Filed 8/27/25 Suffolk Construction Co. v. L.A. Unified School District CA2/7
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has
not been certified for publication or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
SECOND APPELLATE DISTRICT
DIVISION SEVEN
SUFFOLK CONSTRUCTION B314311
COMPANY, INC.,
(Los Angeles County
Plaintiff and Appellant, Super. Ct. No. BC494389)
v.
LOS ANGELES UNIFIED SCHOOL
DISTRICT,
Defendant and Appellant.
APPEAL from a judgment of the Superior Court of
Los Angeles County, Maren Nelson, Judge. Affirmed with
modifications.
KP LAW, Zareh A. Jaltorossian, Pierce Kavcioglu Espinosa
& Cesar, Timothy L. Pierce and Hector H. Espinosa for Plaintiff
and Appellant.
Theodora Oringher, Kevin A. Dorse, Panteha Abdollahi,
Brian J. Headman, Erich R. Luschei and Timothy J. Heggem;
Office of the General Counsel, Devora Navera Reed and Mark
Fall for Defendant and Respondent.
________________________
INTRODUCTION
Suffolk Construction Company, Inc. sued the Los Angeles
Unified School District (District or LAUSD) for breach of contract
related to its construction of the Bell Education and Career
Center. Suffolk recovered significant damages on several of its
contract claims and judgment was entered in its favor, but the
jury found against it with regard to certain amounts Suffolk
claimed were wrongfully retained by the District. Suffolk argues
the trial court erred by entering judgment notwithstanding the
verdict in favor of the District (rather than Suffolk) on the
retention claim, and that it is entitled to a limited new trial on
that issue because the jury returned an inconsistent verdict and
the special verdict form included a “legally problematic” question.
Suffolk also challenges the trial court’s ruling it was not entitled
to recover from the District attorney fees Suffolk incurred in
related litigation with its subcontractors. We affirm the
judgment as it relates to Suffolk’s appeal.
The District cross-appeals from the trial court’s award of
attorney fees, costs, and prejudgment interest. The District
contends the trial court applied incorrect legal criteria to
determine that Suffolk was the prevailing party for purposes of
attorney fees and costs. The District also contests the trial
court’s award of prejudgment interest on three payments the
District made to Suffolk after Suffolk filed suit. We modify the
judgment to reduce the prejudgment interest award and
otherwise affirm the judgment as modified.
2
FACTUAL AND PROCEDURAL BACKGROUND
A. The Prime Contract
On November 10, 2010, the District contracted with Suffolk
to build the Bell Education and Career Center (the project) for
approximately $25 million.1 Suffolk hired subcontractors
Best Contracting Services, Inc. and Quality Production Services,
Inc. (QPS), among others, in connection with the project.
The prime contract required the project to be substantially
completed by June 26, 2012, but the project was delayed
141 days. Although the school was opened and students began to
use some of the facilities in August 2012, the project was not
substantially completed until November 14, 2012.2 The prime
contract authorized liquidated damages of $3,000 per day up to
180 calendar days if Suffolk failed to meet the substantial
completion deadline.
Article 12 of the General Conditions and Supplementary
Conditions and sections 3.06 and 3.07 of Specification 01360 in
the Construction Schedule set out procedures by which Suffolk
could seek extensions of time or additional compensation for
extra work. Article 12.1 stated, “All time limits in the Contract
are of the essence. The Contract Time and/or Milestones can only
be adjusted by a Change order.” Article 12.3 entitled Suffolk to
compensation for delays to the project caused by the District.
Articles 12.4 and 12.5 required Suffolk to provide written notice
1 We adopt the parties’ reference to this contract as the
prime contract.
2 The record indicates the school was completed and all work
finished by March 2013.
3
on a form provided by the District of any “issue, event condition,
circumstance and/or cause of a perceived and/or actual delay,
disruption, interference, hindrance, and/or acceleration” within
three working days after first encountering the issue and within
three working days of the end of the issue. If Suffolk then
wanted an adjustment to the timeline or additional payment, it
was required under Article 12.6 to submit a change order
proposal (COP) within 35 days of the Article 12.5 notice.
Sections 3.06 and 3.07 set out requirements for monetary
recovery for delays and requests for extensions of time. In
pertinent part, section 3.06 provided: “Prior to submitting any
time extension request to the Owner, the Contractor shall first
demonstrate the impact by use of a detailed pre-delay and post-
delay time impact analysis fragnet with an accompanied written
narrative as outlined in Section 01360—Construction Schedule.”3
Section 3.07 provided detailed requirements for time extension
requests. Section 3.07 also emphasized, “Adjustments to
Milestones and/or Contract Time will only be authorized by
Change Order.”
B. Change Order Proposal 199.3
On July 6, 2012, Suffolk submitted COP 199, which sought
an unspecified delay to the substantial completion date. COP 199
stated the delay was “TBD” or to be determined. The District
rejected COP 199 and two subsequent versions for, among other
3 At trial, one of the District’s witnesses testified that a
“fragnet is a detailed explanation of what you did to get to where
you say you got; so . . . it’s a cookbook tactic. It’s a blow by blow
here is what I did. I had to move this in front of that. We had
overtime. It shows how you got to where you say you got.”
4
things, failure to comply with the procedures outlined in
Article 12 and sections 3.06 and 3.07. On May 24, 2013, after the
November 14, 2012 substantial completion date, Suffolk
submitted COP 199.3. COP 199.3 was the final iteration of
COP 199 and the version at issue at trial. In COP 199.3, Suffolk
requested a time extension of 111 days and over $4 million it
asserted was incurred due to District-caused delays. In
particular, COP 199.3 requested acceleration and delay costs
primarily related to problems with the installation of commercial
kitchen hoods and a marquee sign.
