CourtListener 5288909•Mark Benton, Individually and D/B/A Mebco Contracting v. Contractor's Supplies, Inc.
Mark Benton, Individually and D/B/A Mebco Contracting v. Contractor's Supplies, Inc.
CourtListener 5288909Txctapp126 oct. 2021
Texte intégral
NO. 12-20-00207-CV
IN THE COURT OF APPEALS
TWELFTH COURT OF APPEALS DISTRICT
TYLER, TEXAS
MARK BENTON, INDIVIDUALLY § APPEAL FROM THE 159TH
AND D/B/A MEBCO CONTRACTING,
APPELLANT
§ JUDICIAL DISTRICT COURT
V.
CONTRACTOR’S SUPPLIES, INC., § ANGELINA COUNTY, TEXAS
APPELLEE
MEMORANDUM OPINION
Mark Benton, individually and D/B/A MEBCO Contracting appeals the trial court’s order
granting summary judgment in favor of Contractor’s Supplies, Inc. In what we construe as two
issues, Benton argues that the trial court erred in granting summary judgment in favor of
Contractor’s because he argues material issues of fact remain with respect to Contractor’s breach
of contract claim and Benton’s affirmative defenses. We affirm.
BACKGROUND
This case arises from a dispute between a subcontractor and a materials supplier over
payment for concrete and other materials used in the construction of the Pinnacle Senior Living
of Lufkin, an assisted living facility located in Lufkin, Texas. The facility is licensed as an
assisted living community with roughly eighty beds and sixty thousand square feet of indoor
space.
Benton is a self-employed contractor who works in the concrete business. He was
awarded a bid by the general contractor, Regent Construction, to furnish concrete work and
framing on the Pinnacle project. Benton entered into a detailed subcontractor agreement with
Regent on August 1, 2017 to complete the concrete and framing work for $890,570.00.
1
Benton began work on the project in August 2017. Contractor’s sold premixed concrete,
construction supplies and other materials to Benton for the Pinnacle project. During
construction, a dispute arose between Regent and Benton over problems and delays in the
concrete work and framing on the project. Subsequently, Regent hired another contractor to
complete the concrete work and framing and charged Benton for the new subcontractor’s work.
Benton stopped work on the Pinnacle project in December 2017. Contractor’s provided Benton
with $389,211.66 worth of construction materials and concrete from August to December.
Benton paid Contractor’s $5,774.71 at the outset of the work, but thereafter ceased
paying for the materials. In November and December of 2017, Regent directly paid Contractor’s
$74,527.64 for the materials. In January 2018, Contractor’s filed statutory liens for materials
supplied in October ($229,084.14), November ($54,715.00), and December ($3,307.79) in an
attempt to collect the outstanding balance for the materials. However, the lien for the materials
supplied in October 2017 was not timely filed. Additionally, the lien filed for the materials
supplied in November excluded an invoice for $21,801.55. In May of 2018, Regent paid
Contractor’s $58,023.62 to release the valid liens. Thereafter, Regent advised Contractor’s that
all the funds for the concrete portion of the Pinnacle project had been expended.
Contractor’s then filed suit against Benton for breach of contract and unjust enrichment
to recover the remaining $250,889.69 it was owed for the materials. Benton answered and
asserted multiple defenses including modification, estoppel/quasi-estoppel, accord and
satisfaction/novation, and failure to mitigate damages.
Subsequently, Contractor’s filed a traditional motion for summary judgment and no-
evidence motion for summary judgment with respect to Benton’s affirmative defenses. The trial
court granted the motion for summary judgment and signed a final judgment awarding damages
and attorney’s fees to Contractor’s. This appeal followed.
SUMMARY JUDGMENT
In his first issue, Benton argues that the trial court erred in granting summary judgment in
favor of Contractor’s because Contractor’s did not carry its burden to establish entitlement to
summary judgment as a matter of law, as it failed to prove the existence of a valid contract.
2
In his second issue, Benton argues that the trial court erred in granting summary
judgment in favor of Contractor’s because the record establishes disputed issues of fact with
respect to Benton’s affirmative defenses.
Standard of Review and Applicable Law
In a traditional motion for summary judgment, if the movant’s motion and summary-
judgment evidence facially establish its right to judgment as a matter of law, the burden shifts to
the nonmovant to raise a genuine, material fact issue sufficient to defeat summary judgment.
M.D. Anderson Hosp. & Tumor Inst. v. Willrich, 28 S.W.3d 22, 23 (Tex. 2000). In reviewing a
no-evidence summary judgment, we ascertain whether the nonmovant pointed out summary-
judgment evidence raising a genuine issue of fact as to the essential elements attacked in the no-
evidence motion. Johnson v. Brewer & Pritchard, P.C., 73 S.W.3d 193, 206–08 (Tex. 2002).
