed

with in these cases – the allowance of consequential damages excluded from the

waiver by section 271.153. For example, the Zachry Court disapproved of the Court

100
City of Mesquite, 263 S.W.3d 444, 447–48.
101
Id. (“We cannot say on this record that PKG’s claim for damages is solely for damages excluded
by the statute.”).
102
CR 61; see also CR 69 (“settlement option offered in either § 4.1 or § 4.2 related to this Damage
. . . .”).
103
Zachry, 449 S.W.3d at 111 (defining “due and owed” to “simply mean[s] . . . damages payable
and unpaid. Direct damages for breach – ‘the necessary and usual result of the defendant’s
wrongful act’ – certainly qualify”) (quoting Basic Capital Mgmt. v. Dynex Commercial, Inc., 348
S.W.3d 894, 901 (Tex. 2011)).
104
See City of Corpus Christi, 2020 WL 3478661, at *4 n.2 (“However, Zachry only disapproved
of Roma to the extent that [the Roma court] concluded that § 271.153 cannot serve as a proper
basis for granting a plea to the jurisdiction.”).

30
in Roma ISD because the contractor sought recovery, in part, of additional costs of

construction resulting from concealed conditions on the property as consequential

damages. 105 The damages sought for additional work were not expressly authorized

under the contract in Roma ISD and were prohibited by the statute as consequential

damages not otherwise permitted under the Act.106 This is the aspect of Roma ISD

with which the supreme court disagreed – in the court’s own words to the extent it

allowed a claim for “damages not recoverable under section 271.153.”107

Here, by contrast, the RCV damages sought are expressly made due and

owed/owing under the contract as an available measure of the direct contractual

benefit owed for a covered loss and therefore fall within the statute’s waiver of

sovereign immunity. 108 Further, the College does not seek consequential damages

for anything other than the increased cost of construction due to TASB’s delays as

explicitly permitted under Section 271.153. 109

The holding of Zachry in this regard is nothing more than the conclusion that

immunity is not waived when a claimant solely seeks “damages not recoverable

105
Roma ISD, 2012 WL 3025927, at *1 (“claiming the District failed to pay Ewing for: (1) costs
for additional work required to complete the project or required to be undertaken as a result of
concealed conditions . . . .”).
106
See Zachry, 449 S.W.3d at 111, n.54.
107
Id. at 111.
108
See TEX. LOC. GOV’T CODE § 271.153(a)(1); see also CR 69.
109
See id.

31
under section 271.153.” 110 “The waiver does not depend on ultimate liability,” but

“does require a showing of a substantial claim” seeking some relief that meets the

Act’s conditions.111

CONCLUSON & PRAYER

The District Court erred in granting TASB’s Partial Plea to the Jurisdiction to

the extent the Court granted dismissal for the College’s claim for consequential

damages for the increase cost of construction due to TASB’s delays which is

permitted under TEX. LOC. GOV’T CODE § 271.153. Therefore, the order of the

District Court should be reversed to the extent it denies the College’s recovery of

damages caused by TASB’s “owner-caused delay[s]”, such as the increased costs of

materials and labor and other such delay damages that are a direct result of TASB’s

actions throughout the Claim. This issue should proceed on the merits in the District

Court so that a jury may deliberate these statutorily permitted damages and award

such delay damages based upon the evidence presented at trial.

110
Zachry, 449 S.W.3d at 109; San Antonio River Auth. v. Austin Bridge & Rd., L.P., 601 S.W.3d
616, 630 (Tex. 2020); see also Primestar Constr., Inc. v. City of Dallas, No. 05-17-01447-CV,
2019 WL 1033978, at *4 (Tex. App.—Dallas Mar. 5, 2019, pet. denied) (“In Zachry, the court
explained that immunity is not waived when a plaintiff seeks ‘only damages not recoverable under
section 271.153.’”) (quoting Zachry).
111
Primestar, 2019 WL 1033978, at *4.

32
Respectfully submitted,

/s/ Vincent P. Circelli
Vincent P. Circelli
State Bar No. 24058804
vcircelli@dcclawfirm.com
Preston J. Dugas III
State Bar No. 24050189
pdugas@dcclawfirm.com
Andrew D. Spadoni
State Bar No. 24109198
aspadoni@dcclawfirm.com
Sarah Arroyo
State Bar No. 24138756
sarroyo@dcclawfirm.com

DUGAS & CIRCELLI, PLLC
4800 Bryant Irvin Ct.
Fort Worth, Texas 76107
Telephone: (817) 817-7000
Facsimile: (682) 219-0761
ATTORNEYS FOR APPELLEE

33
CERTIFICATE OF COMPLIANCE

1. This petition complies with the type-volume limitations of Texas Rules of

Appellate Procedure 9.4 because it contains 8,109, excluding the parts

exempted by the Texas Rules of Appellate Procedure.

2. This petition complies with the typeface requirements of Texas Rules of

Appellate Procedure 9.4(e) because this response has been prepared in a

proportionally spaced typeface using “Microsoft Word for Microsoft 365

MSO” in 14 point “Times New Roman” style font.

