Holliday Construction, LLC v. George County, Mississippi

CourtListener 10629181Missctapp13 déc. 2022

Texte intégral

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI

NO. 2021-CA-00667-COA

HOLLIDAY CONSTRUCTION, LLC APPELLANT

v.

GEORGE COUNTY, MISSISSIPPI APPELLEE

DATE OF JUDGMENT: 05/18/2021
TRIAL JUDGE: HON. KATHY KING JACKSON
COURT FROM WHICH APPEALED: GEORGE COUNTY CIRCUIT COURT
ATTORNEYS FOR APPELLANT: SAMUEL C. KELLY
ALSTON FRANK LUDWIG
ATTORNEYS FOR APPELLEE: MICHAEL JAMES BENTLEY
ROBERT PAYNE SHEPARD
JAMES STEPHEN FRITZ JR.
NATURE OF THE CASE: CIVIL - CONTRACT
DISPOSITION: AFFIRMED - 12/13/2022
MOTION FOR REHEARING FILED:

BEFORE BARNES, C.J., McDONALD AND McCARTY, JJ.

McDONALD, J., FOR THE COURT:

¶1. Holliday Construction LLC (Holliday) appeals the George County Circuit Court’s

denial of compensatory damages after the court found that the County’s contract for

hurricane debris pickup with an out-of-state contractor was null and void. On appeal,

Holliday asserts that the circuit court’s decision not to award compensatory damages was

made without a substantial evidentiary basis and that a hearing should have been held to

determine Holliday’s compensatory damages. Finding no error, we affirm the circuit court’s

judgment.

FACTS AND PROCEDURAL HISTORY
¶2. On November 16, 2020, George County (the County) began soliciting proposals for

disaster debris removal and disposal services as the result of damage caused by Hurricane

Zeta. The County stated in its “Request For Proposals” (RFP) that the purpose of the RFP

and subsequent contracting activity was to secure the services of qualified, experienced

contractors who were capable of efficiently removing large volumes of disaster-generated

debris from a large area in a timely and cost-efficient manner and lawfully disposing of all

debris. The time for submitting proposals ended on December 4, 2020. The RFP did not

require proposers to have a certificate of responsibility.

A. Certificate of Responsibility

¶3. Mississippi Code Annotated section 31-3-21(1) (Rev. 2020) states:

It shall be unlawful for any person who does not hold a certificate of
responsibility issued under this chapter to submit a bid, enter into a contract,
or otherwise engage in or continue in this state in the business of a contractor,
as defined in this chapter.

“The public policy behind requiring a certificate of responsibility [is] to protect the public

from improper construction . . .” and to obtain for the public the best available price through

competitive bidding with honest, competent contractors. Ace Pipe Cleaning Inc. v. Hemphill

Const. Co. Inc., 134 So. 3d 799, 806 (¶30) (Miss. Ct. App. 2014) (citing Ground Control

LLC v. Capsco Indus. Inc., 120 So. 3d 365, 368 (¶8) (Miss. 2013)). Contractors obtain a

certificate of responsibility from the Mississippi State Board of Contractors (MSBOC) after

showing that they are competent to perform the work outlined in specific areas or

classifications. See Miss. Code Ann. § 31-3-13(a) (Rev. 2020).

No contract for public or private projects shall be issued or awarded to any
contractor who did not have a current certificate of responsibility issued by

2
said board at the time of the submission of the bid, or a similar certificate
issued by a similar board of another state which recognizes certificates issued
by said board. Any contract issued or awarded in violation of this section shall
be null and void.

Miss. Code Ann. section 31-3-15 (Rev. 2020).

B. Contents of George County’s RFP

¶4. The RFP also included a provision which informed proposers that the county reserved

the right to accept or reject any and all proposals. Specifically, the RFP stated:

The COUNTY reserves the right to accept or reject any or all proposals, with
or without cause, to waive technicalities, or to accept the proposals which, in
its sole judgment, best serves the interest of the COUNTY, or to award a
contract to the next most qualified proposers if a successful proposer does not
execute a contract within thirty (30) days after approval of the selection by the
COUNTY. The COUNTY has the right, to cancel a solicitation at any time
prior to approval of the award by the COUNTY.

In addition, under the “Evaluation and Contract Award” section, the RFP stated that the

County retained the option to waive any irregularity in any proposal, or reject any and all

proposals should it be deemed in the County’s best interest to do so. The RFP stated that the

“award will be made to one or more [p]roposers that the [County] determines can accomplish

the requirements set forth in the [RFP] packet in a manner most advantageous to the

[County], cost and other factors considered or to reject any and all proposals.”

¶5. The following criteria was used by the County staff to evaluate the proposals and

make a selection: (1) references from past projects of similar size and scope, (2)

qualifications and experience of key staff on similar projects, (3) knowledge of the County

and local emergency management needs, (4) cost of services offered, and (5) use of minority-

and women-owned business.

3
¶6. Each proposal submitted was also evaluated and ranked by an evaluation committee.

The contract was to be awarded to the most qualified proposer, per the following: “(1)

Contractor’s Experience/Past Performance (years of experience; similar size projects;

experience in debris removal and disposal) – weighted 30%, (2) Proposal/Individual

Credentials of Contractor and Team (key staff members; use of minority women owned

business; experience with [the Federal Emergency Management Agency (FEMA) or the

Mississippi Emergency Management Agency (MEMA)] programs/coordination - weighted

40%, and (3) Price – weighted 30%.”

¶7. The RFP also informed proposers that the project needed to be completed within a

certain time frame because FEMA declared that it would reimburse the county for seventy-

five percent of the hurricane clean-up costs if the project was completed by June 30, 2021.