In our de novo review of a trial court’s summary judgment, we consider all the evidence in the
light most favorable to the nonmovant, crediting evidence favorable to the nonmovant if
reasonable jurors could, and disregarding contrary evidence unless reasonable jurors could not.
Mack Trucks, Inc. v. Tamez, 206 S.W.3d 572, 582 (Tex. 2006). The evidence raises a genuine
issue of fact if reasonable and fair-minded jurors could differ in their conclusions in light of all
of the summary-judgment evidence. Goodyear Tire & Rubber Co. v. Mayes, 236 S.W.3d 754,
755 (Tex. 2007). When a trial court’s order granting summary judgment does not specify the
ground or grounds relied on for the ruling, summary judgment will be affirmed on appeal if any
of the theories advanced are meritorious. State Farm Fire & Cas. Co. v. S.S., 858 S.W.2d 374,
380 (Tex. 1993).
In a no evidence summary judgment context, if the non-movant failed to produce more
than a scintilla of evidence under the standards of Rule 166a(i), then there is no need to analyze
whether the movant’s summary-judgment proof satisfied the less stringent burden set forth for
traditional summary judgment under Rule 166a(c). TEX. R. CIV. P. 166a(c) & (d); E. Hill
Marine, Inc. v. Rinker Boat Co., 229 S.W.3d 813, 816 (Tex. App.—Fort Worth 2007, pet.
denied). That is why, typically, when a party files a hybrid summary-judgment motion on both
no-evidence and traditional grounds, we first review the trial court’s judgment under the no-
evidence standard of review. Ford Motor Co. v. Ridgway, 135 S.W.3d 598, 600 (Tex. 2004); All
Am. Tel., Inc. v. USLD Commc’ns, Inc., 291 S.W.3d 518, 526 (Tex. App.—Fort Worth 2009,
pet. denied); E. Hill Marine, 229 S.W.3d at 816. However, this rule is not absolute. See Dunn
3
v. Clairmont Tyler, LP, 271 S.W.3d 867, 870 (Tex. App.—Tyler 2008, no pet.). Affirmative
defenses, as opposed to defendant’s denials, are the propositions which a defendant may assert
and interpose to defeat a prima facie case made by the plaintiff. Hays Consol. Indep. Sch. Dist.
v. Valero Transmission Co., 645 S.W.2d 542, 546 (Tex. App.—Austin 1982, writ ref’d n.r.e.).
They open the way for the defendant to introduce evidence which does not tend to rebut the
factual propositions asserted in the plaintiff’s case, but seek to establish an independent reason
why the plaintiff should not recover. Id.
The elements of a breach of contract claim are (1) the existence of a valid contract
between plaintiff and defendant, (2) the plaintiff’s performance or tender of performance, (3) the
defendant’s breach of the contract, and (4) the plaintiff’s damage as a result of the breach. Prime
Prods., Inc. v. S.S.I. Plastics, Inc., 97 S.W.3d 631, 636 (Tex. App.—Houston [1st Dist.] 2002,
pet. denied). The elements of a valid contract are (1) an offer, (2) acceptance, (3) a meeting of
the minds, (4) each party’s consent to the terms, and (5) execution and delivery of the contract
with the intent that it be mutual and binding. Id.
Traditional Summary Judgment
Contractor’s moved for traditional summary judgment on its breach of contract claim
against Benton, and moved for no evidence summary judgment on Benton’s affirmative
defenses. For summary judgment on Contractor’s breach of contract claim to have been properly
granted, the trial court had to find that Contractor’s established each element of its breach of
contract claim as a matter of law by competent summary judgment evidence. See Willrich, 28
S.W.3d at 23. Further, as explained above, Benton’s affirmative defenses are only relevant if
Contractor’s established its claim for breach of contract. See Hays Consol. Indep. Sch.
Dist., 645 S.W.2d at 546. Thus, we will review Contractor’s traditional motion for summary
judgment first. Cf. Dunn, 271 S.W.3d at 870.
Benton argues that Contractor’s did not conclusively establish that it had a contract with
Benton. He argues that
The only agreement between the [p]arties, if any, was oral, and the loose terms were based upon a
general course of dealing between the parties.
...
Defining the specific terms of the contract or contracts—which [Contractor’s] has not done
conclusively either in its pleadings or through its summary judgment motions—is a fact issue in
itself which should be resolved by a jury.
...
