Filed 6/21/24 Stronghold Engineering v. City of Monterey CA4/1
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

STRONGHOLD ENGINEERING, D082763
INCORPORATED,

Plaintiff and Appellant, (Super. Ct. No. CVRI2103427)
v.

CITY OF MONTEREY,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Riverside County,
Chad W. Firetag, Judge. Affirmed in part, reversed in part and remanded.

Varela, Lee, Metz & Guarino and Andrew Van Ornum, for Plaintiff and
Appellant.
Colantuono, Highsmith & Whatley; Michael G. Colantuono, Megan A.
Wharton and Merete E. Rietveld; Christine Davi, City Attorney, for
Defendant and Respondent.
Appellant Stronghold Engineering Incorporated (Stronghold)
successfully bid to renovate the City of Monterey’s (the City) conference
center and Portola Plaza (the Project). The City later issued a notice of
violation against Stronghold under the Subletting and Subcontracting Fair
Practices Act (Pub. Contract Code,1 § 4100 et seq., the Act) for allegedly
substituting its concrete and waterproofing subcontractors without notice or
the City’s consent. Stronghold appealed to the City’s Appeals Hearing Board
(the Board) who sided with the City and assessed penalties against
Stronghold for both substitutions. Stronghold filed this action challenging
the Board’s decision and the role of a city attorney at the hearing. The trial
court found in the City’s favor.
Stronghold appeals from the court’s ruling, contending: (1) the Board
did not conduct a fair hearing consistent with due process; (2) the laches
doctrine barred the City’s claims; and (3) substantial evidence does not
support the Board’s decision. We conclude the City’s claim as to the
waterproofing subcontractor is barred by laches and remand the matter to
the trial court to reverse this penalty assessment. We otherwise reject
Stronghold’s arguments.
FACTUAL AND PROCEDURAL BACKGROUND2
In October 2015, Stronghold submitted a bid to the City for the Project.
The bid listed West Coast Concrete as the concrete subcontractor and Gino
Rinaldi, Inc. (Rinaldi) as the waterproofing subcontractor. In November
2015, the City awarded the Project contract to Stronghold and the parties

1 Undesignated statutory references are to the Public Contract Code.

2 This section provides a brief background regarding the parties’
disputes. We provide additional background facts in the sections of this
opinion addressing Stronghold’s arguments on appeal.

2
entered into a written contract. Stronghold sub-contracted with Perry Coast
Construction (Perry) for the concrete work in December 2015 and with F.D.
Thomas, Inc. (F.D. Thomas) for waterproofing in April 2016.
In 2016, Stronghold sued the City regarding interpretation of the
contract and later amended its complaint to seek damages due to the City’s
alleged deficient design and resulting delays (the civil litigation). The City
filed its initial cross-complaint in January 2018. In March 2020, the City
claimed it learned of the subcontractor substitutions during discovery. In
January 2021, it amended its cross-complaint to allege that Stronghold
violated the Act based on its substitution of Perry for West Coast Concrete
and F.D. Thomas for Rinaldi. The civil litigation is still pending.
Separately, in September 2020, the City’s public works director sent
Stronghold a letter notifying it of the Act violations and that the matter had
been set for a hearing before the Board to consider the City’s request for
$437,230 in statutory penalties. As relevant here, the letter claimed:
(1) Perry and West Coast Concrete were not the same company, and West
Coast Concrete did not exist; and (2) Stronghold contracted with F.D. Thomas
for the waterproofing, not Rinaldi as listed in the bid. After a hearing, on
December 7, 2020, the Board issued a decision penalizing Stronghold for two
violations of the Act. It imposed a $291,000 penalty for the concrete
subcontractor substitution and $50,000 for the waterproofing subcontractor
substitution, totaling $341,000.
Stronghold initiated this action by filing a combined petition for
traditional mandamus (Code Civ. Proc., § 1085) and administrative
mandamus (id., § 1094.5) challenging the Board’s decision. Among other
things, Stronghold claimed the hearing process was unfair, the City’s
allegations should have been time-barred, and the evidence did not support

3
the Board’s decision. The trial court denied the writ, finding Stronghold
received a fair hearing and substantial evidence supported the Board’s
conclusion that Stronghold violated the Act.
DISCUSSION
I. THE BOARD’S HEARING WAS FAIR
Stronghold argues on appeal that the Board was unconstitutionally
biased against it because the Board’s legal advisor at the hearing, Salameh,
was an attorney in the office that was suing it in the civil litigation, i.e. the

City Attorney’s Office.3
A. Additional Background
At the Board’s contested hearing to consider penalties against
Stronghold based on alleged violations of the Act, the City was represented
by outside counsel, the same outside counsel who represented the City in the
civil litigation. Salameh was present at the hearing to advise the Board.
Specifically, review of the hearing transcript shows Salameh acted as an
advisor and moderator regarding proper hearing procedures. Because of
Salameh’s involvement in the hearing, Stronghold objected to the hearing
process as unfair. In response, Salameh made an unsworn statement
claiming she has been segregated from other members of the City Attorney’s
Office and has not communicated with the public works director or any other
colleagues in her office regarding the Board hearing or their preparations for
it. Davi made a similar unsworn statement for the record.

3 In the civil litigation, the caption of the amended cross-complaint lists
as representing the City both the City Attorney’s Office and City Attorney
Christine Davi, and outside counsel. Salameh is not listed on the caption in
the civil litigation.