C. Directives For Pricing

¶8. A “Contractor’s Price Proposal” packet was attached to the RFP as “Exhibit B,” which

contained a price proposal form for proposers to complete and submit to the county with total

bid amounts. It included the following provision: “This price proposal form must be fully

completed, signed, and submitted. No substitute forms will be accepted. Proposals

submitted without this fully completed price proposal will be rejected.” The price proposal

form also gave descriptions for the work that was to be done on the project as well as

assumed quantities for various categories of debris to be removed. Proposers were to

multiply their proposed unit price by the assumed quantity to generate an estimated price.

The unit price and price extension columns in the price proposal form were left blank for

proposers to fill in their estimated amounts.

4
¶9. On November 23, 2020, the County published Addendum 1 to the RFP which revised

the estimated quantity of debris listed under the assumed quantity column for certain

categories on the price proposal form. In the initial RFP, the assumed quantity for “site

management and grinding of eligible vegetative debris at a Debris Management Site (DMS)

provided by the contractor” was 50,000; however, Addendum 1 increased the assumed

quantity to 150,000. “Loading and hauling of eligible vegetative debris reduced by grinding

from DMS to an approved landfill” was increased from 12,500 to 38,000. In addition,

“disposal of eligible vegetative debris reduced by grinding at an approved landfill” also was

increased from 12,500 to 38,000.

D. County’s Selection of CTC’s Bid

¶10. On December 14, 2020, the Board of Supervisors considered and evaluated the

proposals received. Custom Tree Care Inc. (CTC), an out-of-state contractor, submitted a

total bid of $1,686,613, which the County considered to be the lowest and best bid received.

Holliday submitted the next lowest bid in the total amount of $2,352,050. However, it was

revealed much later in the court proceedings that CTC used the first page of the price

proposal form from the original RFP instead of the revised first page of the price proposal

form from Addendum 1, which had increased assumed quantities for three of the categories

of debris to be removed. This explained the disparity between CTC’s total bid amount and

Holliday’s total bid amount.1

1
Had CTC submitted the correct first page of the revised price proposal form
included in Addendum 1, its estimated total bid amount would have been $2,121,863, which
was still $230,187 lower than Holliday’s bid amount.

5
E. Holliday’s Protest and The Contract Award

¶11. On December 20, 2020, Holliday sent a letter to the county protesting the award of

the contract to CTC. Holliday asserted that CTC was not qualified nor entitled to the award

of the contract because CTC did not hold a certificate of responsibility issued by the MSBOC

and required by Mississippi Code Annotated section 31-3-15.2 Holliday suggested that the

County obtain an opinion from the MSBOC to determine whether or not a certificate was in

fact required.

¶12. The County took the matter under advisement, and on December 21, 2020 met and

passed a resolution in response. In its resolution, the county cited to section 31-3-15, and

stated that in applying that statute, along with Mississippi Code Annotated section 31-3-1

(Rev. 2020),3 which defined “contractor” and “public project” and Mississippi Code

2
Section 31-3-15 states:

No contract for public or private projects shall be issued or awarded to any
contractor who did not have a current certificate of responsibility issued by
said board at the time of the submission of the bid, or a similar certificate
issued by a similar board of another state which recognizes certificates issued
by said board. Any contract issued or awarded in violation of this section
shall be null and void.
3
Section 31-3-1 defines a “contractor” as follows:

Any person contracting or undertaking as prime contractor, subcontractor or
sub-subcontractor of any tier to do any erection, building, construction,
reconstruction, demolition, repair, maintenance or related work on any public
or private project; however, “contractor” shall not include any owner of a
dwelling or other structure to be constructed, altered, repaired or improved
and not for sale, lease, public use or assembly . . . .

The section defines “public project” as “[a]ny project for erection, building, construction,
reconstruction, repair, maintenance or related work which is funded in whole or in part with

6
Annotated section 31-7-1(g) (Rev. 2020),4 which defined “construction,” the County found

that the RFP was not for the purpose of building, altering, improving or renovating any

public building, public structure, public road, or other public real property. The County

further found that the eight items listed in Holliday’s protest as allegedly requiring a

contractor’s license were not a major part of the proposed contract (i.e., were far less than

50% of the value of the contract); that said items were not in the RFP for the purpose of

improving any public real property or to create something new to be used and enjoyed by the

public for years to come; that the said items listed were merely incident to (and for the

purpose of) cleaning up Hurricane Zeta damage and debris; that the said items have been

listed in accordance with state law and FEMA guidelines; and, therefore, the said items did

not require a contractor’s license for the work to be performed in accordance with the

proposed contract. The County also found that the RFP and the contract to be awarded were

for a service and not for a public project, as contemplated by section 31-3-15. The County

denied Holliday’s protest and proceeded to award the three-year contract to CTC, with the

option to renew for one additional year.5

¶13. Holliday sent its own request on December 30, 2020, to the MSBOC requesting that

public funds.” Id.
4
Section 31-7-1(g) defines “construction” as “the process of building, altering,
improving, renovating or demolishing a public structure, public building, or other public real
property. It does not include routine operation, routine repair or regularly scheduled
maintenance of existing public structures, public buildings or other public real property.”
5
The written contract between the County and CTC included CTC’s price proposal
that was submitted with the first page of the price proposal form from the initial RFP instead
of the first page of the price proposal form from Addendum 1.

7
the board provide an opinion as to whether or not a certificate of responsibility was required

for the project.