4
[Contractor’s] points to “hundreds of receipts and invoices” that were sent to [Benton] as “proving
the existence of the contract” and tries to overwhelm the record with such evidence. However,
invoices are not contracts, [Contractor’s] has not alleged that the invoices were an agreement
themselves or integrated into any agreement.
Benton points out that, although the invoices contain language stating “NET AMOUNT DUE IN
30 DAYS,” Contractor’s made no attempt to enforce or collect after thirty days and further, the
evidence demonstrates that the invoices were sent directly from Contractor’s to Regent
beginning in September 2017.
The elements of a contract are the same whether the contract is written or oral.
Critchfield v. Smith, 151 S.W.3d 225, 233 (Tex. App.—Tyler 2004, pet. denied). The existence
of an oral contract may be proved by circumstantial as well as direct evidence. Harris v.
Balderas, 27 S.W.3d 71, 77 (Tex. App.—San Antonio 2000, pet. denied). We look to the
communications between the parties and to the acts and circumstances surrounding those
communications. Id.
Benton argues that the acts and circumstances indicate that his communication with
Shawn Kaemmerling in late 2017 confirmed this was a “direct pay” job under the parties’ course
of dealing and that Contractor’s had an agreement with Regent that Regent would pay
Contractor’s directly for materials on the project. Kaemmerling is employed by Contractor’s as
the plant manager at the Lufkin plant. Benton testified in his deposition that he had
conversations with Kaemmerling during the project, and Kaemmerling told Benton that
Contractor’s had an agreement with Regent for Regent to pay Contractor’s directly for the
materials used on the Pinnacle project. While Benton acknowledges that Kaemmerling denies
making this representation, he argues that the documentary evidence supports his testimony.
Benton points to invoices he sent directly to Regent and the checks issued by Regent to
Contractor’s, together with the fact that Benton stopped paying Contractor’s after the outset of
the job and Contractor’s made no demands for payment until 2018. Benton argues that these
circumstances establish a disputed issue of material fact and therefore, summary judgment in
favor of Contractor’s was improper.
In our de novo review of the trial court’s summary judgment, we consider all the
evidence in the light most favorable to Benton, crediting evidence favorable to him if reasonable
jurors could, and disregarding contrary evidence unless reasonable jurors could not. Mack
Trucks, Inc., 206 S.W.3d at 582. The evidence raises a genuine issue of fact if reasonable and
5
fair-minded jurors could differ in their conclusions in light of all of the summary-judgment
evidence. Goodyear Tire, 236 S.W.3d at 755. Contractor’s motion for summary judgment
stated as follows:
Regent...was the general contractor on the construction of Pinnacle Senior Living in
Lufkin, Texas. On August 6, 2017, Regent hired [Benton] as a subcontractor to provide concrete
services for the construction of Pinnacle Senior Living. On August 23, 2017, [Benton] ordered
premixed concrete, construction supplies, and other materials from [Contractor’s]. [Contractor’s]
provided all materials as requested, in a timely and prompt manner. [Contractor’s] provided
services to [Benton] starting on August 23, 2017 until December 12, 2017. During this time
period, [Contractor’s] provided $389,211.66 worth of construction materials and concrete to
[Benton].
Under the terms of their oral agreement, [Benton] was to pay [Contractor’s] within 30
days of receiving the concrete and supplies provided. Originally, [Benton] paid the first $5,774.71
owed to [Contractor’s] under the contract. However, after paying the $5,774.71, [Benton] never
directly paid [Contractor’s] again for the concrete and supplies for the Pinnacle Senior Living job.
Rather, Regent issued checks payable to [Contractor’s] in the amounts of $17,439.97 and
$57,987.67 for concrete suppled in August and September 2017. These checks were given to
[Benton] who later forwarded them to [Contractor’s].
(internal citations omitted). In response to this motion, Benton stated as follows:
Regent Construction Group, LLC (“Regent”) was the general contractor on the
construction of Pinnacle Senior Living Center (“Project”) in Lufkin, Angelina County, Texas. On
August 6, 2017, Regent hired [Benton] as a subcontractor to provide concrete services for the
construction of Pinnacle Senior Living Center. [Benton] ordered premixed concrete, construction
supplies, and other materials from Plaintiff, Contractor’s Supplies, Inc. [Contractor’s] provided an
accounting of their invoices for supplies with their petition.
[Benton] paid the first $5,774.71 owed to [Contractor’s] under the invoices as indicated
on Ex N. Thereafter, [Contractor’s] and [Benton] modified any agreement for payment of the
concrete and concrete supplies in that [Contractor’s] would start receiving direct payment from
Regent’s.