/s/Vincent P. Circelli
Vincent P. Circelli

34
CERTIFICATE OF SERVICE

I certify that on this October 2, 2025, a true and correct copy of the foregoing

document was forwarded to the following Respondent and Real Party in Interest in

accordance with Texas Rule of Appellate Procedure 9.5(b).

Via Electronic Service
Jack W. Higdon (Trial and Appellate)
State Bar No. 24007360
jack.higdon@blankrome.com
Barry Abrams (Appellate)
State Bar No. 00822700
barry.abrams@blankrome.com
Joshua A. Huber (Appellate)
State Bar No. 24065457
josh.huber@blankrome.com
Gregory J. Moore (Trial)
State Bar No. 24055999
greg.moore@blankrome.com
Christopher W. Caudill (Trial)
State Bar No. 24104717
christopher.caudill@blankrome.com

BLANK ROME LLP
717 Texas Avenue, Suite 1400
Houston, Texas 77002-2727

Clarissa M. Rodriguez
State Bar No. 24056222
cmrodriguez@rampagelaw.com
Lori Hanson
State Bar No. 21128500
lwhanson@rampagelaw.com

DENTON NAVARRO RODRIGUEZ
BERNAL SANTEE & ZECH, P.C.
2517 N. Main Avenue
San Antonio, Texas 78212

35
/s/Vincent P. Circelli
Vincent P. Circelli

36
No. 15-25-00115-CV

IN THE FIFTHTEENTH COURT OF APPEALS OF TEXAS

TEXAS ASSOCIATION OF SCHOOL BOARDS RISK MANAGEMENT FUND
Appellant/Cross-Appellee

vs.

SOUTHWEST TEXAS JUNIOR COLLEGE
Appellee/Cross-Appellant

Appeal from the 38th Judicial District Court
Uvalde County, Texas, No. 2023-11-35269-CV
The Honorable Kelley T. Kimble, Presiding Judge

APPENDIX

Appendix Document

A House Research Organization: Bill Analysis (4/20/2005)

37
APP. A
HOUSE HB 2039
RESEARCH Nixon
ORGANIZATION bill analysis 4/20/2005 (CSHB 2039 by Rose)

SUBJECT: Waiving local government sovereign immunity for contract disputes

COMMITTEE: Civil Practices — committee substitute recommended

VOTE: 7 ayes — Nixon, Rose, P. King, Madden, Raymond, Strama, Woolley

0 nays

2 absent — Martinez Fischer, Talton

WITNESSES: For — Gregory Cokinos, AGC – Texas Building Branch; Anna Farris,
Associated Builders and Contractors of Greater Houston and ABC of
Texas; Richard Ringo, RBR Construction; Tom Vaughn, Vaughn
Construction; John R. Ward, Texas Surety Federation; Paul Workman,
Workman Commercial

Against — Todd Clark, Texas Association of School Boards and Council
of School Attorneys; Keith Stretcher, City of Midland

BACKGROUND: The doctrine of sovereign immunity precludes a party from asserting an
otherwise meritorious cause of action against a government entity unless
the government consents. The Legislature has waived sovereign immunity
for both the state and for counties in contract lawsuits. There is
disagreement as to whether sovereign immunity has been waived for other
local government entities (such as cities and school districts) in contract
cases. The Texas Supreme Court is currently considering several cases that
deal with the issue.

DIGEST: CSHB 2039 would waive sovereign immunity for local government
entities for claims arising under contracts that the entity entered into. The
bill would apply to political subdivision of the state, other than a county or
a unit of state government, and would include a municipality, a public
school district or junior college district, and a special-purpose district,
such as a navigation district.

A plaintiff could sue the entity in either county or state court for a claim
arising under a written contract for goods or services. The plaintiff would
not be able to sue the entity in federal court as the bill expressly would
maintain sovereign immunity against suits brought in federal court.
HB 2039
House Research Organization
page 2

The bill would limit a judgment against the entity to the following:

• the balance owed by the entity under the contract, including any
amount owed for increased costs borne by the plaintiff to perform
the contract caused by the entity either delaying the plaintiff’s
performance or accelerating the contract;
• the amount owed for change orders or additional work required to
carry out the contract; and
• interest allowed by law.

The bill would not allow the following damage awards:

• consequential damages (losses that did not flow directly from the
defendant’s wrongful act) except for an amount owed for increased
costs borne by the plaintiff to perform the contract caused by the
entity either delaying the plaintiff’s performance or accelerating the
contract;
• exemplary damages (damages awarded in addition to actual
damages when the defendant acted with recklessness, malice, or
deceit and meant to punish and thereby deter blameworthy
conduct); or
• damages for unabsorbed home office overhead.

Adjudication procedures agreed to in the contract (including a requirement
for serving notice to the other party or engaging in alternative dispute
resolution before bringing a suit) between the plaintiff and the entity
would be enforceable unless they conflicted with another provision in the
bill.