F. Holliday’s Circuit Court Appeal and Complaint

¶14. Prior to receiving a response from the MSBOC, Holliday filed an appeal and

complaint in the Circuit Court of George County on January 6, 2021.6 In its complaint,

Holliday alleged that the “[C]ounty’s decision to award the contract to CTC had to be

overturned because CTC did not hold the required license from the MSBOC.” Holliday

further argued that the contract award was arbitrary or capricious because it violated clear

statutory requirements and was beyond the County’s scope or powers. According to

Holliday, it was entitled to the award of the contract as the lowest and best, responsive and

responsible bidder or, in the alternative, that it was entitled to compensatory damages for its

lost profits which Holliday would have earned had the contract been properly awarded.

Holliday also requested that the circuit court stay the contract award to CTC or, alternatively,

enter a preliminary injunction against the County to keep it from awarding the contract to

CTC. Holliday also requested that the court conduct an expedited hearing on the matter.

¶15. On January 8, 2021, Holliday served notice of a hearing on its request to stay the

contract, or alternatively, its request for a preliminary injunction. The hearing was set for

January 25, 2021.

¶16. The County filed its answer to Holliday’s circuit court appeal and “complaint” on

January 15, 2021. The County denied that Holliday was entitled to any relief requested. The

6
Although styled as a “complaint and appeal of decision,” Holliday did not allege any
separate causes of action and merely appealed the County’s decision.

8
County pled that the requirement of a certificate of responsibility found in Mississippi Code

Annotated section 31-3-15 did not apply to the work outlined in the RFP and that Holliday

had no legal authority (or valid argument) for claiming that it did. In addition, the County

argued that if Holliday was seeking an injunction as a civil remedy outside the scope of its

appeal, then Holliday failed to state how it would suffer any irreparable injury if such an

injunction was not granted. The County attached its December 21, 2020 resolution to its

answer.

¶17. On January 20, 2021, Holliday filed a memorandum in support of its complaint further

arguing that the County’s decision to award the contract to CTC was arbitrary and capricious

and beyond the lawful power of the County. Holliday attached an opinion that it received

from the MSBOC on January 13, 2021, to its memorandum. In the opinion letter, the

MSBOC determined that “a certificate of responsibility was required to perform the scope

of work detailed in the RFP specifications because excavation, grading, drainage, and

landscaping work, all required a certificate of responsibility when the contract amount

exceeded fifty thousand dollars ($50,000.00).”

¶18. The circuit court held a hearing on Holliday’s request for stay or in the alternative

request for injunction on January 25, 2021. At the hearing, Holliday requested a stay of

performance on the contract until the court had an opportunity to consider the appeal. The

County argued that there was no authority for the court to grant an injunction. The court took

the matter under advisement.

¶19. On February 1, 2021, Holliday filed a motion to amend or supplement the appellate

record. Holliday argued that although the record contained portions of CTC’s bid, neither

9
CTC’s nor Holliday’s final, complete bids were included. Holliday stated that the bids,

which were part of the County’s underlying decision, should be made a part of the record so

that the circuit court could consider “all of the information – in its entirety – that was before

the County when it reached its decision to award the contract for the project to CTC.” The

County filed a response to Holliday’s motion to amend the appeal record on February 2,

2021. The County argued that Holliday provided no valid reason for why its motion should

be granted and that the granting of the motion would only cause delay and expense in the

case.

¶20. The circuit court granted Holliday’s request for a stay on February 2, 2021.

¶21. On February 4, 2021, the County filed a brief in support of its decision to award the

contract to CTC. The County argued that the MSBOC’s January 13, 2021 opinion, which

was attached to Holliday’s memorandum, was not binding legal authority because, unlike the

Attorney General, the MSBOC did not have statutory authority to issue an opinion. In

addition, the County stated that it had evaluated the work to be completed under MSBOC

Rule 5 and the MSBOC order discussed in Clancy’s Lawn Care & Landscaping Inc. v.

Mississippi State Board of Contractors, 707 So. 2d 1080, 1084 (¶¶14-15) (Miss. 1997),7 and

determined that a certificate of responsibility was not required. Holliday countered with a

reply brief in support of its “complaint” and appeal on February 17, 2021. Holliday argued

that the MSBOC was duly authorized to issue opinions concerning whether a contractor must

7
That case, which held MSBOC opinions are binding on parties when requested, also
references MSBOC Rule 5, which provides a formula whereby cities and counties can assess
their projects and determine the need for a certificate of responsibility. Clancy, 707 So. 2d
at 1084 (¶¶14-15).

10
be licensed in order to perform certain work. Holliday also argued that the County had

misinterpreted Clancy.

G. The Circuit Court’s February 23, 2021 Orders

¶22. On February 23, 2021 the court issued two orders. In one order, the circuit court

granted Holliday’s motion to amend or supplement the appeal record. The court directed the

County to supplement the record with the final, complete bids submitted by Holliday and

CTC in addition to the complete record of any actions taken and issues considered on

remand. In its second order, titled “Order Of Remand Jurisdiction Retained,” the circuit

court remanded the matter to the County to either consider the MSBOC’s January 13, 2021

opinion (provided in response to Holliday’s request) or provide all relevant information

regarding the RFP to the MSBOC to obtain an official opinion as to whether a certificate of

responsibility was required. The court also stated that its February 2, 2021 order, which

granted stay of performance on the contract, was to remain in full force and effect.

¶23. Thereafter, the County decided to request an opinion from the MSBOC and did so on

March 2, 2021. However, the County was told that it would not receive a response until mid-

April. Desiring not to lose any more time, and in the event that the MSBOC deviated from

its order approved in Clancy (therefore requiring a certificate of responsibility in this

instance), and because the County did not want to face this issue in the future, the County

decided to advertise for hurricane clean-up on a long-term contract when and as needed. The

County issued a new RFP requiring a certificate of responsibility for this contract and

received eight bids, including one from Holliday. However, the County found, as outlined

in its April 20, 2021 Resolution, that the lowest and best bid was submitted by AAA General

11
Contractors Inc. (AAA). Because the County knew it needed the court’s approval of these

actions because a stay was in place, there was no contract immediately executed with AAA.