Further, after the first draw, [Benton] paid for the concrete as indicated on Ex. N,
however, after that [Contractor’s] made a direct payment agreement with Regent’s according to
Shawn Kaemmerling, an employee of [Contractor’s]. [Benton] made no further payments, since
he relied on what Mr. Kaemmerling had told him and believed he was no longer responsible for
the payment of the concrete and the concrete supplies. Further, [Contractor’s] accounting shows
three payments by Regent to [Contractor’s] as payment for concrete and supplies.
(internal citations omitted). We agree with Contractor’s that Benton conceded the existence of a
valid contract between the parties. Moreover, as previously discussed, the first element of a
breach of contract claim is the existence of a valid contract. Prime Prods., Inc., 97 S.W.3d at
636. It is clear from both parties’ statement of facts in their motions and responses that
6
Contractor’s provided materials to Benton for the Pinnacle project and Benton accepted and
partially paid for the materials. Benton argues that his alleged communications with
Kaemmerling, in addition to Regent’s direct payments to Contractor’s and Contractor’s delay in
collecting from Benton creates a question of material fact with respect to whether the parties had
a meeting of the minds on the essential terms. We disagree.
Whether the parties had a meeting of the minds must be resolved utilizing an objective
standard; we consider the meaning reasonably conveyed by what the parties said and did, and not
on their subjective state of mind. Parker Drilling Co. v. Romfor Supply Co., 316 S.W.3d 68, 73
(Tex. App.—Houston [14th Dist.] 2010, pet. denied). “We view the conduct and circumstances
surrounding the transaction from a reasonable person’s interpretation at that particular point in
time.” Id. A contract also must be “sufficiently definite to confirm that both parties actually
intended to be contractually bound.” Fischer v. CTMI, L.L.C., 479 S.W.3d 231, 237 (Tex.
2016). “To be enforceable, a contract must address all of its essential and material terms with ‘a
reasonable degree of certainty and definiteness.’” Id. (quoting Pace Corp. v. Jackson, 284
S.W.2d 340, 345 (Tex. 1955)). Whether a particular contractual term is essential, or material is a
question of law. Sharifi v. Steen Auto., LLC, 370 S.W.3d 126, 142 (Tex. App.—Dallas 2012,
no pet.).
Benton does not specifically identify which essential term is missing from the oral
contract, but we assume from the context that he is referring to whether he, Regent, or someone
else would ultimately be responsible for payment of the supplies provided by Contractor’s.
Looking to the communications between the parties and the acts and circumstances surrounding
those communications at the time the parties entered into the oral contract, we determine that a
meeting of the minds on the essential terms occurred. Cf. Bowles Const. Co. v. Bridwell, No.
11-02-00079-CV, 2002 WL 32344569, at *2 (Tex. App.—Eastland Nov. 7, 2002, no pet.) (op.)
(“The testimony concerning the communications and circumstances existing at the time the oral
contract was entered supports a finding that the contract related to dirt only.”) (emphasis added).
Benton’s evidence, including his communications with Kaemmerling, Regent’s payments to
Contractor’s, and Contractor’s delay in collecting from Benton are all communications, acts, or
circumstances that arose after the initial contract was formed. As discussed above, Benton
ordered premixed concrete and other supplies, Contractor’s delivered the supplies, and Benton
initially paid for the supplies. Viewing the conduct and circumstances of the parties at the time
7
Benton ordered the supplies, from a reasonable person’s objective point of view, it is clear that
Benton agreed to pay for the supplies. See Parker Drilling Co., 316 S.W.3d at 73. Therefore,
we overrule his first issue.
Affirmative Defenses
In general, a moving plaintiff is not under any obligation to negate a defendant’s pleaded
affirmative defenses. Tesoro Petroleum Corp. v. Nabors Drilling USA, Inc., 106 S.W.3d 118,
124 (Tex. App.—Houston [1st Dist.] 2002, pet. denied). Rather, an affirmative defense only
prevents the granting of summary judgment if each element of the affirmative defense is
supported by summary judgment evidence. Kirby Expl. Co. v. Mitchell Energy Corp., 701
S.W.2d 922, 926 (Tex. App.—Houston [1st Dist.] 1985, writ ref’d n.r.e.). If the defendant
moves for summary judgment on his affirmative defense, he bears the burden to conclusively
prove each element of the affirmative defense to be entitled to summary judgment. See Am.
Tobacco Co., Inc. v. Grinnell, 951 S.W.2d 420, 425 (Tex. 1997) (defendant carried burden of
conclusively proving pre-emption defense in its summary judgment motion). However, when, as
here, a defendant only seeks to survive summary judgment based on an affirmative defense, he
must do no more than raise a fact issue as to each element of the defense. See Moore Burger,
Inc. v. Phillips Petroleum Co., 492 S.W.2d 934, 937 (Tex. 1972).