On June 6, 2013, the District rejected COP 199.3, noting it
was “as equally inconclusive as the previous versions.” The
District asserted, “Suffolk’s claim that the delay to the project’s
completion was District caused is not supported.” Instead, the
District attributed the delay to the default of Suffolk’s steel
subcontractor at the beginning of the project which had a ripple
effect on subsequent deadlines, as well as the defaults of other
“critical” trades. The District further asserted Suffolk failed to
adhere to Suffolk’s own proposals to recover time by utilizing
overtime, resequencing work, allowing for concurrent work, and
furnishing and maintaining a sufficient workforce.
C. The Lawsuit
On January 24, 2012, Suffolk sued the District, alleging
three causes of action. In the first cause of action for breach of
contract, Suffolk alleged the District failed to pay all sums due
under the prime contract, including progress payments and
5
retention amounts.4 The prime contract contained a 10 percent
retention provision. The District was required to release the
retention amounts withheld from each progress payment within
60 days of completion of the project. Here, the District withheld
$423,000 of the retention amount as liquidated damages
($3,000 per day x 141-day delay). Suffolk also alleged the District
caused delays that resulted in damages.5 Suffolk claimed
damages in the amount of $5 million in connection with its
breach of contract cause of action.
In the second cause of action for implied contractual
indemnity and the third cause of action for declaratory relief,
4 “Construction contracts often call for payment in
installments—known commonly as progress payments—due
when a project reaches various stages of completion. . . . As an
additional hedge against nonperformance and incentive for
completion, an owner may withhold a small percentage of the
money due at each stage—typically 5 to 10 percent—until the
project is finished. [Citations.] If the contractor defaults, or
subcontractors assert mechanics liens for nonpayment, the owner
can use this retention fund to make payment or seek substitute
performance. [Citations.] Once work is done to the owner’s
satisfaction and the period for filing liens has expired, the owner
will release the retention.” (United Riggers & Erectors, Inc. v.
Coast Iron & Steel Co. (2018) 4 Cal.5th 1082, 1087-1088 (United
Riggers).)
5 “‘A building contractor whose performance is delayed by the
owner may have increased overhead and fixed costs resulting
from a delay and may suffer labor and material cost increases or
loss of labor productivity due to delays for all of which he or she
would be entitled to damages.’” (JMR Construction Corp. v.
Environmental Assessment & Remediation Management, Inc.
(2015) 243 Cal.App.4th 571, 586.)
6
Suffolk sought to be indemnified by the District for any damages
or costs it incurred in defending and resolving lawsuits
previously filed by its subcontractors in connection with the
project. The subcontractor suits were subsequently consolidated
with the action filed by Suffolk against the District. Before trial,
the subcontractors settled with Suffolk and agreed to have
Suffolk litigate their claims on a “pass-through” basis.6
The case was tried in phases. In the first phase, the trial
court ruled on an affirmative defense that is not challenged on
appeal or cross-appeal. In the second phase, a jury decided
Suffolk’s breach of contract claim against the District. In the
third phase, the trial court decided Suffolk’s entitlement to
recover, as damages, the attorney fees it incurred to defend itself
in the subcontractor actions, and the attorney fees it paid to the
subcontractors pursuant to fee provisions in the subcontractor
contracts and in the payment bonds Suffolk was required to
obtain. Suffolk challenges the second and third phase findings in
its appeal. The District’s cross-appeal challenges the trial court’s
subsequent attorney fees and prejudgment interest award.
6 “When a public agency breaches a construction contract
with a contractor, damage often ensues to a subcontractor. In
such a situation, the subcontractor may not have legal standing
to assert a claim directly against the public agency due to a lack
of privity of contract, but may assert a claim against the general
contractor. In such a case, a general contractor is permitted to
present a pass-through claim on behalf of the subcontractor
against the public agency.” (Howard Contracting, Inc. v. G. A.
MacDonald Constr. Co. (1998) 71 Cal.App.4th 38, 60.)
7
1. The Second-phase Jury Trial
A significant issue at trial was which party bore
responsibility for the 141-day delay to the project’s substantial
completion date, for which the District withheld $423,000 in
retention amounts as liquidated damages. The trial court
instructed the jury that Suffolk claimed, “the District breached
this contract by providing incorrect plans and specifications for
various items of work including the steel framing and kitchen
hood support layout among other things. Suffolk also claim[ed]
that the District breached the contract by failing to timely review
and correct design errors in the plans and specifications, failing
to review and approve change order requests, make payments for
extra and completed work, and refusing to pay all sums due
under the contract. Suffolk further claim[ed] that the District
breached the contract by interfering with and delaying Suffolk
from performing its obligations and unilaterally directing the
contractor’s means and methods of construction.” In particular,
Suffolk asserted the project was delayed because there were
conflicts between the design of the kitchen hood supports to be
installed in the ceiling and the other mechanical and electrical
components contained in the ceiling. Suffolk also asserted the
District failed to request the installation of a marquee until after
the project had begun, leading to delays in obtaining approval
from the State of California for its design and installation.
At trial, the District argued to the jury that Suffolk’s
mismanagement was to blame for the delay as well as the default
of its original steel subcontractor, which caused downstream
delays. The District also argued Suffolk was not entitled to
recovery of the liquidated damages because it failed to
substantially comply with the COP and fragnet requirements
8
contained in Article 12 and sections 3.06 and 3.07 in seeking
additional time, payment, or change orders.