It should be noted that Holliday never sought to enjoin this new bidding procedure or bring

it to the attention of the court. Instead, Holliday participated in the re-bidding for the new

project.

¶24. The MSBOC responded to the County in an opinion letter dated April 14, 2021. The

MSBOC stated that it had established specialty classifications such as “clearing, grubbing

and snagging,” “excavation, grading and drainage,” or “landscaping, grading and

beautification” as classifications that cover much of the work described in the request and/or

project specifications. Work under these specialty classifications met the definition of

contractor and therefore required a certificate of responsibility. The MSBOC determined that

storm debris removal, specifically hurricane debris removal involving the use of mechanized

equipment other than human labor, met the definition of “contractor” and therefore required

a certificate of responsibility when the contract exceeded $50,000 pursuant to Mississippi

Code Annotated section 31-3-1.

¶25. In response to the MSBOC opinion letter, the County met on April 19, 2021, and

terminated its contract with CTC. The County then awarded the contract to AAA, subject

to the circuit court’s approval. On April 20, 2021, the County reported these developments

to the circuit court and attached a resolution summarizing them. The County informed the

court that its consultant who was familiar with FEMA regulations was concerned that if the

court determined that the CTC contract was illegal, then FEMA would not reimburse the

County for the work done by CTC, and the county would have to pay the full amount owed.

12
The County also pointed out that most of the governmental entities on the coast did not

require a certificate of responsibility for contractors doing similar work because MEMA did

not require it. The County feared that if the court ruled that the contract with CTC was

illegal, then all the other counties might then be responsible for paying back the funds that

FEMA had paid to them. The County also requested that the circuit court lift the stay that

had stopped the debris removal in the county.

¶26. On April 26, 2021, Holliday filed a response in opposition to the County’s report and

a motion for partial summary judgment. In the response, Holliday argued that the circuit

court had no authority under Mississippi Code Annotated section 11-51-75 (Rev. 2019)8 to

grant the County’s request to hire AAA, a new separate contractor. Holliday argued that the

court was obligated to either affirm or reverse the County’s original decision. Holliday

further argued that it was entitled to an award of the remaining unfinished, incomplete

original RFP work as well as lost profits on the work CTC had performed instead of

Holliday. In the event that the court granted the County’s request to award a new long-term

contract to AAA, Holliday contended that it was entitled to an award of compensatory and

8
Section 11-51-75(d) states:

The circuit court, as an appellate court, either in term time or in vacation, shall
hear and determine the same on the record and shall affirm or reverse the
judgment. The circuit court shall enter an order establishing a briefing
schedule and a hearing date, if any, for the parties to appear and present oral
argument. If the judgment is reversed, the circuit court shall render such
judgment or decision as the board of supervisors or the governing authority
of the municipality ought to have rendered, and certify the same to the board
of supervisors or the governing authority of the municipality. Costs shall be
awarded as in other cases.

13
consequential damages on the work completed by CTC and the unfinished portion of the

original RFP work.

H. The Circuit Court’s April 30, 2021 Order

¶27. On April 30, 2021, the circuit court entered an order affirming the County’s

termination of the contract with CTC. After reviewing the original RFP and the MSBOC’s

opinions, the court stated that based on the nature of the work and the amount of the contract,

CTC was, in fact, required to have a certificate of responsibility. Therefore, the court found

that the contract between the County and CTC was null and void. The court also stated that

all other actions that had been taken by the County, as reported in its April 20, 2021

Resolution, other than considering whether or not the certificate of responsibility was

required, exceeded the court’s remand order and thereby voided any proposed contract with

AAA. The court directed the County to consider all other proposals received by December

4, 2020, for the original RFP, and to make a finding accepting or rejecting the previously

submitted bids. The findings and actions of the board of supervisors were to be submitted

to the circuit court for review. Thereafter, should the County decide to reject all the

December 4, 2020 bids, the court stated that the County would then have the authority to re-

open the bidding process for the same services or make a determination that a different

service contract was necessary to serve the best interest of the county.

¶28. On May 7, 2021, the County filed a report in response to the circuit court’s April 30,

2021. The County attached a resolution to the report also dated May 7, 2021, detailing the

actions that had been taken pursuant to the court’s order. In its resolution, the County stated

that the board of supervisors had reviewed all the December 4 bids, debated and discussed

14
what the circuit court’s order required, and spent more than three hours on the subject.9 The

County recognized that a certificate of responsibility was required which had not been

required in the original RFP. The County reported that it planned to reject all proposals and

re-advertise for proposals from contractors who obtained a certificate of responsibility

number. The County also stated that due to time and cost restraints, it was restricting the

remaining Hurricane Zeta work to be done to tasks that were absolutely necessary, and

therefore amended the new request for proposals accordingly.

I. The Circuit Court’s Final Order and Judgment

¶29. On May 18, 2021, the court entered its final order and judgment. The court stated that

although contracting with CTC, a contractor without a certificate of responsibility, was in

violation of the law, the action of the Board was not arbitrary and capricious but instead

based upon a mistaken reliance on the Clancy decision. The court also stated it nor the

County was required to award the contract to the next lowest bidder. Instead, the court stated

that it was permitted to award the contract to the next lowest bidder or order the County to

reject all bids and rebid the project. Considering the fact that the County reserved the right

to reject all bids, the significant difference in the monetary amount between CTC and

Holliday’s bids,10 and the entry of the stay order, the court found that all the bids should have

9
In the resolution, the County did not submit the specifics of its discussions.
10
The court stated that Holliday’s bid was $665,437 higher than CTC’s bid. Holliday
contends that if CTC had used the correct bid forms, CTC’s bid amount would have been
$2,121,863 instead of the reported amount of $1,686,613, which the court relied on.
However, even if we look to CTC’s corrected bid amount, Holliday’s bid was still $230,187
higher than CTC’s bid amount.