4
After the hearing, Salameh drafted the Board’s proposed decision. At a
subsequent hearing to adopt the proposed decision, she stated: “I tried to
distill the Board’s deliberations from the November 18th, 2020 hearing and
the findings they made and then the ultimate vote imposing penalties for two
violations. So I tried to capture all of that in the written decision but, of
course, you are welcome to edit and provide further direction as you see fit.”
The Board adopted the proposed decision as its own.
Stronghold filed a verified petition for traditional mandamus and
administrative mandamus in the superior court, seeking to set aside the
Board’s decision. The court granted Stronghold’s motion to augment the
administrative record to include a privilege log from the City showing
Salameh’s communications relating to the civil litigation. The privilege log
shows that from November 10, 2014, to July 31, 2018, Salameh was copied on
14 privileged communications. On March 9, 2018, after being copied on two
privileged communications, Salameh prepared two privileged emails and
directly received two privileged emails. After the privilege log was mentioned
at the hearing, Salameh stated, “And, again, I’ll just say for the record, you
know, those likely were e-mails with Staff from years ago. I have not been
communicating with anyone in the Public Works Department regarding any
of the subcontracting issues that are before the Board today.”
The trial court acknowledged that Stronghold had presented evidence
showing Salameh was involved in the civil lawsuit but found that “the
evidence does not show . . . bias on the part of the City, nor is there any
evidence to conclude that Salameh’s representation [about being screened
from the civil lawsuit] was untrue or unreliable.” The court stated:
“Here, the civil lawsuit was filed on 12/13/16. The bulk of
the emails in the privilege log that involve Ms. Salameh,
just have her cc'ed on the email. Out of the 18 emails, she

5
only prepared two of the emails on the privilege log and
only directly received two emails, one of these emails was
sent before the civil lawsuit was filed. Petitioner has
provided no evidence that Ms. Salameh had more
involvement in this matter than the 18 emails listed on the
privilege log, which span 4 years. It points to no evidence
that Ms. Salameh had any involvement in the civil matter
after July 2018. It points to no evidence that Ms. Salameh
had any involvement in the investigation regarding
[Act]violations. It fails to point to or provide any evidence
that Ms. Salameh has any personal or financial interest or
actual bias in the [Act] violations or civil lawsuit. There is
no evidence in the record that Ms. Salameh has had any
involvement in the civil lawsuit filed by Petitioner since
July 2018, that her involvement in this matter was
substantial, that she had any financial interest, or actual
bias in the [Act] or civil matter.”

B. Analysis
The determination of whether the administrative proceeding was
fundamentally fair is a question of law that we review de novo. (Nightlife,
Partners, Ltd. v. City of Beverly Hills (2003) 108 Cal.App.4th 81, 87
(Nightlife).) If there are conflicts in the evidence, then we apply the
substantial evidence test to the findings that support the trial court’s factual
determinations. (Ibid.)
“When . . . an administrative agency conducts adjudicative proceedings,
the constitutional guarantee of due process of law requires a fair tribunal.
[Citation.] A fair tribunal is one in which the judge or other decision maker
is free of bias for or against a party.” (Morongo Band of Mission Indians v.
State Water Resources Control Bd. (2009) 45 Cal.4th 731, 737 (Morongo).) A
due process violation can be established by proof of an agency’s actual bias; or
“by showing a situation ‘in which experience teaches that the probability of
actual bias on the part of the judge or decisionmaker is too high to be

6
constitutionally tolerable.’ ” (Id. at p. 737; see also Knudsen v. Department of
Motor Vehicles (2024) ___ Cal.App.5th ___, ___ [2024 Cal.App. LEXIS 228,
*9].)
As a preliminary matter, we note that Stronghold does not assert that
Salameh was involved in the preparation or presentation of the Act’s
violations to the Board; instead, it contends that because the City’s cross-
claims in the civil litigation included allegations of Act violations, they are
functionally the same matter. Stronghold then argues that because Salameh
had taken an adversarial role against Stronghold concerning the same
disputes in the civil litigation, her role “tainted her from being impartial”
before the Board and therefore tainted the Board’s decision.
We do not agree that the Board hearing and the civil litigation are the
same proceeding, but we acknowledge the overlap between the allegations in
the Board proceeding and the cross-claims in the amended complaint.
Accordingly, we will consider Stronghold’s unfairness arguments as if they
arose in the course of a single proceeding.
In Howitt v. Superior Court (1992) 3 Cal.App.4th 1575 (Howitt) our
court addressed “the foundational question . . . whether a county counsel’s
office ‘is ever permitted to place [it]self in [the] position’ of acting as an
advocate for one party in a contested hearing while at the same time serving
as the legal adviser for the decision maker.” (Id. at p. 1579.) In Howitt, the
decision maker was a quasi-independent commission established to resolve
county employment disputes. (Id. at p. 1578.) During a contested
evidentiary hearing over a complaint against the sheriff’s department by an
employee, an attorney from the county counsel’s office represented the
sheriff’s department, while a second attorney from that office advised the
commission. (Ibid.) The court concluded that county counsel could not

7
undertake this dual representation, in which the office was both advocate
and adviser to the decision maker in a contested hearing, unless “there are
assurances that the advisor for the decision maker is screened from any
inappropriate contact with the advocate.” (Id. at p. 1586; see id. at pp. 1579,
1587.)
The Howitt court stated that the party asserting proper screening had
the burden “to demonstrate its existence and effectiveness.” (Howitt, supra, 3
Cal.App.4th at p. 1587.) In a footnote, the Howitt court remarked on
screening: “we do not envision that an adequate screening procedure for due
process purposes requires the creation of functionally separate offices to
advocate and advise. It should be sufficient if the lawyer advising the Board
has no potential involvement in or responsibility for the preparation or
presentation of the case.” (Id. at p. 1587, fn. 4.)4
Thus, our first inquiry is whether the City sufficiently demonstrated
the “existence and effectiveness” of measures to ensure that Salameh had “no
potential involvement in or responsibility for the preparation or presentation”
in the civil litigation against Stronghold. (Howitt, supra, 3 Cal.App.4th at
p. 1587 & fn. 4.) We conclude they have.
Salameh and Davi represented at the contested hearing that Salameh
had been screened from other members of the City Attorney’s Office and had
no contact with other members of the office regarding the Act violations.5
The City’s privilege log supports this conclusion.