The jury found in favor of Suffolk on its general breach of
contract claim and awarded damages for specified breaches,
including for COPs that were improperly rejected by the District,
for other COPs that were only partially approved, and for the
District’s failure to pay the contract balance. The jury further
found COP 199.3 did not satisfy the contract claim procedures
contained in Article 12 and sections 3.06 and 3.07. As a result,
the jury did not award damages related to the District’s rejection
of COP 199.3. As further explained in the Discussion below, the
special verdict form instructed the jury to stop deliberations and
return the verdict if it found COP 199.3 did not satisfy the
contract claim procedures. The trial court, however, instructed
the jury to continue its deliberations. After it answered three
additional questions on the verdict form, the jury was discharged.
The parties filed cross-motions for judgment
notwithstanding the verdict (JNOV) and Suffolk additionally
filed a motion for a new trial. The trial court granted the
District’s JNOV motion and denied Suffolk’s motions for JNOV
and new trial. We describe the posttrial motions and the court’s
ruling in greater detail below.
2. The Third-phase Bench Trial
In the third phase, the court conducted a bench trial on the
issue of attorney fees as damages. Suffolk argued its damages
included attorney fees and costs it was required to pay to the
subcontractors pursuant to statutory and contractual fee
provisions, as well as the fees Suffolk incurred in defending itself
in the subcontractor actions. Suffolk contended it was entitled to
9
recover those attorney fees under a theory of implied contractual
indemnity. The trial court ruled Suffolk could not recover those
fees as a matter of law. We discuss the proceedings more
extensively below.
Judgment on the jury verdict was entered in favor of
Suffolk on its general breach of contract claims and in favor of
the District on the implied contractual indemnity claim.
Damages and penalty interest were also awarded to Suffolk. The
judgment reserved consideration of attorney fees, costs and
prejudgment interest.
3. The Attorney Fees and Prejudgment Interest Orders
After the court entered judgment, Suffolk and the District
filed competing motions for attorney fees and to strike or tax the
other party’s memorandum of costs. Suffolk additionally filed a
motion for prejudgment interest. The trial court issued one order
addressing these motions. The court awarded Suffolk attorney
fees in the amount of $32,726.50 pursuant to Public Contract
Code, section 7107 (section 7107), awarded Suffolk costs of
$169,484.72 under that same section, and granted Suffolk’s
motion for prejudgment interest in the amount of $216,044
pursuant to Civil Code section 3278.
A “final amended judgment on jury verdict” was entered
January 22, 2022, awarding damages to Suffolk in the total
amount of $856,429, penalty interest in the amount of $26,681,
and fees, costs, and prejudgment interest as set forth above.
Suffolk timely appealed, and the District timely cross-
appealed.
10
DISCUSSION
A. The Trial Court Properly Granted the District’s Motion for
JNOV and Denied Suffolk a New Trial and JNOV
Suffolk argues a new trial was required because the jury
returned an inconsistent verdict. It further contends the
District’s motion for JNOV was wrongly granted. We conclude
the trial court properly granted the District’s motion for JNOV
and denied Suffolk’s motion for JNOV and new trial motions.
1. Additional Proceedings
a. The special verdict and jury deliberations
Before closing arguments, the parties and the court
discussed the verdict form and jury instructions over several
days. Among the issues discussed was the interplay between
compliance with the prime contract as a whole by completing the
project and compliance with various individual provisions of the
contract. Suffolk argued that substantial performance of the
prime contract is shown as a matter of law in construction cases
when an owner has taken possession of the building. Suffolk
further argued that substantial compliance with individual COPs
or claims would be addressed “at the damage level. Did we do
what we’re supposed to, to recover our overtime claim? Did we do
what we’re supposed to, to recover our extended general
conditions claim?”
The District argued (correctly) that substantial compliance
with the prime contract by completing the project was different
from substantial compliance with the contract claim procedures
in Article 12 or sections 3.06 and 3.07. The District requested a
special verdict question and jury instructions specifically directed
11
to whether COP 199.3 fulfilled the prime contract’s claim
procedure requirements. Suffolk rejected parsing out substantial
compliance as to each component of COP 199.3.
The jury was ultimately presented with a 14-question
special verdict form. The relevant portions are as follows:
BREACH OF CONTRACT
QUESTION NO. 1: Did the Los Angeles Unified School
District (“LAUSD”) breach the implied warranty of
correctness of plans and specifications in the contract by
providing Project plans or specifications to Suffolk
Construction Company. Inc. (“Suffolk”) that were not
correct?
___ YES ___ NO
Continue to Question No. 2.
QUESTION NO. 2: Did LAUSD breach the contract by
failing to do something the contract required it to do?
___ YES ___ NO
If you selected “YES” to Question No. 1 or Question No. 2,
continue to Question No. 3. If you selected “NO” to Question
No. 1 and Question No. 2, stop and have the presiding juror
sign and date this form.
QUESTION NO. 3: Was LAUSD’s breach of contract a
substantial factor in causing harm to Suffolk?
___ YES ___ NO
If you selected “YES” continue to Question No. 4. If you
selected “NO” stop and have the presiding juror sign and
date the form.
12
DAMAGES FOR EXTRA WORK AND CONTRACT BALANCE
QUESTION NO. 4: What damages for extra work, if any is
Suffolk entitled to for the following claims (the amounts
include amount for QPS and Best)?
A. Rejected COPS
[listing 10 COPs not at issue in this appeal]
B. Partially Approved Change Orders
[listing six change orders not at issue in this appeal]
C. Contract Balance (includes Buy-Out Savings,
Contingency and unpaid Contract Balance)
Continue and answer Question No. 5.
DAMAGES FOR DELAY, ACCELERATION, AND
LOST PRODUCTIVITY
QUESTION NO. 5: Subject to the Court’s
instructions on this issue, did Suffolk substantially
comply with the contract claim procedures with
respect to COP 199.3?[7]
7 Of relevance to Question 5 were Jury Instruction Nos. 38 to
41. Jury Instruction No. 38 stated the agreed procedures for
handling claims “govern the format of the claims and the manner
in which the claims are presented,” and “the contractor must
follow those procedures except as I will explain to you.”