15
been rejected. The court therefore affirmed the County’s May 7, 2021 resolution rejecting

all the bids and instructed the County to rebid for the unfinished hurricane debris pickup and

removal. The court denied all other requests for relief.

¶30. Holliday now appeals arguing that the circuit court’s decision not to award

compensatory damages was not based on substantial evidence and that the circuit court

should have held a hearing to determine Holliday’s compensatory damages.

STANDARD OF REVIEW

¶31. The Mississippi Supreme Court reviews a decision by a chancery or circuit court

concerning an agency or board action by applying the same standard of review that the lower

courts are bound to follow. Miss. Sierra Club Inc. v. Miss. Dep’t of Envtl. Quality, 819 So.

2d 515, 519 (¶15) (Miss. 2002); see also Hooks v. George County, 748 So. 2d 678, 680 (¶10)

(Miss. 1999). “Our review of a decision by a county board of supervisors is limited.”

Preferred Transp. Co. LLC v. Claiborne Cnty. Bd. of Supervisors, 32 So. 3d 549, 551 (¶5)

(Miss. Ct. App. 2010). “We will not set aside the action of the governing body of a

municipality unless such action is clearly shown to be arbitrary, capricious, or discriminatory

or is illegal or without substantial evidentiary basis.” Id. “An act is arbitrary and capricious

when it is done at pleasure, without reasoned judgment or with disregard for the surrounding

facts and circumstances.” Precision Commc’ns Inc. v. Hinds County, 74 So. 3d 366, 369 (¶9)

(Miss. Ct. App. 2011). “Substantial evidence is such relevant evidence as reasonable minds

might accept as adequate to support a conclusion or more than a mere scintilla of evidence.”

Id.

DISCUSSION

16
¶32. Holliday argues that it is entitled to compensatory damages. However, we must first

decide whether the County acted in a manner that was arbitrary, capricious or illegal, thus

exposing it to liability when it awarded the original contract to CTC.

I. Whether the County’s award of the original contract to CTC was
arbitrary and capricious.

¶33. Holliday argues that the County’s original award of the contract to CTC was arbitrary

and capricious because CTC did not hold a certificate of responsibility. Under Mississippi

law, “[a]n act is arbitrary and capricious when it is done at pleasure, without reasoned

judgment or with disregard for the surrounding facts and circumstances.” Id. In response,

the County stated that it relied on the MSBOC order in Clancy, a Mississippi Supreme Court

case, to determine that a certificate of responsibility was not needed to perform the work

outlined in the RFP.

¶34. In Clancy, 707 So. 2d at 1081 (¶4), the City of Ocean Springs, Mississippi issued an

RFP for landscape and maintenance work to be done along U.S. Highway 90. Id. “The

scope of the work described by the RFP was to provide pruning, mulching, weeding,

fertilizing, insecticide and fungicide treatment, plant replacement, mowing, trimming and

litter removal.” Id. In response to the advertisement, Clancy submitted a bid of $120,000,

and Your Personal Gardener (YPG) submitted a bid of $57,000. Id. at (¶5). Clancy had a

certificate of responsibility issued by the MSBOC, but YPG did not. Id. The City decided

to award the contract to YPG based on a prior MSBOC opinion determining “that no

certificate of responsibility was required to do mowing or litter removal.” Id. at (¶6).

¶35. In response, Clancy filed an injunction lawsuit against the city and YPG, but the

17
lawsuit was “dismissed after all parties agreed to attend the quarterly meeting of the

[MSBOC] to seek a clarification of the board’s previous ruling . . . concluding that mowing

and litter removal did not require a certificate of responsibility.” Id. at 1081-82 (¶6). At the

meeting, the MSBOC “concluded . . . that work under the classification of Grounds

Maintenance [met] the definition of ‘contractor’ in Miss[issippi] Code Ann[otated] [section]

31-3-1 and therefore required a certificate of responsibility issued by the [MSBOC] . . . .”

Id. at 1082 (¶6). The MSBOC also entered an order stating,

[U]nder Rule 5 of the Rules and Regulations of the Board (1) the awarding
agency must make a determination of which classification of work covers at
least 50% of the total cost of the project; (2) if at least 50% of the total cost of
the project constitutes ground maintenance, then a certificate of responsibility
is needed; and (3) if at least 50% of the total cost of the project constitutes
mowing and/or litter removal, then a certificate of responsibility is not needed.

Id. at (¶7).

¶36. Clancy then appealed from the MSBOC’s order to the Jackson County Chancery

Court. Id. at (¶8). The chancery court held that “the action taken by [the MSBOC] was

supported by substantial evidence, was not arbitrary [or] capricious, was within the power

of the Board [of Contractors] to make, and did not violate any statutory or constitutional right

of Clancy’s.” Id. The chancery court also held that the MSBOC was “within their authority

to conclude that mowing and/or litter removal did not require a certificate of responsibility.”

Id.

¶37. Clancy appealed the chancery court’s ruling to the Mississippi Supreme Court arguing

that the MSBOC “did not have the authority to determine that mowing and/or litter removal

did not require a bidder to have a current certificate of responsibility.” Id. at 1083 (¶10).