4 As noted ante, Stronghold does not contend that Salameh had any
involvement in the preparation or presentation of the Acts violation before
the Board, and Salameh and Davi specifically denied such involvement.

5 Although Salameh’s and Davi’s statements are unsworn, Stronghold
did not object to them on this basis at the hearing, and therefore the
contentions are forfeited. (Niles Freeman Equipment v. Joseph (2008)

8
The privilege log shows that between November 2014 and July 2018,
Salameh was privy to a total of 18 privileged communications regarding the
Project and that she authored two of those emails. Further, the privilege log
shows Salameh’s last communication about the civil litigation was sent in
July 2018, approximately 20 months before March 2020, when the City
claimed it first learned of the subcontractor substitutions. Thus, Salameh’s
brief and tangential involvement in the civil litigation ended well before the
alleged Act violations were even discovered.
Salameh’s separation from the civil litigation makes the instant case
distinguishable from the cases Stronghold relies on. For example, in
Midstate Theatres, Inc. v. County of Stanislaus (1976) 55 Cal.App.3d 864, the
appellate court found dual representation to be improper where a lawyer
represented a county assessor whose valuations had been challenged, and the
same lawyer then advised the board of equalization at hearings addressing
the challenged assessments. (See also Howitt, supra, 3 Cal.App.4th 1575;
Nightlife, supra, 108 Cal.App.4th at p. 94 [city attorney’s “role as advisor to
the decision-maker” regarding denial of the plaintiff's regulatory permit
“violated petitioners’ right to due process” because the attorney “acted as both
an advocate of City’s position and as advisor to the supposedly neutral
decision-maker”].)

161 Cal.App.4th 765, 787 [“issues not presented at an administrative hearing
cannot be raised on review”].) Further, as the Board chair noted at the start
of the contested hearing, the hearing was informal, the rules of evidence did
not apply and “the Board may consider any evidence or information deemed
relevant and reasonably reliable.” The trial court necessarily considered
Salameh’s and Davi’s unsworn statements to be “reasonably reliable.” We do
as well.

9
Having concluded that the City sufficiently screened Salameh from the
civil litigation, we consider whether Stronghold met its burden of
establishing bias. We begin with the presumption of impartiality.
In Morongo, supra, 45 Cal.4th 731, the Morongo Mission Band of
Indians challenged the team of attorneys prosecuting a license revocation
case against the Band before the State Water Resources Control Board
because one of the attorneys was also advising the board on an unrelated
matter. (Id. at p. 734.) In considering the propriety of the dual
representation, the court dismissed the notion of an absolute separation
between an agency’s enforcement and advisory roles, emphasizing instead
the importance of the board’s impartiality. (Id. at p. 739, see id. at pp. 741–
742.) It found that in the absence of financial or personal interest, and where
the agency adheres to rules mandating internal separation of functions and
prohibiting ex parte communications, “the presumption of impartiality can be
overcome only by specific evidence demonstrating actual bias or a particular
combination of circumstances creating an unacceptable risk of bias.” (Id. at
p. 741.) The Morongo court rejected the idea of a blanket prohibition on
agency attorneys holding both advisory and prosecutorial roles
simultaneously, especially in unrelated matters. (Id. at pp. 739–741 & 740,
fn. 2.)
Thus, under Morongo, we presume the Board’s impartiality, unless
Stronghold can overcome the presumption “by specific evidence
demonstrating actual bias or a particular combination of circumstances
creating an unacceptable risk of bias.” (Morongo, supra, 45 Cal.4th at
pp. 741–742.) Stronghold has failed to present such evidence.

10
Relying on Ward v. Monroeville (1972) 409 U.S. 57 (Ward), Stronghold
suggests that Salameh and the Board had a financial interest in the outcome
of the hearing because penalties are paid to the City. We reject this
argument. In Ward, a mayor, authorized by state statute to sit as judge in
cases of certain traffic offenses, convicted the defendant of two such offenses
and fined him a total of $100. (Id. at p. 57.) Under these circumstances, the
court held that a possible temptation “to forget the burden of proof required
to convict the defendant” plainly existed because “the mayor’s executive
responsibilities for village finances may make him partisan to maintain the
high level of contribution from the mayor’s court.” (Id. at p. 60.)
In contrast, in Lent v. California Coastal Commission (2021)
62 Cal.App.5th 812 (Lent), the appellate court held the appellants, oceanfront
landowners, did not carry their burden of demonstrating the Coastal
Commission had such a disqualifying financial bias when it imposed a
penalty of more than $4 million for obstructing public access to the beach.
(Id. at pp. 825, 853.) The court found appellants “did not meet their burden
of showing the commissioners have a strong enough institutional financial
interest in the penalties they impose to create a constitutionally
impermissible risk of bias,” because no evidence existed showing how much
the commissioners rely on the penalties to carry out their executive duty to
implement the Coastal Act. (Id. at p. 853.) Without such evidence the court
could not “determine whether the commissioners’ motives are strong enough
to reasonably warrant a ‘fear of partisan influence’ on the Commission’s
judgment or to cause the commissioners “ ‘ “not to hold the balance nice,
clear, and true between the state and the accused.” ’ ” (Ibid.) Similarly,
Stronghold failed to produce any evidence to suggest that penalties fund the
Board’s work or pay Salameh’s salary. Absent such evidence, an adjudicator