Jury Instruction No. 39 stated Suffolk must prove it made a
good faith effort to comply with the contract and time extension
procedures and that it “substantially achieved the purpose of the
claims procedure” to assure the District had notice and
opportunity to review the issues raised in COP 199.3.
13
___ YES ___ NO
If you selected “YES” continue to Question No. 6. If you
selected “NO” stop and have the presiding juror sign and
date the form.
On June 4, 2019, the jury returned the verdict form and
answered “Yes” to Questions 1 through 3. It determined Suffolk
was entitled to a total of $592,609 for the damages identified in
Questions 4A and 4B. It also found the District owed a contract
balance in Question 4C of $318,665. The jury responded “No” to
Question 5 and, pursuant to the directions on the verdict form,
the presiding juror signed and dated the form and returned it to
the court.8
Upon receiving the verdict, the trial court asked the parties
whether it was ambiguous, and the parties discussed whether the
jury should answer any other questions in the verdict form.
Suffolk argued Questions 11 through 14 (“Prompt Payment
Penalties”) were not precluded by the jury’s “No” response to
Question 5. In its view, the jury’s award of a contract balance
under Question 4C could include some retention amount or
progress payment and thus the jury should be directed to answer
Questions 11 through 14. The District opposed sending the jury
Jury Instruction Nos. 40 and 41 stated the District must
have been prejudiced by Suffolk’s failure to give timely notice
under the prime contract and that Suffolk could be excused from
strict compliance with the notice provision if the District had
timely actual notice of the claims.
8 The jury never answered questions 6 through 10 of the
special verdict, which dealt with damages relating to COP 199.3
and are not relevant to any issue on appeal.
14
back for further deliberations, arguing the verdict was not
ambiguous on its face. The trial court instructed the jury to
continue its deliberations and to answer Questions 11 and 13,
and Questions 12 and 14, if appropriate.
Questions 11 through 14 provided:
PROMPT PAYMENT PENALTIES
QUESTION NO. 11: Did LAUSD wrongfully withhold
retention payments from Suffolk?
___ YES ___ NO
If you selected “YES” continue to Question No. 12. If you
selected “NO” stop and have the presiding juror sign and
date the form.
QUESTION NO. 12: For any amounts you find LAUSD
wrongfully withheld from retention payments, provide the
first date the funds were improperly withheld and the
amount withheld (only use the lines below as needed to list
improperly withheld amounts):
QUESTION NO. 13: Did LAUSD wrongfully withhold the
progress payments for Suffolk’s Payment Application
No. 24?
___ YES ___ NO
If you selected “YES” continue to Question No. 14. If you
selected “NO” stop and have the presiding juror sign and
date the form.
15
QUESTION NO. 14: State the amount that LAUSD
wrongfully withheld from Payment Application No. 24 and
the first date those funds were improperly withheld.
During its continued deliberation, the jury asked, “May we
have the relevant exhibits regarding question no. 12 and no. 14?
Also, proposed amounts for late payments, and dates?” The
parties prepared a list of relevant exhibits and a chart for the
jury listing “Proposed Prompt Payment Penalty Amounts/Dates.”
As to Question 12, Suffolk proposed two amounts: $423,000
withheld on January 13, 2013 and $166,754 withheld on
January 23, 2015. The District objected to answering these
questions given the jury’s response to Question 5. The court
stated, “I understand that point of view, . . . I think we are better
off giving answers to these questions th[a]n not.” The District
then proposed a prompt payment penalty amount of “$0 to
maximum of $166,754.77 (LAUSD disputes merit)” that was
withheld on March 23, 2015, “if applicable.”
After further deliberations, the jury responded “Yes” to
Question 11, finding the District did “wrongfully withhold
retention payments from Suffolk” in the amount of $111,000 in
liquidated damages on January 13, 2013 and $166,754 in
retention amounts on March 23, 2015 (Question 12). The jury
responded “No” to Question 13 and did not answer Question 14,
as directed. The trial court discharged the jury after polling
them.
b. The posttrial motions
After the jury returned the verdict, the parties filed cross
motions for JNOV. Suffolk also filed a motion for a new trial.
16
The District argued the jury’s finding in Question 5 that Suffolk
failed to substantially comply with the contractual claim
procedures in COP 199.3 meant the District did not wrongfully
withhold retention amounts, despite the jury’s response to
Question 12 that the District wrongfully withheld $111,000 in
retention amounts as liquidated damages.9 According to the
District, the trial court was empowered to enter JNOV in its
favor on the issue of wrongfully withheld retention amounts to
resolve this ostensible inconsistency in the verdict because it
presented an issue of law.
Suffolk argued a new trial on COP 199.3 was “the only
means to resolve the inconsistent verdicts” and that Question 5
was legally erroneous, which resulted in a legally flawed verdict.
It also asserted it was entitled to JNOV because the jury’s
response to Question 5 was not supported by the evidence and
was invalid.
The trial court issued a 42-page order granting the
District’s JNOV motion and denying Suffolk’s motions for JNOV
and new trial. It determined that, “The verdict form does not
contain irreconcilable factual findings, express or implied.” The
court explained, “The fact that the jury found in Question 4
[awarding damages for breach of the prime contract] that Suffolk
was entitled to some payment under the Prime Contract for
9 The parties acknowledge the District released $166,754 of
retention amounts to Suffolk before trial and that amount was
not at issue in the parties’ posttrial motions. Because the jury
determined the District wrongfully withheld $166,754 in
retention amounts, however, Suffolk was entitled to penalty
interest on that amount under section 7107. The judgment
therefore granted Suffolk $26,681 in penalty interest.