18
The supreme court held that because Mississippi Code Annotated 31-3-13 expressly grants

the MSBOC with the “authority to set forth the requirements for a certificate of responsibility

and [the authority] to classify the kind of works that a contractor can perform under its

certificate of responsibility, then it [was] “necessarily implied,” and a “logical necessity,” that

the board also have the authority to determine what types of work require a contractor to

obtain a certificate of responsibility. Id. at 1084 (¶15). The supreme court also reviewed and

approved the order issued by the MSBOC regarding Rule 5 of the MSBOC Rules and

Regulations. In summary, Clancy held two things: first, it approved MSBOC Rule 5 that

instructed local authorities on how they could determine when a certificate of responsibility

was required for a project; and second, when consulted, the MSBOC did have the authority

to determine when a certificate of responsibility was needed based on the specifications of

the project presented.

¶38. In the present case, Holliday submitted its protest, in which it asserted that a certificate

of responsibility was required to complete certain work included in the RFP. The County

met and evaluated the work to be done under the contract based on Clancy and Rule 5 of the

Rules and Regulations of the MSBOC. The County concluded that a certificate of

responsibility was not required to perform the work outlined in the RFP. Based on this

evaluation, the County proceeded with its award of the contract to CTC. At this point,

neither the County nor Holliday had any opinion from the MSBOC.

¶39. In its final order the circuit court held that “while ultimately the original award of the

contract to CTC . . . was in violation of the law, the action of the Board was not arbitrary and

capricious but based upon a mistaken reliance upon the Clancy decision.” We agree. There

19
is no evidence in the record to show that the County’s reliance on Clancy was misplaced.

Clancy is still good law and does give the County the authority to evaluate the work

described in an RFP to determine if a certificate of responsibility is required. Prior to the

execution of the contract with CTC, no MSBOC opinion had been rendered. After the

County received an opinion from the MSBOC, the County took the appropriate action.

Although the County’s assessment that a certificate of responsibility was not required was

later determined by the MSBOC to be incorrect and thus in violation of the law, the County’s

actions were not arbitrary and capricious. Therefore, we affirm the circuit court’s holding

that the County’s initial decision to award the contract to CTC was illegal but not arbitrary

and capricious.

II. Whether Holliday was entitled to compensatory damages for the
month of work CTC completed on the contract.

¶40. Although the County’s original contract with CTC was illegal, that determination,

alone, does not entitle Holliday to an award of compensatory damages. Rather, in addition

to that determination being made, Holliday was required to show that the County would have

awarded it the contract had it not awarded the contract to CTC, and that the contract with

CTC was substantially completed, thus precluding Holliday from rebidding on the project.

Holliday has not proven either of these latter elements.

¶41. The Mississippi Supreme Court has held that if a project was not substantially

completed and a determination was made that the contract was illegally awarded, the circuit

court can either decide to (1) award the contract to the next lowest bidder or (2) allow the

County to reject all bids and re-advertise for the project. City of Durant v. Laws Const. Co.,

20
721 So. 2d 598, 600 (¶4) (Miss. 1998). In Durant, the city of Durant “advertised and

published for bidders to construct a 100,000 square foot building.” Durant, 721 So. 2d at

600 (¶5). The City accepted a bid from King Metal Buildings Inc. (King), which failed to

include its certificate of responsibility number on the exterior of its bid envelope as required

by Mississippi Code Annotated section 31-3-21. Id. at 599 (¶2). Laws Construction

Company (Laws) submitted a letter protesting the opening of King’s bid. Id. at 600 (¶7). In

response to Law’s protest, the alderman and mayor for the City held a meeting. Id. at (¶8).

At the meeting, the attorney for the City discussed opinions the Attorney General’s office had

rendered in other cases. Id. According to the city attorney, the opinions advised “that under

the circumstances, the City could legally award the bid to King” although it had failed to

have its certificate of responsibility number listed on its bid envelope. Id. However, a field

representative, who was employed with the MSBOC for seven years, also spoke at the

meeting, and informed the alderman and mayor that “a bid may not be opened without a

certificate of responsibility number located on the exterior of the envelope.” Id. at 601 (¶8).

He further stated that he had always advised public bodies not to open bid envelopes that did

not have the number located on the exterior of the envelope. Id. Despite this admonition of

the MSBOC representative, the board of alderman awarded the project to King. Id. at (¶9).

Laws appealed the City’s award to the Holmes County Circuit Court but, by the time the

appeal was heard, the work on the project was substantially completed. Id. at (¶2).

¶42. The circuit court held that section 31-3-21 clearly required the certificate of

responsibility number on the exterior of the bid envelope and therefore the City had violated

a statutory requirement, and thus its action was illegal. Id. at (¶11). The circuit court further

21
held that the City had erred in considering King’s bid and determined that either Laws would

have been entitled to the contract or the City could have rejected all bids. Id. However,

“[s]ince the project was precluded from being awarded to Laws due to its substantial

completion, the circuit court determined that Laws was entitled to recover damages.” Id. at

605 (¶28). In addition, the circuit court noted that the “City had conceded that it would have

accepted Laws’ bid and awarded Laws the contract . . . if the city had neither opened nor

considered King’s bid.” Id. at 601 (¶11). Therefore, the circuit court awarded Laws a

judgment against the City for compensatory damages and attorneys’ fees, and the City

appealed. Id. The Mississippi Supreme Court affirmed the circuit court’s determination that

the contract was illegally awarded to King, and held that Laws was entitled to damages as

measured by the law of contracts. Id. at 606 (¶34). In summary, Laws was awarded damages

because of the finding that the City had acted illegally, because the work on the project was

substantially completed, and because the City conceded that it would have awarded the

contract to Laws, as the next lowest bidder. Therefore, the supreme court held that the only

relief available to Laws was compensatory damages.