11
with no financial interest in the outcome is “presumed to be impartial.”
(Morongo, supra, 45 Cal.4th at p. 737.)
Bias may not be implied; instead, the requisite evidence must come
from “ ‘concrete facts.’ ” (Nasha v. City of Los Angeles (2004) 125 Cal.App.4th
470, 483 (Nasha).) “ ‘[A] party’s unilateral perception of an appearance of
bias cannot be a ground for disqualification unless we are ready to tolerate a
system in which disgruntled or dilatory litigants can wreak havoc with the
orderly administration of dispute-resolving tribunals.’ ” (BreakZone Billiards
v. City of Torrance (2000) 81 Cal.App.4th 1205, 1237.) Here, beyond
Stronghold’s articulated concern about Salameh’s role, the record contains no
specific facts that establish actual bias or even the probability of bias on the
part of the Board as a result of Salameh’s advisory position during the
hearing.
Finally, Stronghold notes that the proposed decision Salameh drafted,
which the Board subsequently adopted without change, contained two
findings not directly ruled on by the Board, including: (1) “[i]n the interest of
fairness, the Board’s decision places the burden on the City to establish by a
preponderance of the evidence that [Stronghold] violated the [Act]”; and
(2) “This Board finds that [the City’s assessment of penalties was not barred
by the statute of limitations].” Stronghold contends the Board likely adopted
Salameh’s proposed decision based on her established relationship with the
Board. Stronghold likens this to the facts in Quintero v. City of Santa Ana
(2003) 114 Cal.App.4th 810,6 where the attorney played a leading role in
advising the personnel board about revision of its procedural rules and had
acted as the personnel board’s legal adviser in other matters during the years

6 Quintero disapproved of in part in Morongo, supra, 45 Cal.4th at
p., 740, fn. 2.)

12
immediately preceding the discharge claim at issue. (Id. at p. 816.) Here,
unlike Quintero, there is no evidence in the record showing Salameh had a
longstanding relationship with the Board before the contested hearing.
Moreover, while Stronghold is correct that the Board did not debate
who had the burden of proof or whether the City’s claims were untimely,
Stronghold raised both issues at the hearing and the City addressed the
timeliness issue in its closing argument. Stronghold does not explain why it
was improper for Salameh to include in the proposed decision two disputed
issues that had been presented to the Board at the contested hearing.
Additionally, the Board impliedly rejected Stronghold’s timeliness challenge
when it adopted the motion to assess penalties against Stronghold.
Under the independent standard of review, the foregoing facts do not
establish Stronghold was denied a fair hearing or suffered a due process
violation.
II. TIMELINESS OF THE CITY’S CLAIMS
Stronghold argues that the City’s claims were barred by laches, that
the one-year statute of limitations of Code of Civil Procedure section 340
applied, and that the City knew the facts giving rise to its claims under the
Act but inexcusably waited to initiate its claims.
A. Legal Principles
“Laches is an equitable time limitation on a party’s right to bring suit,
resting on the maxim that ‘equity aids the vigilant, not those who sleep on
their rights.’ ” (Magic Kitchen LLC v. Good Things Internat., Ltd. (2007) 153
Cal.App.4th 1144, 1156 (Magic Kitchen).) This principle “has been made
applicable to quasi adjudicative proceedings as a common law policy
pursuant to the ‘inherent power [of courts] independent of statutory
provisions to dismiss an action on motion of the defendant where it is not

13
diligently prosecuted.’ ” (Brown v. State Personnel Bd. (1985) 166 Cal.App.3d
1151, 1158).
Laches is an affirmative defense and the defendant has the burden of
proof on each element of the defense. (Highland Springs Conference &
Training Center v. City of Banning (2016) 244 Cal.App.4th 267, 282.) Where,
as here, “ ‘ “the trier of fact has expressly or implicitly concluded that the
party with the burden of proof did not carry the burden and that party
appeals,” ’ ” “ ‘ “the question for a reviewing court becomes whether the
evidence compels a finding in favor of the appellant as a matter of law” ’
because ‘ “ the appellant’s evidence was (1) ‘uncontradicted and unimpeached’
and (2) ‘of such a character and weight as to leave no room for a judicial
determination that it was insufficient to support a finding.’ ” ’ ” (Lent, supra,
62 Cal.App.5th at p. 837 [applying this standard to a laches defense].) “We
have no power on appeal to judge the credibility of witnesses or to reweigh
the evidence.” (Bookout v. State of California ex rel. Department of
Transportation (2010) 186 Cal.App.4th 1478, 1486.)
A laches defense has three elements: (1) the plaintiff delayed in
asserting a right or a claim; (2) the delay was not reasonable or excusable;
and (3) the defendant suffered prejudice.7 (Magic Kitchen, supra, 153
Cal.App.4th at p. 1157.) In matters before administrative agencies, “the
element of prejudice may be ‘presumed’ if there exists a statute of limitations
which is sufficiently analogous to the facts of the case, and the period of such
statute of limitations has been exceeded by the public administrative agency
in making its claim. In [this] situation, the limitations period is ‘borrowed’

7 Prejudice “ ‘ “ensues when a defendant has changed his position in a
way that would not have occurred if the plaintiff had not delayed.” ’ ” (Magic
Kitchen, supra, 153 Cal.App.4th at p. 1161.)