Benton argues that the trial court erred in granting summary judgment in favor of
Contractor’s because he raised a fact issue as to each element of the affirmative defenses of
modification, estoppel/quasi-estoppel, accord and satisfaction/novation, and the failure to
mitigate damages. Benton relies on Kaemmerling’s alleged representations to argue that he
established a fact issue with respect to his modification, estoppel, and accord and satisfaction
defenses. Benton relies on Contractor’s failure to timely file statutory liens for the materials it
supplied to argue it created a fact issue with respect to his failure to mitigate damages defense.
Modification
Contract modification is an affirmative defense. Arthur J. Gallagher & Co. v. Dieterich,
270 S.W.3d 695, 701 (Tex. App.—Dallas 2008, no pet.). Modification of a contract is some
change in an original agreement that introduces a new or different element into the details of the
contract but leaves its general purpose undisturbed. In re F.C. Holdings, Inc., 349 S.W.3d 811,
815 (Tex. App.—Tyler 2011, no pet.).
8
Benton argues that “there is evidence of a modification of the agreement to direct pay by
Regent Construction.” In support of this argument, he cites to his own deposition testimony:
Benton: And I discussed that with the plant manager, Shawn Kaemmerling, after we
finally got our first payment. I paid them that first month that I had drawn on. And beyond that I
think Shawn had called Regent, Shawn or someone else had called Regent, and they had discussed
being paid directly. And from that point on they started sending checks to Contractor’s Supplies.
Counsel: All right. So it’s your recollection that after the first check that you received –
first progress payment and you paid Contractor's Supplies, after that Regency (sic) was paying
Contractor’s Supplies directly?
Benton: Correct, according to Shawn Kaemmerling, who is the manager at Contractor’s
Supplies.
Counsel: Okay. That’s what he told you?
Benton: Shawn and I would have lunch nearly every month and discuss this project
because it was late in payment. And you have time guidelines that fall on the 15th of the month, as
far as filing a notice of intent to lien or a notice of filing a lien.
And I started prompting Shawn to make sure that he filed his notices of intent on time, on
the 13th or 14th of every month. And on the second draw Shawn told me that he had – he had
received a check from them and we had already discussed that that would be all right with me if
they paid him direct and I had told him it was.
And he told me, “I received a check from them. They’re going to pay. It’s not going to
be a problem.” And so he didn’t seem worried about it.
...
Counsel: Is it your understanding from talking with Shawn Kaemmerling that going
forward from November on they were supposed to be paid directly by Regent?
Benton: Shawn told me he had discussed with Regent that they were going to pay them. I
think that was his words almost verbatim. And he wasn't worried about it. And as far as I was
concerned, I was done with paying these. They were paying for it, so –
...
Counsel: All right. Did you ever see a written agreement that reflects what you testified
to; that Regent agreed to pay Contractor’s Supplies directly for the concrete?
Benton: No, I did not.
Counsel: Okay.
Benton: I had Shawn Kaemmerling’s word that he called them and they were paying
Contractor’s Supplies.
In short, Benton testified that Kaemmerling told him that Contractor’s contacted Regent
and Regent had agreed to pay Contractor’s directly. However, Kaemmerling’s statements do not
reflect an agreement between Benton and Contractor’s to discharge Benton’s obligation to pay
9
for the materials he ordered in favor of collecting directly from Regent. Kaemmerling’s alleged
statements only indicate that Contractor’s successfully attempted to collect some of the money it
was owed from Regent directly. Nothing in Kaemmerling’s alleged statements, if true, indicate
an intent on behalf of the evidence in Contractor’s to discharge Benton from his obligation to pay
for the materials. Thus, viewing the light most favorable to Benton, we must still conclude that
the trial court correctly found that he failed to produce more than a scintilla of evidence on his
affirmative defense of modification. See TEX. R. CIV. P. 166a(i); Johnson, 73 S.W.3d at 206–
08.
Quasi-Estoppel 1
Quasi-estoppel is an affirmative defense that precludes a party from asserting, to
another’s disadvantage, a right inconsistent with a position previously taken. Lindley v.
McKnight, 349 S.W.3d 113, 131 (Tex. App.—Fort Worth 2011, no pet.). The defense applies
when it would be unconscionable to allow a person to maintain a position inconsistent with one
to which he acquiesced or from which he accepted a benefit. Id. Thus, quasi-estoppel forbids a
party from accepting the benefits of a transaction and then subsequently taking an inconsistent
position to avoid corresponding obligations or effects. Id.