¶43. In this case, however, although the contract was awarded to CTC illegally, the work

on the project was not substantially completed and there was no admission by the County or

determination by the circuit court that Holliday was entitled to the original RFP contract.

Thus, pursuant to Durant, the County had the option of awarding the contract to Holliday or

rejecting all bids and starting anew. Holliday had the opportunity to bid on the new contract,

which included the work remaining from the original contract with CTC, and thus Holliday

is not entitled to damages as was Laws in Durant.

22
¶44. Holliday incorrectly challenges the authority of the circuit court to order or allow the

County to rebid the project. In fact, this court has twice affirmed a circuit court’s authority

to allow a county to reject all bids and re-advertise for an incomplete project that was

illegally awarded.

¶45. In Preferred, 32 So. 3d at 554 (¶13), Claiborne County requested competitive

proposals for the collection and disposal of solid waste pursuant to Mississippi Code

Annotated section 31-7-13(r) (Rev. 2020),11 and both Preferred Transport Company LLC

(PTC) and HomeBase Litter Control, LLC (HomeBase) submitted sealed proposals. Id. at

550 (¶2). The County awarded the contract to HomeBase although PTC was the lowest

bidder. PTC appealed to Claiborne County Circuit Court arguing that the county’s award of

the contract to HomeBase “was in violation of statutory authority as the bid award was based

on factors not contained in the [RFP].” Id. at 550 (¶1). The circuit court agreed with PTC’s

11
Section 31-7-13(r) states, in pertinent part:

Any request for proposals when issued shall contain terms and conditions
relating to price, financial responsibility, technology, legal responsibilities and
other relevant factors as are determined by the governing authority or agency
to be appropriate for inclusion; all factors determined relevant by the
governing authority or agency or required by this paragraph (r) shall be duly
included in the advertisement to elicit proposals. After responses to the
request for proposals have been duly received, the governing authority or
agency shall select the most qualified proposal or proposals on the basis of
price, technology and other relevant factors and from such proposals, but not
limited to the terms thereof, negotiate and enter into contracts with one or
more of the persons or firms submitting proposals. If the governing authority
or agency deems none of the proposals to be qualified or otherwise
acceptable, the request for proposals process may be reinitiated.

(Emphasis added).

23
claim that the County had exceeded the statutory authority when it considered factors that

were not listed in the RFP. Id. at 551 (¶4). Instead of awarding the contract to PTC, the

circuit court ordered the County to reopen the request for proposal process to include such

factors in the RFP. Id. PTC argued to this court that once the circuit court found that the

award of the contract to HomeBase was invalid, the circuit court had the statutory authority

to award the contract to PTC pursuant to Mississippi Code Annotated section 11-51-75(d),

or, alternatively, to award PTC compensatory damages. Id. PTC cited Durant to support its

contention for an award of compensatory damages. Id. at 554 (¶15). However, this court

held that Durant was distinguishable from PTC’s case because in Durant the contract had

been substantially completed by another vendor, and thus it was impossible to award the

contract to Laws. Id. at (¶15). We also stated that because the contract PTC was disputing

was an ongoing service contract, which could have been renewed upon the award of a new

contract at the closing of the RFP process, an award of compensatory damages was not

warranted. Id. at (¶15). Therefore, we denied PTC damages and specifically found no error

in the circuit court’s order to re-institute the RFP process. Id. at 555 (¶17).

¶46. Similarly, in Precision, 74 So. 3d at 367 (¶1), this court also affirmed the Hinds

County Circuit Court’s decision to allow the Hinds County Board of Supervisors (HCBS) to

reject all previous bids and re-advertise the contract for the installation of early-warning

tornado sirens. In that case, “HCBS published a notice that it was requesting proposals to

replace up to fifty-one broken and/or outdated emergency weather sirens.” Id. at 367 (¶3).

HCBS received seven bids in response to its notice. Id. at (¶4). HCBS held a special

meeting and voted to award the contract to Emergency Dispatch Notification Systems

24
(EDNS). Id. On November 26, 2008, Precision Communications Inc. (PC) appealed to the

circuit court after HCBS awarded the contract to EDNS instead of PC. Id. In its appeal, PC

“requested that the circuit court stay HCBS’ award of the contract to EDNS until after the

circuit court had ruled on PC’s bill of exceptions.” Id. at 368 (¶5). The circuit court denied

PC’s motion, and “HCBS and EDNS entered into a contract for the installation of ten of the

fifty-one weather sirens.” Id.

¶47. On July 28, 2009, HCBS moved to dismiss PC’s appeal, arguing that it was moot

because HCBS had “chosen to rebid the work that [was] the subject of [the] appeal.” Id. at

(¶6). In response, “PC requested that the circuit court stay HCBS’ attempt to rebid the

project.” Id. “[T]he circuit court entered an order denying HCBS’ motion to dismiss PC’s

appeal”, and “imposed a stay of PC’s appeal and remanded the matter to HCBS with

instructions to reconsider the previous bids.” Id. at 368 (¶7). “HCBS provided the circuit

court with a copy of a transcript and executive session minutes regarding its reconsideration

of all previous bids.” Id. The minutes reflected that HCBS had been informed that awarding

the contract to PC could endanger the grant funding for the project because PC had helped

the County secure the funds from the federal government. Id. “HCBS informed the circuit

court that it had voted to reject all of the bids and rebid the award for early warning sirens.”

