CourtListener 10152101•The Charleston County School District v. Charleston County
The Charleston County School District v. Charleston County
CourtListener 10152101Scctapp15 déc. 2021
Texte intégral
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE
CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
EXCEPT AS PROVIDED BY RULE 268(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
The Charleston County School District, Appellant,
v.
Charleston County, South Carolina; The Charleston
County Board of Zoning Appeals; and Joel Evans in his
capacity as Director of the Charleston County Zoning
and Planning Department, Respondents.
Appellate Case No. 2019-000125
Appeal From Charleston County
Jennifer B. McCoy, Circuit Court Judge,
Unpublished Opinion No. 2021-UP-449
Heard November 3, 2021 – Filed December 15, 2021
AFFIRMED
Jamie A. Khan and Ross A. Appel, both of McCullough
Khan, LLC, of Mount Pleasant, for Appellant.
Jeremy E. Bowers, of Barnwell Whaley Patterson &
Helms, LLC, of Charleston; and Deputy County
Attorneys Bernard E. Ferrara, Jr. and Edward L. Knisley,
Jr., both of Charleston, all for Respondents.
PER CURIAM: In this civil matter, the Charleston County School District (the
District) appeals the circuit court's order affirming the findings of the Charleston
County Board of Zoning Appeals (the BZA), which affirmed the administrative
decision of the Charleston County Planning Director (the Planning Director) to
deny the District's request seeking an extension to complete the conditions of its
site plan approval issued pursuant to the Charleston County Zoning and Land
Development Regulations Ordinance (the ZLDR). We affirm.
We find the circuit court did not err in affirming the BZA's finding that the District
failed to timely appeal the Planning Director's decision. See Boehm v. Town of
Sullivan's Island Bd. of Zoning Appeals, 423 S.C. 169, 182, 813 S.E.2d 874, 880
(Ct. App. 2018) (providing that this court applies the same standard of review as
the circuit court in matters involving appeals from the BZA); id. ("In reviewing the
questions presented by the appeal, th[is] court shall determine only whether the
decision of the [BZA] is correct as a matter of law." (quoting Austin v. Bd. of
Zoning Appeals, 362 S.C. 29, 33, 606 S.E.2d 209, 211 (Ct. App. 2004)); S.C. Code
Ann. § 6-29-840(A) (Supp. 2020) ("The findings of fact by the board of appeals
must be treated in the same manner as a finding of fact by a jury, and the court may
not take additional evidence."). The Planning Director denied the District's request
for an extension via letter to ADC Engineering, Inc. on February 28, 2018.
Therefore, the District was required to file its application for an appeal to the BZA
no later than March 30, 2018. See ZLDR § 3.7 (addressing the Planning
Department's development procedures regarding site plan review); ZLDR § 3.7.8
("Appeals shall be processed in accordance with the procedures of Article
3.13 . . . ." (emphasis added)); ZLDR § 3.13.3 ("Appeals of Administrative
Decisions to grant or deny a Zoning Permit shall be filed within [thirty] calendar
days from the date of the Administrative Decision." (emphasis added)). However,
the District did not file its appeal until April 18, 2018. Thus, the BZA did not err
in finding the District failed to comply with the filing deadlines established within
the ZLDR. Although the District contends its appeal to the BZA was timely
pursuant to subsection 6-29-800(B) of the South Carolina Code (Supp. 2020), 1 we
find the filing deadline contained within subsection 6-29-800(B) is not triggered
because the ZLDR contains a specific time limit for appealing decisions regarding
site plan review.
1
See § 6-29-800(B) (providing that appeals to the BZA "must be taken within a
reasonable time, as provided by the zoning ordinance . . . . If no time limit is
provided, the appeal must be taken within thirty days from the date the appealing
party has received actual notice of the action from which the appeal is taken"
(emphasis added)).
In its application for an appeal to the BZA and in its appeals going forward, the
District asserts the Planning Director additionally denied the extension request for
the Project based on a "reinterpretation" of the definition of accessory use;
however, the February 28, 2018 denial makes no such assertion. Rather, the
Planning Director explained that since the February 9, 2017 approval had been
rescinded for failing to complete the stated conditions of approval, the site plan
review process for the Project would need to be repeated should the District wish
to further pursue the Project. The Planning Department also notified the District of
this procedure in the February 9, 2017 approval. In his March 13, 2018 email, the
Planning Director clearly stated the interpretation would be applied to any future
applications for site plan approval for the Project. Therefore, the District's
challenge to the alleged "reinterpretation" is not ripe for review. See Sloan v.
Greenville County, 356 S.C. 531, 547, 590 S.E.2d 338, 346 (Ct. App. 2003) ("The
concept of justiciability encompasses the doctrines of ripeness, mootness, and
standing."); Jowers v. S.C. Dep't of Health & Env't Control, 423 S.C. 343, 353, 815
S.E.2d 446, 451 (2018) ("We have explained ripeness by defining what is not ripe,
stating 'an issue that is contingent, hypothetical, or abstract is not ripe for judicial
review.'" (quoting Colleton Cnty. Taxpayers Ass'n v. Sch. Dist. of Colleton Cnty.,
371 S.C. 224, 242, 638 S.E.2d 685, 694 (2006))).
Based on the foregoing, the order of the circuit court is
AFFIRMED. 2
LOCKEMY, C.J., and WILLIAMS and MCDONALD, JJ., concur.
2
Because our finding that the District failed to timely appeal the Planning
Director's decision is dispositive, we decline to address the District's remaining
arguments on appeal. See Futch v. McAllister Towing of Georgetown, Inc., 335
S.C. 598, 613, 518 S.E.2d 591, 598 (1999) (holding an appellate court need not
review remaining issues when its determination of a prior issue is dispositive of the
appeal).
Poursuivez vos recherches dans ChatGPT ou Claude
Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.