17
specific items does not imply that it was entitled to a time
extension. The answer to Question 5 [noncompliance with claim
procedures] is the jury’s factual finding that Suffolk failed to
substantially comply with the contract’s procedures for payment
for a time extension and that LAUSD was prejudiced by that
conduct. The answer to Question 12 [awarding damages despite
noncompliance with claim procedures] reflects the jury’s factual
finding that LAUSD was responsible for 37 days of the delay in
completing the Project. All of these factual determinations are
fully within the evidence presented. However, under the terms of
the Prime Contract, Suffolk cannot recover monies for delay or
acceleration where it did not comply with the procedures for a
time extension, even if the jury found that LAUSD delayed the
project for 37 days. [Citation.] This is a legal consequence of the
three factual findings.”
In other words, the trial court determined the verdict
contained a legal inconsistency it could resolve by granting JNOV
to the District on the issue of wrongfully withheld retention
amounts.
2. Standard of Review
“‘[A] special verdict’s correctness must be analyzed as a
matter of law.’” (City of San Diego v. D.R. Horton San Diego
Holding Co., Inc. (2005) 126 Cal.App.4th 668, 678 (City of
San Diego); see McCoy v. Gustafson (2009) 180 Cal.App.4th 56,
94 (McCoy).) “We analyze the special verdict form de novo.”
(Saxena v. Goffney (2008) 159 Cal.App.4th 316, 325 (Saxena).)
“‘A motion for judgment notwithstanding the verdict may
be granted only if it appears from the evidence, viewed in the
light most favorable to the party securing the verdict, that there
18
is no substantial evidence in support. [Citation.] [¶] . . . As in
the trial court, the standard of review [on appeal] is whether any
substantial evidence—contradicted or uncontradicted—supports
the jury’s conclusion.’” (Cabral v. Ralphs Grocery Co. (2011)
51 Cal.4th 764, 770; accord, Webb v. Special Electric Co., Inc.
(2016) 63 Cal.4th 167, 192; Markow v. Rosner (2016)
3 Cal.App.5th 1027, 1045 (Markow).) But where the “sole
question before us . . . is one of law” and the “jury . . . was not
asked to resolve any factual questions bearing on the question,”
we “address the issue under a de novo standard of review.”
(Sweatman v. Department of Veterans Affairs (2001) 25 Cal.4th
62, 68 (Sweatman); see Brown v. City of Sacramento (2019)
37 Cal.App.5th 587, 598 [“to the extent a motion for judgment
notwithstanding the verdict raises legal issues such as the
application of law to undisputed facts . . . , we review the trial
court’s ruling on the motion de novo”]; Wolf v. Walt Disney
Pictures & Television (2008) 162 Cal.App.4th 1107, 1138 [same].)
We generally review orders granting or denying a motion
for a new trial for abuse of discretion. (See Aguilar v. Atlantic
Richfield Co. (2001) 25 Cal.4th 826, 859; Denton v. City and
County of San Francisco (2017) 16 Cal.App.5th 779, 794.) But
“any determination underlying any order is scrutinized under the
test appropriate to such determination.” (Aguilar, at p. 859;
accord, Tun v. Wells Fargo Dealer Services, Inc. (2016)
5 Cal.App.5th 309, 323.) Here, we review the trial court’s
posttrial orders, including its denial of Suffolk’s new trial motion,
de novo because they present questions of law. (See Aguilar, at
p. 860.)
19
3. Background Law
“‘The verdict of a jury is either general or special. A
general verdict is that by which they pronounce generally upon
all or any of the issues, either in favor of the plaintiff or
defendant; a special verdict is that by which the jury find the
facts only, leaving the judgment to the Court. The special verdict
must present the conclusions of fact as established by the
evidence, and not the evidence to prove them; and those
conclusions of fact must be so presented as that nothing shall
remain to the Court but to draw from them conclusions of law.’
(Code Civ. Proc., § 624.)” (J.P. v. Carlsbad Unified School Dist.
(2014) 232 Cal.App.4th 323, 338.) “The elements of a cause of
action constitute the essential or ultimate facts in a civil case.”
(Stoner v. Williams (1996) 46 Cal.App.4th 986, 1002.) “Ultimate
facts are distinguished from evidentiary facts and from legal
conclusions.” (Central Valley General Hospital v. Smith (2008)
162 Cal.App.4th 501, 513 [“the term ‘ultimate fact’ generally
refers to a core fact, such as an essential element of a claim”].) A
special verdict must resolve every controverted issue in the case.
(See Myers Building Industries, Ltd. v. Interface Technology, Inc.
(1993) 13 Cal.App.4th 949, 960.)
“A special verdict is inconsistent if there is no possibility of
reconciling its findings with each other.” (Huy Fong Foods, Inc. v.
Underwood Ranches, LP (2021) 66 Cal.App.5th 1112, 1125; see,
e.g., Trejo v. Johnson & Johnson (2017) 13 Cal.App.5th 110, 123-
124 (Trejo) [jury found the defendant liable for negligent failure
to warn, but not liable for strict liability failure to warn]; City of
San Diego, supra, 126 Cal.App.4th at pp. 681-684, 686 [jury
found the same property had two different fair market values];
Mizel v. City of Santa Monica (2001) 93 Cal.App.4th 1059, 1071
20
[jury found a dangerous condition on the defendant’s property
caused the plaintiff's injuries, but also found that this condition
did not create a reasonable, foreseeable risk of the kind of injury
the plaintiff suffered].)
“Where the jury’s findings are so inconsistent that they are
incapable of being reconciled and it is impossible to tell how a
material issue is determined, the decision is ‘“against law”’ within
the meaning of Code of Civil Procedure section 657. [Citation.]