Id. at 369 (¶7). After being informed of HCBS’s decision, the circuit court “filed [an] order

lifting its stay and dismissing PC’s appeal.” Id. at (¶8). The circuit court stated that “the

County’s ultimate rejection of all bids initially submitted to the County makes moot the

appeal before the court.” Id. PC appealed the circuit court’s decision, and this court, relying

on Preferred, held that because “the circuit court could have ordered HCBS to reject all bids

25
and reopen the request-for-proposals process,” it was appropriate to affirm the circuit court’s

finding that PC’s appeal was moot. Id. at 371 (¶16).

¶48. Therefore, in this case, under the holdings of Preferred and Precision, the circuit court

did not act arbitrarily or capriciously when it allowed the County to reject all bids and re-

advertise after finding that the County had illegally awarded the contract to CTC. It follows

then that the County had the authority to rebid the hurricane debris removal project, and

because Holliday had an opportunity to bid on that work, under our reasoning in Preferred,

no damages were warranted.

¶49. Holliday also cites W.G. Yates & Sons Construction Co. v. City of Waveland, 168 So.

3d 963 (Miss. Ct. App. 2012), in support of its contention that it is entitled to compensatory

damages. However, the Yates decision, with facts similar to those in Durant, actually

supports our holding that Holliday is not entitled to damages in this case.

¶50. In Yates, the City advertised for bids for a sewer project on May 14, 2009. Yates, 168

So. 3d at 964 (¶2). Yates and Sons Construction Company (Yates) submitted a bid for

$9,471,859, and Reynolds Inc. (Reynolds) submitted a bid for $9,356,601. Id. “Reynolds

and Yates submitted the two lowest bids.” Id. at (¶3). The City awarded the contract to

Reynolds, and Yates appealed to the Hancock Circuit Court, arguing that Reynolds, which

was not a resident contractor, had failed to “attach its state’s current law related to the state’s

treatment of non-resident contractors.”12 Id. at 967 (¶14). The City had concluded that

12
Mississippi Code Annotated section 31-3-21(3) provides that “a non-resident
contractor shall attach a copy of its state’s current law related to the treatment of non-
resident contractors in that state.” Yates, 168 So. 3d at 966 (¶14). This law is meant to
ensure equal treatment of non-resident bidders in each state.

26
Reynolds was a resident contractor due to its affiliation with another corporation. Id. at 965

(¶7). On August 8, 2009, Yates requested that the circuit court stay the contract award to

Reynolds, id. at 974 (¶61), but on December 18, 2009, the circuit court denied Yates’s

motion, stating that Yates could seek compensatory damages if the court were wrong. Id. at

(¶62). The circuit court ultimately dismissed Yates’s appeal and affirmed Waveland’s

decision to award the contract to Reynolds, finding that Reynolds was a resident contractor

under Mississippi Code Annotated section 31-3-21(3), and thus was not required to attach

its state’s laws on non-resident bidding. Id. at (¶62).

¶51. On appeal, this Court held that because Reynolds should not have been treated as a

resident contractor, id. at 971 (¶40), the City’s actions had been arbitrary and capricious. Id.

at 971 (¶38). We stated that the City’s decision to award the sewer project to Reynolds was

not supported by substantial evidence because “there [was] no evidence in the record that

Waveland’s governing authority considered or was even aware of whether Reynolds met the

state’s public-bid laws.” Id. at 971 (¶38). With respect to damages, this court found the case

to be similar to and applied Durant. The contract was bid in May 2009, id. at 964 (¶2), and

in August 2009, Yates requested that performance on the contract be stayed. Id. at 974 (¶61).

In December 2009, the circuit court denied Yates request, id. at (¶62), and we rendered our

opinion on July 12, 2012, over two-and-a-half years after the improper contract had been

executed and work on the contract had been performed in the interim. Thus, finding Durant

applicable, we remanded the case for a hearing on whether Yates was entitled to damages.

Id. at 675 (¶¶63-65). In the case at hand, unlike in Yates, CTC had only completed one

month of work on the contract before the court-ordered stay. In addition, Holliday had an

27
opportunity to secure the contract when the County rebid the project, albeit without the

circuit court’s authority, and again Holliday was outbid. Moreover, according to the circuit

court’s final order, the County was allowed to reject all bids and rebid the project, thus giving

Holliday a third opportunity to secure the contract.

¶52. Finally, Holliday has not shown that it was entitled to an award of the original

contract. The County did not concede, as did the City in Durant, that it would have accepted

Holliday’s bid if CTC’s had not been considered. When ordered by the circuit court to

review the original bids received on December 4, the County ultimately chose to reject all

original bids, including Holliday’s, which the circuit court found it had the authority to do.

CONCLUSION

¶53. We affirm the circuit court’s ruling that although the CTC contract was illegal, the

County had not acted arbitrarily and capriciously. We further hold that the circuit court did

not act arbitrarily and capriciously but rather had the authority to allow the County to reject

all bids, re-advertise, and allow companies to re-bid for the hurricane debris removal work.

Finally, because Holliday failed to show that it was entitled to the original award of the

contract, and the work on the project had not been substantially completed, we affirm the

circuit court’s ruling that Holliday was not entitled to compensatory damages.

¶54. AFFIRMED.

BARNES, C.J., GREENLEE, WESTBROOKS, LAWRENCE, McCARTY,
SMITH AND EMFINGER, JJ., CONCUR. WILSON, P.J., CONCURS IN PART AND
IN THE RESULT WITHOUT SEPARATE WRITTEN OPINION. CARLTON, P.J.,
CONCURS IN PART AND DISSENTS IN PART WITHOUT SEPARATE WRITTEN
OPINION.

28

Poursuivez vos recherches dans ChatGPT ou Claude

Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.