14
from the analogous statute, and the burden of proof shifts to the
administrative agency. To defeat a finding of laches, the agency . . . must
then (1) show that the delay involved in the case . . . was excusable, and
(2) rebut the presumption that such delay resulted in prejudice to the
opposing party. [Citations.].’ ” (Fountain Valley Regional Hospital &
Medical Center v. Bonta (1999) 75 Cal.App.4th 316, 324, fn. omitted
(Fountain Valley).)
We start, then, with determining the analogous statute of limitations.
B. Code of Civil Procedure section 388 is the analogous statute of limitation
Part 2 of Title 2 of the Code of Civil Procedure, entitled, “Of the Time of
Commencing Civil Actions,” provides a set of potentially analogous statutes
of limitations for consideration.
The trial court found the analogous statute of limitations for laches was
the three-year period in Code of Civil Procedure section 338, subdivision (a),
which establishes a three-year statute of limitations for “[a]n action upon a
liability created by statute, other than a penalty or forfeiture.” Stronghold
counters that the analogous statute of limitations for the laches defense is
Code of Civil Procedure section 340, subdivision (a), which establishes a
one-year statute of limitations for an action for a penalty.
Thus the question becomes whether the judgment against Stronghold
constitutes a penalty. In The TJX Companies, Inc. v. Superior Court (2008)
163 Cal.App.4th 80 (TJX Companies), the court considered which of the two
statutes at issue here applied in an action on an alleged violation of the Song-
Beverly Credit Card Act of 1971 (Civ. Code, §1747). The court explained that
the determining factor is whether the penalty is mandatory or discretionary.
Code of Civil Procedure, section 340 subdivision (a) applies if the penalty is
mandatory; and Code of Civil Procedure section 338 subdivision (a) applies if

15
the penalty is discretionary. (TJX Companies, at p. 85.) The statute in TJX
Companies provided that “[v]iolators ‘shall be subject to a civil penalty’ ” (id.
at p. 86), and therefore the court concluded that Code of Civil Procedure
section 340 subdivision (a) applied because the penalty was mandatory, even
though the amount of the penalty remained in the discretion of the awarding
authority. The TJX Companies court distinguished as permissive those
statutes in which the awarding authority had the discretion to decide
whether to impose a penalty at all, such as Civil Code section 1790, which
contains the permissive language, “the judgment may include . . . a civil
penalty . . . .” (See Jensen v. BMW of North America, Inc. (1995)
35 Cal.App.4th 112, 132, fn. 8.)
Here, the City asserted a statutory claim against Stronghold for
violation of section 4107. After the Board found that Stronghold violated
section 4107, it then assessed the award against Stronghold pursuant to
section 4110, which states: “A prime contractor violating any of the
provisions of this chapter violates his or her contract and the awarding
authority may exercise the option, in its own discretion, of (1) canceling his or
her contract or (2) assessing the prime contractor a penalty in an amount of
not more than 10 percent of the amount of the subcontract involved . . . .”
(Italics added.)
Whether a penalty under section 4110 is permissive or mandatory
presents a question of statutory interpretation which we review de novo.
(Ventura County Deputy Sheriffs’ Assnn. v. County of Ventura (2021) 61
Cal.App.5th 585, 590.) We begin our analysis with the “ ‘ “actual words of
[section 4110],” “giving them a plain and commonsense meaning . . . .” ’ ”
(Mikkelsen v. Hansen (2019) 31 Cal.App.5th 170, 178.) The above italicized

16
language in section 4110 shows that the imposition of any penalty under this
section is permissive, not mandatory.
Our plain reading of section 4110 is supported by an opinion from the
California Attorney General. The Attorney General was asked whether a
public entity could accept a construction bid that violated section 4104. (86
Ops.Cal.Atty.Gen. 90 (2003).) In reaching the conclusion the public entity
had the discretion to accept the bid, the Attorney General stated: “The terms
of section 4110 are permissive. The awarding authority is not required to
cancel the contract or impose a penalty but ‘may’ do so in the exercise of ‘its
own discretion.’ ” (Id. at p. 8.)8 The Attorney General also examined the
legislative history of section 4110 and concluded this history supported the
“ ‘plain meaning’ of the statute.” (Id. at p. 9.)
Accordingly, because section 4110 permits but does not mandate the
assessment of a penalty, we conclude that the claim here is “[a]n action upon
a liability created by statute, other than a penalty or forfeiture” making the
analogous statute of limitations the three-year period set forth in Code of
Civil Procedure section 338, subdivision (a). (See TJX Companies, supra, 163
Cal.App.4th at pp. 84–85.)
Turning then to the issue of delay, delay is “measured by the period
‘from when the plaintiff knew (or should have known) of the allegedly
infringing conduct, until the initiation of the lawsuit in which the defendant
seeks to counterpose the laches defense.’ ” (Magic Kitchen, supra,

8 “Although we are not bound by the Attorney General’s interpretation of
a statute, ‘ “ ‘[a]bsent controlling authority, [the Attorney General’s opinion]
is persuasive because we presume that the Legislature was cognizant of the
Attorney General’s construction of [the statute] and would have taken
corrective action if it disagreed with that construction.’ ” ’ ” (Towner v.
County of Ventura (2021) 63 Cal.App.5th 761, 773.)