Benton argues that
[He] relied on the representation made to him by Shawn Kaemmerling related to receipt of
payment and the manner that Contractor’s Supplies, Inc. would be paid on the project. These facts,
at a minimum, provide summary judgment evidence that under Texas Law Contractor’s Supplies
should be estopped from seeking payment From Mr. Benton instead of Regent.
...
Here, Contractor’s Supplies should be estopped from seeking to recover the remaining balance
owed from Mr. Benton after previously taking the position that general contractor Regent
Construction would pay for concrete directly and communicating that position to Mr. Benton.
[Benton] has presented evidence (1) that Contractor’s Supplies accepted a benefit under a
transaction—in that it began accepting payments directly from general contractor Regent
Construction; and (2) also that position was inconsistent with the initial arrangement whereby Mr.
Benton paid for Contractor’s Supplies’ invoices himself. (3) It is unconscionable for Contractor’s
Supplies to remain silent on the outstanding amounts for roughly a year and pursue litigation
against Mr. Benton after representing an agreement for direct payment from Regent Construction,
particularly when Mr. Benton had already suffered a significant loss for the balance of the Project.
1
Benton entitled this section of his brief “estoppel/quasi-estoppel” but only argued quasi estoppel.
Contractor’s recognizes this fact in its brief and responded to Benton’s quasi-estoppel arguments. In reply, Benton
countered Contractor’s quasi-estoppel arguments, but did not argue estoppel. Therefore, we only consider quasi-
estoppel. See TEX. R. APP. P. 38.1 (i) (“The brief must contain a clear and concise argument for the contentions
made, with appropriate citations to authorities and to the record.”).
10
We disagree. Cf. Lopez v. Munoz, Hockema & Reed, L.L.P., 22 S.W.3d 857, 864 (Tex. 2000)
(plaintiffs’ initial acceptance of lesser portion of settlement not inconsistent with later assertion
that they were entitled to more).
As stated above, Contractor’s sought and recovered payment directly from Regent for
some of the supplies it provided to Benton. However, none of the facts Benton alleges, even if
taken as true, would demonstrate that Contractor’s took a position inconsistent with the initial
contract. Simply put, Contractor’s attempt to recover directly from Regent, at Benton’s
suggestion, is not inconsistent with its original contract with Benton. Moreover, the doctrine of
quasi-estoppel forbids a party from accepting the benefits of a transaction and subsequently
taking an inconsistent position to avoid corresponding obligations or effects. McKnight, 349
S.W.3d at 131. Benton has not argued nor does the evidence disclose that Contractor’s accepted
payments from Regent to avoid a corresponding obligation or effect, therefore the doctrine is
inapplicable. See id. Additionally, Benton failed to offer authority to support his contention that
it is unconscionable for Contractor’s to remain silent on the outstanding amounts for roughly a
year and pursue litigation against Benton after Kaemmerling represented to Benton that there
was a direct pay arrangement between Contractor’s and Regent. See TEX. R. APP. P. 38.1(i).
Nor is this Court aware of any authority that would support such a contention. For the above
reasons, viewing the evidence in the light most favorable to Benton, we conclude that the trial
court did not err in finding that Benton failed to produce more than a scintilla of evidence on his
affirmative defense of quasi-estoppel. See TEX. R. CIV. P. 166a(i); Johnson, 73 S.W.3d at 206–
08.
Accord and Satisfaction/Novation
An “accord” is a new contract to discharge an existing obligation. Honeycutt v.
Billingsley, 992 S.W.2d 570, 576 (Tex. App.—Houston [1st Dist.] 1999, pet. denied) (citing
Jenkins v. Henry C. Beck Co., 449 S.W.2d 454, 455 (Tex. 1969); Bueckner v. Hamel, 886
S.W.2d 368, 372 (Tex. App.—Houston [1st Dist.] 1994, writ denied)). “Satisfaction” is the
performance of the new contract. Billingsley, 992 S.W.2d at 576 (citing City of Houston v. First
City, 827 S.W.2d 462, 472 (Tex. App.—Houston [1st Dist.] 1992, writ denied)). In the new
contract: (1) the parties agree to discharge the existing obligation; (2) the parties agree that one
party will perform and the other will accept something different from what each expected from
the existing obligation; (3) the parties unmistakably communicate that the different performance
11
will discharge the existing obligation; (4) the agreement to discharge the existing obligation is
plain, definite, certain, clear, full, explicit, and not susceptible of any other interpretation; and (5)
the parties’ agreement must be accompanied by acts and declarations that the creditor is “bound
to understand.” Billingsley, 992 S.W.2d at 576 (citing Jenkins, 449 S.W.2d at 455).
