McIntire v. Seaquest Development Company

CourtListener 10151223Scctapp31 déc. 2019

Texte intégral

THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE
CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING
EXCEPT AS PROVIDED BY RULE 268(D)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals

Andrew and Kimberly McIntire, Appellants,

v.

Seaquest Development Company, Inc.; Red Bay
Constructors Corp.; Benzenberg Custom Cabinets, Inc.;
Jonathan Marshall Construction; Coastal Window &
Door Center of Charleston, LLC; Carolina Window &
Millwork, LLC n/k/a Carolina Window & Millwork-
Omni Glass Industries, LLC; Southcoast Exteriors, Inc.;
Michael Casteen d/b/a Casteen Custom Cabinets; Quality
Cedar Products, Inc. of Michigan d/b/a Michigan Prestain
Co.; Coastal Plumbing & Gas, LLC; Foam Insulation Co.
Inc.; Jerry Comer d/b/a Jerry's Tile & Marble, LLC;
Lowcountry Fireplaces, Inc; Carolina Pest Solutions,
Inc.; New South Construction Supply, LLC, Defendants,

Of which Seaquest Development Company, Inc. is the
Respondent.

Appellate Case No. 2017-001270

Appeal From Charleston County
Jean Hoefer Toal, Circuit Court Judge

Opinion No. 2019-UP-413
Heard November 5, 2019 – Filed December 31, 2019

REVERSED AND REMANDED
Andrew K. Epting, Jr., Jaan Gunnar Rannik, and
Michelle N. Endemann, all of Andrew K. Epting, Jr.,
LLC, of Charleston, for Appellant.

Edward D. Buckley, Jr., Stephen Lynwood Brown, Jason
Alan Daigle, and Russell Grainger Hines, all of Young
Clement Rivers, LLP, of Charleston, for Respondent.

PER CURIAM: In this residential construction defect case, Andrew and
Kimberly McIntire (the McIntires) appeal from the trial court's denial of their
motion to compel arbitration with general contractor Seaquest Development
Company, Inc. (Seaquest). The McIntires argue the trial court erred in (1) not
ordering the dispute to arbitration when the parties' contract contained a valid
arbitration clause; (2) addressing issues of statute of limitations, right to cure, and
waiver when the court's sole jurisdiction was to decide the question of arbitrability;
and (3) dismissing the case for failure to comply with the South Carolina Notice
and Opportunity to Cure Construction Dwelling Defects Act ("Right to Cure
Act").1 We reverse and remand the case for arbitration.

FACTS

The McIntires entered into a written contract with Seaquest for the construction of
a home in Mount Pleasant in August 2007. A certificate of occupancy was issued
in September 2008. On April 8, 2016, the McIntires filed an action against
Seaquest, alleging defects in the home's construction and asserting causes of action
for negligence and gross negligence, breach of warranty of habitability, negligent
misrepresentation and constructive fraud, and breach of warranty of good and
workmanlike work. Prior to bringing the action, the McIntires had discovered a
number of alleged construction defects in their home and hired experts and began
repairs without notifying Seaquest. The repairs were substantially completed
before the lawsuit was filed or were completed soon thereafter.

On June 17, 2016, Seaquest filed a motion to dismiss or stay proceedings, arguing
the McIntires failed to comply with the Right to Cure Act. On July 27, 2016, the
McIntires filed a motion to stay and compel arbitration. The McIntires also filed a

1
S.C. Code Ann. § 40-59-810, et seq. (2011).
motion on August 15, 2016, seeking an order staying their responses to Seaquest's
requests for admission until the court ruled on Seaquest's motion. After a hearing
on October 13, 2016, the trial court granted Seaquest's motion to dismiss and
denied the McIntires' motion to compel arbitration. This appeal follows.

STANDARD OF REVIEW

Unless the parties otherwise provide, the question of the arbitrability of a claim is
an issue for judicial determination. Zabinski v. Bright Acres Assocs., 346 S.C. 580,
596, 553 S.E.2d 110, 118 (2001). Determinations of arbitrability are subject to de
novo review, but if any evidence reasonably supports the trial court's factual
findings, this court will not overrule those findings. Stokes v. Metro. Life Ins. Co.,
351 S.C. 606, 609-10, 571 S.E.2d 711, 713 (Ct. App. 2002).

LAW/ANALYSIS

I. Arbitration

The McIntires argue the trial court erred in not ordering the dispute to arbitration
when the parties' contract contained a valid arbitration clause. We agree.

"The initial inquiry to be made by the trial court is whether an arbitration
agreement exists between the parties." Hous. Auth. of the City of Columbia v.
Cornerstone Hous., LLC, 356 S.C. 328, 334, 588 S.E.2d 617, 620 (Ct. App. 2003).
"Arbitration is available only when the parties involved contractually agree to
arbitrate." Towles v. United Healthcare Corp., 338 S.C. 29, 37, 524 S.E.2d 839,
843-44 (Ct. App. 1999). Arbitration will be denied if a court determines no
agreement to arbitrate existed. S.C. Code Ann. § 15-48-20(a) (2005) ("On
application of a party showing an agreement described in § 15-48-10, and the
opposing party's refusal to arbitrate, the court shall order the parties to proceed
with arbitration, but if the opposing party denies the existence of the agreement to
arbitrate, the court shall proceed summarily to the determination of the issue so
raised and shall order arbitration if found for the moving party, otherwise, the
application shall be denied."). "There is a strong presumption in favor of the
validity of arbitration agreements because both state and federal policy favor
arbitration of disputes." Simpson v. MSA of Myrtle Beach, Inc., 373 S.C. 14, 24,
644 S.E.2d 663, 668 (2007).
The written contract between the McIntires and Seaquest provides at the top of the
contract:

WARNING: THIS AGREEMENT [IS] SUBJECT TO
BINDING ARBITRATION IN THE STATE OF
SOUTH CAROLINA, CITY OF CHARLESTON,
UNDER THE SOUTH CAROLINA UNIFORM
ARBITRATION ACT (CODE SEC. 15-48-10, ET
SEQ.).