17
153 Cal.App.4th at p. 1157.) Here, the action against Stronghold was
initiated by the City’s notification letter in September 2020. The issue for us
is when the City knew or should have known of the substitutions, so that we
can determine whether that date occurred more than three years before
September 2020.
The Board concluded the City’s claims were not time-barred because
evidence of the Act violations did not come to light until discovery in the
parties’ litigation related to the Project in 2019. Stronghold contends that
the City knew or should have known of the violations well before that time.
Because the facts regarding the City’s knowledge are different as to
each of the two subcontractors, we separately address each subcontractor
substitution below.
1. The Concrete Subcontractor Substitution Claim is Timely
Stronghold contends the City knew Perry was “West Coast Concrete”
no later than June 2016. Thus, it argues that even if the three-year
limitation period applied, the City’s claims would be untimely because
penalty claims were asserted more than three years after the substitutions
and are not subject to tolling or the discovery rule. Specifically, Stronghold
first argues the claim accrued when the substitution was made (i.e. when
Stronghold contracted with Perry), in December 2015, not when the City
discovered it. Stronghold cites no authority to support its contention that the
City’s cause of action accrued when Stronghold made the substitution and we
reject it. (In re Marriage of Stanton (2010) 190 Cal.App.4th 547, 561 [“When
a party provides a brief without argument or citation of authority, we may
‘treat the points as waived, or meritless, and pass them without further
consideration.’ ”].)

18
Stronghold further argues that the City’s claim was not subject to
tolling or the discovery rule, relying upon Eisenberg Village etc. v. Suffolk

Const. Co., Inc. (2020) 53 Cal.App.5th 1201 (Eisenberg).9 In Eisenberg, the
appellate court held that disgorgement claims against unlicensed contractors
were a penalty that must be made within one year of completion of the work
under Code of Civil Procedure section 340, subdivision (a). (Eisenberg, at
pp. 1212, 1214–1215.) Eisenberg is inapposite because it did not address the
equitable doctrine of laches. Rather, the delay element of the laches defense
is “measured by the period ‘from when the plaintiff knew (or should have
known) of the [wrongful] conduct, until the initiation of the lawsuit in which
the defendant seeks to counterpose the laches defense.’ [Citation.]” (Magic
Kitchen, supra, 153 Cal.App.4th at p. 1157.)
Stronghold next argues the City should have known of the substitution
when Stronghold signed its subcontract with Perry in December 2015. We
reject this assertion for two reasons. First, Stronghold had a statutory duty
to give notice of substitutions. (§ 4107, subd. (a).) The City had no legal
obligation to monitor construction for improper substitutions.
Second, there is nothing in the record to indicate that the City would
have been on notice that Stronghold had subcontracted with Perry (license
No. 857992), instead of West Coast Concrete (license No. 811853), which was
the entity named in its bid. Communications from Stronghold and

9 The common law discovery rule postpones accrual until a plaintiff
discovers or has reason to discover the cause of action. (Samuels v. Mix
(1999) 22 Cal.4th 1, 9.) In contrast, the equitable tolling doctrine “allows our
courts, ‘in carefully considered situations’ [citation], to exercise their inherent
equitable powers to ‘soften the harsh impact of technical rules’ [citation] by
tolling statutes of limitations.” (Saint Francis Memorial Hospital v. State
Dept. of Public Health (2020) 9 Cal.5th 710, 724.)

19
construction documents referred to the concrete subcontractor as West Coast
Concrete. Moreover, as the trial court noted, Stronghold used the names
West Coast Concrete and West Coast Construction interchangeably. In fact,
Stronghold’s position on appeal is that West Coast Concrete and Perry are
the same entity, an argument we reject. (Post, pt. III.) Stronghold does not
explain how the City could have determined that West Coast Concrete and
Perry were different entities when Stronghold itself continues to assert they
are not different entities. The evidence further fails to show that the City
ever acquiesced to the use of Perry instead of West Coast Concrete.
In sum, the evidence does not show that the City knew or should have
known that Stronghold had substituted in Perry at any time before it learned
of the substitution in 2019, well within the three-year statute of limitations.
Stronghold cannot establish prejudice, and there is no showing of delay or
inexcusable delay. (See Fountain Valley, supra, 75 Cal.App.4th at p. 324.)
Accordingly, the City’s claim as to the concrete subcontractor substitution is
not barred by laches.
2. The Waterproofing Subcontractor Substitution Claim is Untimely
We adopt the relevant legal analysis from the preceding section in
considering Stronghold’s substitution of F.D. Thomas for Rinaldi.
As to whether there was a delay causing prejudice, the evidence
indicates that the City should have known of the substitution as early as
June 28, 2016, when Ausonio, Inc. (Ausonio), the City’s construction
manager, wrote to Stronghold asking for a current subcontractor list. That
same day, Stronghold provided the list, which showed F.D. Thomas as the
waterproofing subcontractor. In August 2016, Ausonio requested a proposal
for the design-build of a system to seal underground concrete ductwork to
prevent water intrusion. F.D. Thomas quoted that work on September 1,