An accord and satisfaction may work a novation. Billingsley, 992 S.W.2d at 576. In an
accord and satisfaction, it is generally the performance of the new obligation, and not the
obligation itself, that is considered a novation. Id. (citing DoAll Dallas Co. v. Trinity Nat’l
Bank, 498 S.W.2d 396, 400 (Tex. Civ. App.—Texarkana 1973, writ ref’d n.r.e.)). An agreement
that modifies an existing obligation will result in both an accord and satisfaction and a novation
if the parties intended to extinguish the existing obligation. Billingsley, 992 S.W.2d at 576.
Thus, the common requirement under both novation and accord and satisfaction is that
the new contract must extinguish or excuse the duty to perform the existing obligation. Id.
Under either theory, the parties must intend to release the other from a prior obligation and to
assume a new one. Id. Because the same element of both defenses (i.e., whether there was an
extinguishment of prior obligations) is at issue in this case, we will discuss novation and accord
and satisfaction together.
Benton argues that the summary judgment evidence related to his communications with
Kaemmerling create a genuine issue of material fact as to whether there was an accord and
satisfaction/novation. According to Benton, “[t]he new arrangement consummated by an oral
agreement constitutes the modification of an existing agreement that extinguishes the existing
obligation.” As previously discussed, viewing the evidence in the light most favorable to
Benton, the alleged statements made by Kaemmerling did not indicate that Contractor’s was
extinguishing Benton’s obligation to pay for the materials he ordered. If true, Kaemmerling’s
statements to Benton merely indicated that Contractor’s would try to collect the money it was
owed directly from Regent, not that Contractor’s would no longer attempt to collect the monies it
was owed by Benton. Thus, we conclude that the trial court correctly found that Benton failed to
produce more than a scintilla of evidence on its affirmative defense of accord and
satisfaction/novation. See TEX. R. CIV. P. 166a(i); Johnson, 73 S.W.3d at 206–08.
Failure to Mitigate Damages
The doctrine of mitigation of damages, sometimes referred to as the doctrine of avoidable
consequences, requires an injured party to use reasonable efforts to avoid or prevent losses. E.L.
12
& Assocs. v. Pabon, 525 S.W.3d 764, 768 (Tex. App.—Houston [14th Dist.] 2017, no pet.)
(citing Pulaski Bank & Trust Co. v. Tex. Am. Bank/Fort Worth, N.A., 759 S.W.2d 723, 735
(Tex. App.—Dallas 1988, writ denied)). In the context of a breach of contract case, the doctrine
has been stated as follows: “Where a party is entitled to the benefits of a contract and can save
himself from the damages resulting from its breach at a trifling expense or with reasonable
exertions, it is his duty to incur such expense and make such exertions.” Pabon, 525 S.W.3d at
768 (citing Great Am. Ins. Co. v. N. Austin Mun. Util. Dist. No. 1, 908 S.W.2d 415, 426 (Tex.
1995) (quoting Walker v. Salt Flat Water Co., 96 S.W.2d 231, 232 (1936)).
Benton states that “[d]espite reminders from [him], [Contractor’s] failed to serve lien
notices on time which apparently prevented further payment from Regent Construction.” Benton
argues that he created a fact issue with respect to his defense that Contractor’s failed to mitigate
its damages because he showed that Contractor’s failed to timely serve lien notices related to the
project. He further argues that “[Contractor’s] summary judgment briefing...cites just one
unpublished case for the proposition that Texas law does not recognize the failure to pursue liens
as a failure to mitigate.” See Kondos Entm’t, Inc. v. Quinney Elec., Inc., No. 04-96-00251-CV,
1999 WL 1261455 (Tex. App.—San Antonio Dec. 29, 1999, no pet.) (op.).
In Kondos, Quinney was retained by Kondos Entertainment, Inc. (Kondos) to do
electrical work for the construction of a night club in San Antonio, Texas. Kondos
Entertainment, Inc. v. Quinney Elec., Inc., 948 S.W.2d 820, 821 (Tex. App.—San Antonio
1997), rev’d, 988 S.W.2d 212 (Tex.1999). When it was not paid, Quinney sued Kondos, Jay
Snyder, a representative of Kondos, and V-Ball, Inc. (V-Ball), the company named on the checks
Snyder used to pay Quinney’s invoices. Id. at 822. Four months after suit was filed, V-Ball
filed for bankruptcy. Id. Quinney filed a proof of claim for $83,991.32 with the bankruptcy
court which was accepted as a general unsecured claim and paid. Id. Quinney pursued its claim
in state court against Kondos and Snyder, ultimately securing a judgment of $83,991.21 in actual
damages, $18,839.13 in prejudgment interest, $20,000.00 in attorney’s fees, and $978.00 in court
costs. Id. Post-judgment interest on the foregoing sums was also awarded. Id. The court
further ordered the $83,991.32 awarded to Quinney in the bankruptcy proceedings be credited to
the amount in the judgment, ultimately resulting in a judgment against Kondos and Snyder in the
unsatisfied amount of $40,083.58, plus post-judgment interest, which represented primarily the
prejudgment interest, attorney’s fees, and court costs not included in the amount paid in
13
connection with the bankruptcy. Id. The Fourth Court of Appeals ultimately held that Quinney
was collaterally estopped from bringing suit because the specific issues central to Quinney’s
claims were previously litigated in the bankruptcy proceeding. Id. at 824-25. The Texas
Supreme Court reversed the Fourth Court’s decision and remanded the case to the Fourth Court
to consider Kondos’ and Snyder’s additional points of error.