‘“The inconsistent verdict rule is based upon the fundamental
proposition that a factfinder may not make inconsistent
determinations of fact based on the same evidence. . . .”
[Citations.] An inconsistent verdict may arise from an
inconsistency between or among answers within a special verdict
[citation] or irreconcilable findings. [Citation.] Where there is an
inconsistency between or among answers within a special verdict,
both or all the questions are equally against the law. [Citation.]
The appellate court is not permitted to choose between
inconsistent answers.’” (Oxford v. Foster Wheeler LLC (2009)
177 Cal.App.4th 700, 716 (Oxford).) The remedy for inconsistent
verdicts is therefore to order a new trial, not to grant a judgment
as a matter of law in favor of one of the parties. (See Stillwell v.
The Salvation Army (2008) 167 Cal.App.4th 360, 374-376
(Stillwell); Missakian v. Amusement Industries, Inc. (2021)
69 Cal.App.5th 630, 654 (Missakian).)
A court properly grants a defendant’s motion for JNOV,
however, when an inconsistent verdict lacks an “essential
foundational predicate” required to impose liability on the
defendant. (Trujillo v. North County Transit Dist. (1998)
63 Cal.App.4th 280, 289 (Trujillo); see McCoy, supra,
180 Cal.App.4th at p. 63; Simgel Co., Inc. v. Jaguar Land Rover
21
North America, LLC (2020) 55 Cal.App.5th 305, 315-316
(Simgel).) As we shall explain, in such circumstances, one verdict
precludes the other as a matter of law because one verdict
contains an essential foundational predicate to liability while the
other verdict relates to damages (as in McCoy and Simgel) or
some other issue arising only after liability has been established
(as in Trujillo). The proper way to remedy such a defective
verdict is to grant the defendant’s motion for JNOV, not to order
a new trial. (See Saxena, supra, 159 Cal.App.4th at pp. 329-330;
see also Code Civ. Proc., § 629.)
4. Analysis
Suffolk argues the jury’s answers to Questions 5, 11, and 12
render the special verdict inconsistent and a limited new trial is
required to resolve the inconsistency because the court is not
permitted to determine that one of the verdicts prevails over the
other.10 According to Suffolk, the jury’s “No” response to
Question 5 (whether Suffolk substantially complied with the
10 Although Suffolk asserts Question 4C is also irreconcilable
with Question 5, it fails to explain how. Suffolk instead
subsumes its argument regarding Question 4C within its analysis
of Questions 11 and 12. Suffolk alludes to “the possibility of
question 4C including retention.” Suffolk does not explain how
the jury included a retention amount in its determination of the
contract balance in Question 4C so that it would be inconsistent
with the jury’s answer to Question 5, which found the District did
not owe any retention amounts. Suffolk has failed to meet its
burden to demonstrate this “possibility.” (See Hearn v. Howard
(2009) 177 Cal.App.4th 1193, 1207 [“When an appellant raises an
issue ‘but fails to support it with reasoned argument and
citations to authority, we treat the point as [forfeited].’”].)
22
contract claim procedures for COP 199.3) meant Suffolk was not
entitled to a time extension and thus liquidated damages were
properly withheld for the delay. By contrast, the jury’s “Yes”
response to Question 11 (did LAUSD wrongfully withhold
retention amounts) and Question 12 (the date and amount
wrongfully withheld from retention amounts) meant Suffolk was
entitled to some extension of time (37 out of the requested
111 days) and thus $111,000 (37 days x $3,000 per day) in
liquidated damages were wrongfully withheld.
We conclude a new trial is not required and the trial court
properly granted JNOV in favor of the District because any
inconsistency in the verdict was legal in nature and was properly
resolved as a matter of law by the trial court. We are persuaded
by McCoy, Trujillo, Markow, and Simgel, which the parties
address extensively.
In McCoy, the jury made a finding that meant the statute
of limitations had run on the plaintiff’s claim. But the jury also
awarded punitive damages to the plaintiff, creating a potential
inconsistency in the special verdict. Because a foundational
predicate for liability (i.e., the timeliness of the plaintiff’s claim)
was lacking, McCoy held the trial court should not have granted
a new trial but instead it should have granted the defendants’
JNOV motion based upon an examination of the legal effect of the
jury’s findings. (See McCoy, supra, 180 Cal.App.4th at p. 86.)
The McCoy plaintiff was a downhill property owner who
sued the current and former owners of an uphill property for oil
contamination to her property under theories of nuisance and
trespass. (See McCoy, supra, 180 Cal.App.4th at p. 64.) In a
special verdict, the jury found the uphill property owners caused
oil contamination to be released to the downhill property but also
23
concluded it was “‘unknown’” whether “‘the unauthorized entry
can be removed, repaired, or abated by reasonable means and at
a reasonable cost.’” (Ibid.) The jury’s finding meant that the
nuisance and trespass were permanent and not continuing. An
action for a permanent nuisance or trespass must be filed within
three years of discovery or the claim is untimely. (See Mangini v.
Aerojet-General Corp. (1996) 12 Cal.4th 1087, 1103 (Mangini II).)
It was undisputed the McCoy plaintiff discovered the oil
contamination more than three years before the lawsuit and her
claim would be timely only if the oil contamination constituted a
continuing, not permanent, nuisance. (See McCoy, at p. 66.)
The special verdict directed the jury to skip the remaining
questions if they answered “‘unknown’” or “‘no’” to the question of
reasonable abatement. (McCoy, supra, 180 Cal.App.4th at p. 81.)
As in this case, over the defendants’ objection, the court directed
the jury to continue its deliberations and to answer subsequent
questions, which in McCoy related to whether the defendants
acted with malice, fraud, or oppression. The jury answered yes
and then awarded punitive damages against the defendants.