20
2016, and Stronghold passed along the quote to the City a few weeks later.
The City later negotiated directly with F.D. Thomas regarding the scope and
price of the work.
Although the City asserts Stronghold concealed its substitution of F.D.
Thomas for Rinaldi, the only evidence it cites to support this contention is a
construction record dated February 2017 from Stronghold listing Rinaldi as a
“finisher” and “[s]etter.” This document does not list Rinaldi as working on
waterproofing. Instead, the same document shows F.D. Thomas as doing the
waterproofing. The City’s concealment claim lacks merit and we reject it. If
anything, the construction record establishes that the very latest date that
the City should have known of the substitution was February 2017, when
Stronghold listed F.D. Thomas as the waterproofing subcontractor.
Whether the City “knew or should have known” of the substitution in
June of 2016, when Stronghold told Ausonio that F.D. Thomas was the
waterproofing subcontractor, or in February 2017, when the construction
record listed F. D. Thomas as the waterproofing contractor, it is clear that
over three years passed before the City notified Stronghold of the violation in
September 2020. Thus, a presumption arises that a prejudicial delay
occurred as to the F.D. Thomas substitution. (Magic Kitchen, supra, 153
Cal.App.4th at p. 1157; Fountain Valley, supra, 75 Cal.App.4th at pp. 323–
324.)
The City cites no evidence to rebut this presumption. Nor did the City
present any legally sufficient justification for their delay. Accordingly, even
viewing all factual matters most favorably to the City, Stronghold’s “ ‘
“uncontradicted and unimpeached” ’ ” evidence compels a finding in its favor
as a matter of law. (Ajaxo, Inc. v. E*Trade Financial Corp. (2020)
48 Cal.App.5th 129, 164.)

21
In sum, on this record the City’s delay in pursuing its claim as to the
substitution of the waterproofing subcontractor was unreasonable and
prejudiced Stronghold. Accordingly, the superior court abused its discretion
in refusing to find that laches barred this claim. (Craig v. City of Poway
(1994) 28 Cal.App.4th 319, 343.) We remand the matter to the trial court to
grant the administrative writ in part and set aside the $50,000 penalty
assessment imposed as to the substitution of the waterproofing
subcontractor.
III. SUBSTANTIAL EVIDENCE SUPPORTS THE BOARD’S
CONCLUSION THAT STRONGHOLD VIOLATED THE ACT AS TO THE
CONCRETE SUBCONTRACTOR10

Stronghold’s bid listed West Coast Concrete as the concrete
subcontractor. Stronghold instead contracted with Perry for the concrete
work. The Board found this substitution constituted a violation of the Act.
The trial court concluded that substantial evidence supported the Board’s
findings.
We address the relevant Act requirements and analyze whether
substantial evidence supported the Board’s conclusions. (JMS Air
Conditioning & Appliance Service, Inc. v. Santa Monica Community College
Dist. (2018) 30 Cal.App.5th 945, 967 (JMS) [“we review ‘the agency’s decision,
rather than the trial court’s decision” under the substantial evidence
standard”].) We stand in the shoes of the trial court and apply the same
standard of review. (Donley v. Davi (2009) 180 Cal.App.4th 447, 455–456.)
In applying this deferential review we presume Board’s findings are
supported by the administrative record; it is the appellant’s burden to show

10 Because we conclude that the action against the waterproofing
subcontractor is barred by laches, we do not address Stronghold’s further
arguments regarding the waterproofing subcontractor.

22
that they are not. We do not reweigh the evidence but indulge in all
presumptions and resolve all conflicts in favor of the Board’s decision. (Id. at
p. 456.)
A. The Act
“The Legislature enacted the [Act] . . . to prevent ‘bid shopping’ and ‘bid
peddling’ after the award of a public contract and to give the awarding
authority the opportunity to investigate and approve the initial
subcontractors and any replacements.” (Titan Electric Corp. v. Los Angeles
Unified School Dist. (2008) 160 Cal.App.4th 188, 202, fn. omitted (Titan
Electric).)11 The Act requires that for public work, a prime contractor must
specifically list in its bid the subcontractors it intends to use for the project.
(§ 4104.) The general contractor is required to provide “[t]he name, the
location of the place of business, the California contractor license number,
and public works contractor registration number issued pursuant to Section
1725.5 of the Labor Code of each subcontractor who will perform work or
labor or render service to the prime contractor . . . .” (Id., subd. (a)(1).)
Once the awarding authority accepts a bid, the Act permits the prime
contractor to substitute out a listed subcontractor only on nine enumerated
conditions. (§ 4107, subd. (a).) Eight of these conditions relate to the
unwillingness or inability of the listed subcontractor to perform the work.
(Id., subd. (a)(1)–(4), (6)–(9).) The remaining condition occurs when the prime
contractor demonstrates to the awarding authority that the name of the
subcontractor listed in the original bid was an inadvertent clerical error, but

11 “ ‘Bid shopping is the use of the low bid already received by the general
contractor to pressure other subcontractors into submitting even lower bids.
Bid peddling . . . is an attempt by a subcontractor to undercut known bids
already submitted to the general contractor in order to procure the job.’ ”
(Titan Electric, supra, 160 Cal.App.4th at p. 202, fn. 6.)

23
this condition is “subject to the further provisions set forth in Section 4107.5.”
(Id., subd. (a)(5).)
Section 4107.5 requires that a prime contractor’s claim of inadvertent
clerical error in the listing of the subcontractor be made “within two working
days after the time of the prime bid opening by the awarding authority,” with
timely notice to both the listed subcontractor and the intended subcontractor.
The Act further provides for a public hearing if the listed subcontractor
timely objects. “The two-day written notice provision of section 4107.5 fosters
[the legislative purpose of the Act] by forcing the prime contractor to assert
its error in short order, and on the record, thus minimizing the time in which
the contractor can shop for lower bids and limiting the room for deceptive
maneuver.” (Cal–Air Conditioning, Inc. v. Auburn Union School Dist. (1993)
21 Cal.App.4th 655, 668.)
Additionally, after accepting a bid the general contractor cannot
“[p]ermit a subcontract to be voluntarily assigned or transferred or allow it to
be performed by anyone other than the original subcontractor listed in the
original bid, without the consent of the awarding authority, or its duly
authorized officer.” (§ 4107, subd. (b).) The agency has the right to
investigate the proposed substitution and reject it if unacceptable. (See Titan
Electric, supra, 160 Cal.App.4th at page 202 [the Act gives “the awarding
authority the opportunity to investigate and approve the initial
subcontractors and any replacements”].) “These procedures require that a
subcontractor receive written notice of a substitution request and, if the
subcontractor timely objects, ‘the awarding authority’ must hold a hearing to
decide if it will allow the substitution.” (JMS, supra, 30 Cal.App.5th at
p. 951.)