In one of those additional points of error, Kondos and Snyder argued that Quinney failed
to mitigate damages because Quinney failed to file a materialman’s lien, which would have
resulted in its claim being secured against V-Ball in bankruptcy and allowing it to recover
interest and attorney’s fees against V-Ball. Kondos, 1999 WL 1261455, at *3. The court
rejected this argument because the attorney’s fees and interest could not have been “avoided,”
and the lien simply would have enabled Quinney to collect the same amount from a different
source. Id. at *3. The court went on to state that “Kondos and Snyder are really contending that
Quinney’s filing of the lien might have minimized the ‘loss’ to Kondos and Snyder, not the
damages to Quinney.” The court held that “[t]he doctrine of mitigation does not apply in that
manner.” Id. at *4.
Here, Benton argues that the factual scenario in Kondos is distinguishable from this case
because
[t]he Kondos scenario is talking about attorney’s fees and interest that are not even damages that
could have been awarded in the original breach of contract case. That is why the Kondos opinion
says that such damages would have been “avoided.” There is reason Contractor’s Supplies cannot
point to any other case for the legal proposition that failing to send a lien notice absolutely cannot
constitute a failure to mitigate damages—because it is misreading the Kondos case and attempting
to apply it overly broadly.
We disagree with Benton’s interpretation of the Kondos court’s holding and reasoning.
The operative reasoning behind the Kondos holding is that the filing of a lien did nothing to
avoid Quinney’s damages; the only effect of the lien would allow Quinney to collect his
damages from another source. Id. at *3. The lien might have allowed Quinney to collect the
damages from a different source and minimized Kondos’ and Snyder’s exposure, but it would
not have avoided Quinney’s damages, and therefore does not implicate the mitigation of
damages doctrine. See Id. at *4.
We find the Kondos holding persuasive in our analysis of this issue. Here, Contractor’s
damages would not have been avoided had it correctly and timely filed its lien. Rather, the lien
14
would have allowed Contractor’s to collect its damages from another source, Regent. This
would have minimized Benton’s exposure but would have done nothing to “avoid” Contractors’
damages. See Id. at *4. Thus, we conclude that the trial court correctly granted Contractor’s no
evidence summary judgment motion on Benton’s affirmative defense that Contractor’s failed to
mitigate its damages. See TEX. R. CIV. P. 166a(i); Johnson, 73 S.W.3d at 206–08.
Conclusion
Accordingly, for the above reasons, we overrule issue two.
DISPOSITION
Having overruled both of Benton’s issues, we affirm the trial court’s judgment.
GREG NEELEY
Justice
Opinion delivered October 6, 2021.
Panel consisted of Worthen, C.J., Hoyle, J., and Neeley, J.
15
COURT OF APPEALS
TWELFTH COURT OF APPEALS DISTRICT OF TEXAS
JUDGMENT
OCTOBER 6, 2021
NO. 12-20-00207-CV
MARK BENTON, INDIVIDUALLY AND D/B/A MEBCO CONTRACTING,
Appellant
V.
CONTRACTOR’S SUPPLIES, INC.,
Appellee
Appeal from the 159th District Court
of Angelina County, Texas (Tr.Ct.No. CV-00387-19-07)
THIS CAUSE came to be heard on the appellate record and briefs filed
herein, and the same being considered, it is the opinion of this court that there was no error in the
judgment.
It is therefore ORDERED, ADJUDGED and DECREED that the judgment of
the court below be in all things affirmed, all costs of this appeal are assessed against the
Appellant, MARK BENTON, INDIVIDUALLY AND D/B/A MEBCO CONTRACTING,
and that this decision be certified to the court below for observance.
Greg Neeley, Justice.
Panel consisted of Worthen, C.J., Hoyle, J., and Neeley, J.
16
Poursuivez vos recherches dans ChatGPT ou Claude
Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.