(See ibid.) The defendants moved for JNOV and an order
vacating the punitive damage award on the ground the plaintiff’s
claim was time barred. The plaintiff moved for a new trial on all
issues or solely on the issue of compensatory damages,
contending the verdict was inconsistent since the jury found
liability and awarded punitive damages but not compensatory
damages. The court granted the new trial motion and denied the
defendants’ motion for JNOV. (See McCoy, at p. 83.)
The Court of Appeal reversed. It reasoned the jury’s
finding that it was unknown whether the contamination could be
reasonably abated meant, as a matter of law, that the plaintiff
24
had failed to prove its claim the nuisance and trespass were
continuing. Because the plaintiff’s claim was untimely, the trial
court should have granted the defendants’ JNOV motion and
vacated the punitive damages award. (See McCoy, supra,
180 Cal.App.4th at p. 86.)
McCoy rejected the plaintiff’s argument that a new trial
was required. It explained, “the finding that defendants acted
with malice, fraud, or oppression is not inconsistent with the
special verdict on question No. 5. The intentional nature of
defendants’ conduct in trespassing or creating a nuisance is not
relevant under Mangini II to whether the trespass or nuisance is
reasonably abatable or permanent. It was not until the trial
court asked the jury whether to award punitive damages that
apparently inconsistent verdicts were created.” (McCoy, supra,
180 Cal.App.4th at p. 93.)
In Trujillo, the jury found by special verdict that the
defendant employers did not discriminate against or harass the
plaintiff employees. (See Trujillo, supra, 63 Cal.App.4th at
p. 282.) The jury, however, also found the defendants failed to
take all reasonable steps necessary to prevent employment
discrimination and harassment from occurring in violation of
Government Code section 12940, subdivision (i). The jury
awarded compensatory and punitive damages to the plaintiffs
under the statute. The trial court granted JNOV to the
defendants. (See id. at pp. 282-283.) Trujillo affirmed the JNOV,
holding the jury’s special verdict was too inconsistent to be
enforced. Trujillo explained the statutory language did not
permit “recovery on such a private right of action where there has
been a specific factual finding that no such discrimination or
harassment actually occurred at the plaintiffs’ workplace.” (Id.
25
at pp. 288-289.) The JNOV in favor of the employers was
correctly granted because the jury did not find the “essential
foundational predicate” of harassment or discrimination for a
violation of Government Code section 12940. (Trujillo, at p. 289.)
Markow, supra, 3 Cal.App.5th at page 1032, held a
defendant hospital was entitled to JNOV because the jury found
the hospital’s negligence was not a substantial cause of the
plaintiff’s injuries, but the jury also allocated 40 percent fault to
the hospital. Markow held the hospital could be liable for
plaintiff’s injuries only if the defendant doctor, whose negligence
was found to have been a substantial cause of the injuries, was
an agent of the hospital. The evidence showed, as a matter of
law, that the doctor was not an agent of the hospital: the plaintiff
initialed and signed numerous documents over four and one-half
years of treatment that expressly advised him that doctors were
not agents of the hospital. (See id. at p. 1040.) Given the lack of
an essential foundational predicate—ostensible agency—the
Court of Appeal determined the trial court should have granted
JNOV in favor of the hospital rather than order a new trial, as
requested by the plaintiff. (See ibid.)
Finally, in Simgel, the jury found the subject vehicle did
not have a defect with its window mechanism. But, due to a
mistake in the instructions in the special verdict, the jury also
answered other questions regarding whether the plaintiff
suffered damages for the breach of the implied warranty of
merchantability. Despite finding no defect, the jury awarded the
plaintiff damages under that theory. (See Simgel, supra,
55 Cal.App.5th at p. 309.) The appellate court concluded the trial
court properly vacated the judgment in favor of the plaintiff and
entered judgment in favor of the defendant car manufacturer
26
based on the finding there was no defect and the failure of the
court or the parties to recognize that the verdict form should have
instructed the jury to stop deliberating after it found that there
was no defect.11 (See id. at p. 319.)
As in McCoy, Trujillo, Markow, and Simgel, the verdict
here lacked an essential foundational predicate (i.e., Suffolk’s
substantial compliance with the contract claim procedures)
necessary to impose liability on the District for construction
delays.12 The trial court properly granted JNOV to the District
because Question 5 precluded an award of damages in
Questions 11 and 12 for withholding retention amounts. That is
because in Question 5 the jury determined Suffolk did not comply
with the notice and claim procedures, and hence there could be no
damages for wrongful withholding of retention amounts. The
trial court correctly recognized this in its statement of decision:
“[U]nder the terms of the Prime Contract, Suffolk cannot recover
monies for delay or acceleration where it did not comply with the
procedures for a time extension, even if the jury found that
LAUSD delayed the project for 37 days.” The special verdict
recognized the need for a “Yes” response to Question 5 as a
predicate to the remaining questions and further liability. And
the special verdict directed the jury to “stop and have the
presiding juror sign and date the form” if it answered “no” to
11 The court additionally concluded that JNOV was properly
granted to the defendant because there was insufficient evidence
of a defect.
12 We address in the next section Suffolk’s argument that the
doctrine of substantial performance in construction law applies
only to the prime contract and not to individual provisions
therein.
27
Question 5. The jury did so and only reached subsequent
questions on damages (Questions 11 to 14) after the court
directed it to continue deliberations, as in McCoy.