24
If a prime contractor violates the Act, it “violates [its] contract,” and the
awarding authority has discretion to either cancel the contract or assess a
penalty of up to “10 percent of the amount of the subcontract involved.”
(§ 4110.)
B. Additional Background
Stronghold’s bid listed West Coast Concrete, license number 811853, as
the concrete subcontractor. License No. 811853 actually belongs to South
Coast Concrete Construction dba South Coast Construction located in
Riverside, California at 6770 Central Ave # B. On October 20, 2015, West
Coast Construction, license No. 857992, submitted to Stronghold a written
proposal for concrete work on the Project, and Stronghold accepted the
proposal in December 2015. The Contractor’s State License Board lists
license No. 857992 as belonging to Perry “dba West Coast Construction”
located in Riverside, California on 14457 Meridian Parkway. In sum,
Stronghold’s bid listed “West Coast Concrete,” license No. 811853, but it
entered into the subcontract for the concrete work on the Project with Perry
“dba West Coast Construction,” license No. 857992.
Perry has a “B-General Building Contractor” license, not the C-8
concrete contractor’s license necessary for the Project. The City’s public
works director and city engineer testified at the Board hearing that a class
“B” contractor can do driveways and sidewalks but not structural work. The
fact Perry did not have a license to do structural concrete concerned him
because the Project required “a lot of structural concrete” of good quality to
withstand earthquakes. Based on the erroneous information contained in the
bid submitted by Stronghold, he could not determine which company was
responsible for the work or what type of license that company held. Further,

25
there is no evidence that Stronghold ever requested the City’s consent to
substitute Perry for West Coast Concrete.
C. Analysis
Stronghold argues the evidence shows it intended to contract with
Perry, even though it failed to identify Perry by its correct name and wrote
the wrong license number in its bid to the City.12 Stronghold argues the trial
court erred in failing to interpret the contract and subcontract under the
rules of contract interpretation to determine Stronghold’s intent and the
City’s understanding. We disagree. The goal of contract interpretation is to
ascertain the parties’ mutual intent at the time of contracting. (Civ. Code,
§ 1636.) The mutual intent of the parties is determined by the words used in
the agreement, which are to be understood in their ordinary and popular
sense. (Id., § 1644.) Mutual intention is determined by objective
manifestations of the parties’ intent including the surrounding circumstances
under which the parties entered into the contract, the object, nature and
subject matter of the contract, and the subsequent conduct of the parties.
(Morey v. Vannucci (1998) 64 Cal.App.4th 904, 912.)
The trial court concluded that Stronghold’s intent to contract with
Perry is irrelevant. We agree. The relevant question is what Stronghold and
the City intended at the time of contracting. On this issue, the only evidence
is the bid Stronghold submitted to the City naming West Coast Concrete as
the concrete subcontractor and listing a license number belonging to South

12 If Stronghold’s inclusion in its bid of West Coast Concrete and license
number 811853 was made in error, Stronghold could have avoided the bid
mistake if it had followed the edicts of section 4104 by providing not only the
subcontractor’s name and contractor license number but also the
subcontractor’s place of business (id. subd. (a)(1)) and then confirming that
the information it listed in its bid aligned with the subcontractor it allegedly
intended, i.e., Perry.

26
Coast Concrete Construction. The bid Stronghold submitted did not alert the
City that Perry “dba West Coast Construction” would be the concrete
subcontractor.
Moreover, section 4107.5 directs what a prime contractor must do when
it makes an inadvertent clerical error in its original bid. Namely, within two
working days after the City opened the bid, Stronghold was required to give
written notice to the City, West Coast Concrete, South Coast Concrete
Construction, and Perry that the West Coast Concrete name and the South
Coast Concrete Construction license number were listed in error. West Coast
Concrete and South Coast Concrete Construction then had six working days
to submit a written objection to Stronghold and the City. The failure of a
listed subcontractor to timely file an objection constitutes “primary evidence
of his or her agreement that an inadvertent clerical error was made.”
(§ 4107.5.) Thereafter, a public hearing must be held before the awarding
authority may consent to the substitution. (Ibid.)
Thus, if the inclusion of West Coast was a typographical error,
Stronghold was required to comply with section 4107.5, so that the error
could be promptly rectified. Stronghold did not do so.
Alternatively, if Stronghold wished to make a substitution from West
Coast to Perry, it was first required to comply with section 4107, subdivision
(b) and obtain the City’s consent to the substitution. Stronghold did not do
so.
In summary, we conclude substantial evidence supports the Board’s
finding that Stronghold unlawfully substituted its concrete subcontractor.

27
DISPOSITION
The judgment denying mandamus relief is affirmed in part and reversed
and remanded in part as follows: On remand, the trial court is directed to issue
a writ of administrative mandate compelling the Board to set aside the penalty
assessment issued regarding the substitution of the waterproofing
subcontractor. In all other respects, the judgment is affirmed. In the interests
of justice, each side shall bear its own costs on appeal. (Cal. Rules of Court, rule
8.278(a)(5).)

KELETY, Acting P. J.

WE CONCUR:

CASTILLO, J.

RUBIN, J.

28