The contract further provides, "AIA Document A201 – 1997 General Conditions of
the Contract for construction is adopted in this document by reference." AIA
Document A201, section 4.6 states that "[a]ny Claim arising out of or related to the
Contract . . . shall . . . be subject to arbitration."

The right to enforce an arbitration clause may be waived. Rhodes v. Benson
Chrysler-Plymouth, Inc., 374 S.C. 122, 126, 647 S.E.2d 249, 251 (Ct. App. 2007).
In Rhodes, this court stated three factors our courts consider to determine if a party
waived its right to compel arbitration:

(1) whether a substantial length of time transpired
between the commencement of the action and the
commencement of the motion to compel arbitration; (2)
whether the party requesting arbitration engaged in
extensive discovery before moving to compel arbitration;
and (3) whether the non-moving party was prejudiced by
the delay in seeking arbitration. These factors, of course,
are not mutually exclusive, as one factor may be
inextricably connected to, and influenced by, the others.

Id.

"[T]o establish waiver, a party must show prejudice through an undue burden
caused by delay in demanding arbitration." Liberty Builders, Inc. v. Horton, 336
S.C. 658, 665, 521 S.E.2d 749, 753 (Ct. App. 1999). "To establish prejudice, the
non-moving party must show something more than 'mere inconvenience.'" Rhodes,
374 S.C. at 127, 647 S.E.2d at 251 (quoting Evans v. Accent Manufactured Homes,
Inc., 352 S.C. 544, 550, 575 S.E.2d 74, 76-77 (Ct. App. 2003)). "To ascertain
whether the non-moving party was prejudiced, our courts often examine whether
the party requesting arbitration took 'advantage of the judicial system by engaging
in discovery.'" Id. (quoting Evans, 352 S.C. at 548, 575 S.E.2d at 76). "'[A]
substantial length of time' varies from one case to the next, depending on the extent
of discovery conducted and the corresponding presence or absence of prejudice to
the party opposing arbitration." Id. at 126, 647 S.E.2d at 251. "Of course, cases do
not always fit neatly into clearly defined categories, which is why our law resists a
formulaic approach and motions to compel arbitration are resolved only after a
fact-intensive inquiry. Accordingly, each case turns on its particular facts." Id. at
127, 647 S.E.2d at 252.

The trial court found the McIntires had "engaged in extensive discovery in that
they retained forensic and construction liability and repair experts to investigate,
document, and repair the alleged defects at their house." The repairs to the
McIntires' home were substantially completed prior to the filing of the motion to
compel arbitration, which the court found resulted in material prejudice to
Seaquest because it precluded "Seaquest from investigating, inspecting, and/or
challenging the McIntires' claims." The trial court also found a "substantial
amount of time transpired between the time the McIntires engaged their experts
and the time they moved to compel arbitration."

The McIntires argue the trial court erred in finding they waived their arbitration
right because hiring a contractor to inspect and repair issues with their residence
does not amount to engaging in discovery. The McIntires also argue the trial court
erred in focusing on the amount of time between when the McIntires engaged their
experts and the filing of the motion to compel arbitration, instead of on the amount
of time between the filing of the suit and the filing of the motion as set forth in
Rhodes, 374 S.C. at 126, 647 S.E.2d at 251.

Based on our review, we find the evidence in the record does not support the trial
court's finding that the McIntires participated in discovery, much less "extensive
discovery," or retained "forensic and construction liability and repair experts."
Also, the McIntires moved to compel arbitration on July 27, 2016, two days after
they received notice the last defendant had been served with their complaint. 2 The
complaint was filed on April 8, 2016. Thus, we find a "substantial length of time"
did not occur between the commencement of the action and the commencement of
the motion to compel arbitration. Accordingly, we reverse on this issue and
remand the case for arbitration.

2
The McIntires' counsel told the court it took a while to serve all the defendants
because many of the defendant companies were out of business.
II. Jurisdiction and Right to Cure Act

The McIntires argue the trial court erred in addressing the issues of statute of
limitations, Right to Cure Act, and waiver when the court's sole jurisdiction was to
decide the question of arbitrability. The McIntires also argue the trial court erred
in dismissing the case for failure to comply with the Right to Cure Act.

Because we already determined the trial court erred in finding the McIntires
waived their arbitration right and remand for arbitration, we need not address these
issues. See Futch v. McAllister Towing of Georgetown, Inc., 335 S.C. 598, 613,
518 S.E.2d 591, 598 (1999) (holding an appellate court need not review remaining
issues when its determination of another issue is dispositive of the appeal).

CONCLUSION

Accordingly, the decision of the trial court is

REVERSED and REMANDED.

SHORT, THOMAS, and GEATHERS, JJ., concur.

Poursuivez vos recherches dans ChatGPT ou Claude

Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.