The bill state that it is not intended to affect in any way the sovereign
immunity of a local gove rnment entity for a lawsuit arising from a contract
executed before September 1, 2005. The bill would take effect September
1, 2005, and would apply to contracts executed on or after that date.

SUPPORTERS CSHB 2039 would bring fairness to business relationships between
SAY: contractors and local government entities, thus encouraging top
contractors to take on government contracts. Under current law, a plaintiff
cannot sue a local government entity for a claim that arises from a
contract. This creates a fundamentally unfair situation that denies redress,
for example, to a contractor who completed a project for a city that refused
to pay. As a result, to protect themselves from potentially irrecoverable
HB 2039
House Research Organization
page 3

losses, certain contractors do not bid for local gove rnment contracts. Some
of the best and most experienced contractors choose to bid only on other
contracts while small contractors effectively are shut out of the bidding
process because they cannot afford the risk of contracting with local
governments. In the end, all that local government entities may be left
with to receive bids are s ub-par contractors.

Another problem resulting from the inability of a contractor to bring suit
against government entities is that contractors often submit bids that are
artificially high or perform substandard work. They do this to provide
themselves with an informal type of insurance — if they overcharge
enough local government entities or save money on each job by cutting
corners, contractors financially are better equipped to absorb losses from
government entities that refuse to pay. This creates a situation where local
government entities often pay more for a contract job than the fair market
value. CSHB 2039 would provide reasonable assurance to contractors that
they would receive payment, or at least the opportunity to seek redress, in
exchange for performing competent work at a fair price.

OPPONENTS The bill's provision stating that sovereign immunity would be waived for
SAY: any claim “arising under the contract” is too broad. It is unclear from this
language whether a plaintiff could bring a claim only for breach of
contract, or whether the plaintiff could bring any claim — such as fraud —
based on the contract. Government Code, ch. 2260, which allows a
contractor to bring a claim against the state, limits a contractor to breach
of contract claims. It would be fair and reasonable to include a similar
limitation in this bill.

Local Government Code, sec. 262.007, which waives the sovereign
immunity of counties in claims arising from contracts they entered, waives
a county’s sovereign immunity only for claims involving a contract for
engineering, architectural, or construction services or for goods related to
those contracts. By not limiting the type of contract for which a local
government entity could be sued, local government entities would be
exposed to a vast amount of liability based on any contracts they entered.

OTHER The bill should allow recovery for attorney’s fees. Local Government
OPPONENTS Code, sec. 262.007, which waives sovereign immunity for certain contract
SAY: claims against counties, allows for the recovery of attorney’s fees. A
contractor should be able to collect attorney’s fees against a city or other
local governmental entity also.
HB 2039
House Research Organization
page 4

NOTES: The bill as introduced would have allowed for the recovery of attorney’s
fees from the local government entity as part of the plaintiff’s judgment
award.
Automated Certificate of eService
This automated certificate of service was created by the efiling system.
The filer served this document via email generated by the efiling system
on the date and to the persons listed below. The rules governing
certificates of service have not changed. Filers must still provide a
certificate of service that complies with all applicable rules.

Jen Saenz on behalf of Vincent Circelli
Bar No. 24058804
jen@pjdlawfirm.com
Envelope ID: 106394425
Filing Code Description: Brief Not Requesting Oral Argument
Filing Description: Appellee/Cross-Appellant's Brief
Status as of 10/3/2025 7:48 AM CST

Case Contacts

Name BarNumber Email TimestampSubmitted Status

Barry Abrams barry.abrams@blankrome.com 10/2/2025 5:01:21 PM SENT

Jack Higdon jack.higdon@blankrome.com 10/2/2025 5:01:21 PM SENT

Joshua Huber josh.huber@blankrome.com 10/2/2025 5:01:21 PM SENT

Penny Johnson penny.johnson@blankrome.com 10/2/2025 5:01:21 PM SENT

Gregory J.Moore Greg.Moore@BlankRome.com 10/2/2025 5:01:21 PM SENT

Preston J.Dugas III pdugas@dcclawfirm.com 10/2/2025 5:01:21 PM SENT

Vincent P. Circelli vcircelli@dcclawfirm.com 10/2/2025 5:01:21 PM SENT

Andrew D. Spadoni aspadoni@dcclawfirm.com 10/2/2025 5:01:21 PM SENT

Sarah Arroyo sarroyo@dcclawfirm.com 10/2/2025 5:01:21 PM SENT

Clarissa Rodriguez cmrodriguez@rampagelaw.com 10/2/2025 5:01:21 PM SENT

Liniuse Umunna Liniuse.Umunna@blankrome.com 10/2/2025 5:01:21 PM SENT

Noorhan Chahal noorhan.chahal@blankrome.com 10/2/2025 5:01:21 PM SENT

Yvette Manzano yvette.manzano@blankrome.com 10/2/2025 5:01:21 PM SENT

Christopher W.Caudill Christopher.Caudill@BlankRome.com 10/2/2025 5:01:21 PM SENT

Amy Easley aeasley@dcclawfirm.com 10/2/2025 5:01:21 PM SENT

Poursuivez vos recherches dans ChatGPT ou Claude

Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.