During the ensuing posttrial motions, the trial court
correctly determined that, as a matter of law, Suffolk could not
recover liquidated damages absent substantial compliance with
the claim procedures in the prime contract. This is similar to
Trujillo, supra, 63 Cal.App.4th at pages 288-289, where the
appellate court determined the jury’s finding that no
discrimination or harassment occurred precluded compensatory
and punitive damages on the statutory violation for failure to
prevent discrimination and harassment. Likewise, the plaintiff’s
failure to timely file her complaint in McCoy precluded punitive
damages, just as the lack of ostensible agency in Markow
precluded any allocation of fault. And in Simgel, the lack of a
defect precluded damages for breach of the implied warranty of
merchantability. In this case, as in McCoy, Trujillo, Markow,
and Simgel, the trial court did not “choose” between inconsistent
answers in the jury’s special verdict. Rather, the special verdict’s
factual findings established the District could not, as a matter of
law, be liable for the delay to the project and thus Suffolk could
not recover the damages the jury awarded in Questions 11
and 12. As stated, the trial court merely determined the legal
effect of the jury’s findings and directed judgment in favor of the
District on damages.
We are not persuaded by Suffolk’s argument that a new
trial was required because the trial court lacked authority to
choose one verdict over another. As stated, the trial court here
did not choose one verdict over another; it instead was bound as a
matter of law by the jury’s finding that Suffolk failed to
28
substantially comply with the contract claim procedures in
COP 199.3, which precluded the District from being found liable
and having to pay damages for the 141-day delay.
Suffolk cites several cases in support of its argument, but
these are distinguishable. First, in Missakian, supra,
69 Cal.App.5th at page 637, the jury made inconsistent findings
despite undisputed evidence on the issue. There, the defendant
was the founder of a company who promised the plaintiff that he
would receive a bonus and share in the proceeds of litigation if he
came to work for the company as general counsel. The plaintiff
sued the founder and the company for promissory fraud.
Although the case was tried on the theory the founder, and only
the founder, spoke for the company, the jury reached inconsistent
verdicts when it found the company liable for promissory fraud
but not the founder. (Ibid.) The jury awarded compensatory and
punitive damages based on the company’s fraud. (Ibid.) The
trial court granted JNOV in favor of the company, reasoning that
the company could not be found liable for fraud if the jury
determined the founder did not make any fraudulent promises.
(See id. at p. 642.)
The Court of Appeal in Missakian concluded the special
verdict was inconsistent and there was no way to resolve the
inconsistency because the plaintiff “framed the case solely on [the
founder’s] promises and never argued to the jury that [the
company] made any misrepresentation through anyone other
than [the founder].” Although there was evidence of other
employees making promises to the plaintiff, that evidence did not
undercut the pleadings, trial briefs, opening statements, jury
instructions, or closing arguments. (Missakian, supra,
69 Cal.App.5th at p. 659.) The appellate court rejected the
29
company’s argument that the JNOV should be affirmed. It held
the trial court could not credit one finding (that the founder did
not make false promises) over another (that the company did
make false promises) when the entire theory of the case was that
the founder’s promises were the company’s promises. Given
these circumstances, a new trial was warranted and JNOV was
improperly granted. (See id. at p. 662.)
This case is unlike Missakian because there the jury was
presented with a single, undisputed theory of the case from which
it deviated and created an inconsistent verdict. Here, there was
no similar single, undisputed theory of the case. In this case, the
jury made a factual finding based on disputed evidence: whether
Suffolk substantially complied with the claim procedure
requirements in COP 199.3. Because the jury determined the
answer to this was “no” in Question 5, Suffolk was not entitled to
the delay damages the jury purported to award in Questions 11
and 12. Further, here the ostensible inconsistency in the verdict
resulted from the McCoy-like direction to continue deliberating
despite the special verdict’s instruction to stop if the answer to
Question 5 was “No.”
Suffolk also relies on Oxford, supra, 177 Cal.App.4th at
pages 716 to 722, and Stillwell, supra, 167 Cal.App.4th at
pages 373 to 375 to argue the trial court may not “credit the
answer to question 5 and cast aside the answer to question 11.”
Oxford is distinguishable because the jury there rendered
inconsistent verdicts on separate but related causes of action—
negligent versus strict liability failure to warn. (See Oxford, at
p. 721; see also Trejo, supra, 13 Cal.App.5th at p. 123 [same].)
Such competing theories of liability did not allow the court to
decide liability as a matter of law. By contrast here, Questions 5,
30
10, and 11 did not involve different irreconcilable theories of
liability; instead, they involved a finding precluding liability but
a finding awarding damages. The court correctly determined
that as a matter of law the former precluded the latter.
Stillwell, supra, 167 Cal.App.4th at pages 373 to 375 is also
distinguishable because the jury there found the plaintiff both
was and was not an at-will employee. The jury returned a special
verdict that determined there was an effective agreement for at-
will employment but also that the employer breached the
employer’s promise to discharge the employee only for good
cause. (See id. at p. 363.) On appeal, the parties conceded the
verdicts were inconsistent and the court remanded the matter for
a new trial. (See also Shaw v. Hughes Aircraft Co. (2000)
83 Cal.App.4th 1336, 1344-1346 [same].) Here, the jury did not
find that Suffolk both did and did not substantially comply with
the contract claim procedures. Further, Oxford and Stillwell are
distinguishable because the inconsistent verdicts in those cases
did not allow the trial court to draw from them conclusions of
law, as the trial court properly did in this case.
Lastly, Suffolk relies on Roby v. McKesson Corp. (2009)
47 Cal.4th 686 to argue “that when a special verdict is internally
inconsistent, the inconsistency cannot be explained away on the
theory that it’s really of a ‘legal’ nature and something the trial
court can iron out post-verdict by accepting one finding and
tossing out another.” Roby is inapposite. Roby stands for the
proposition that “‘[d]ouble or duplicative recovery for the same
items of damage amounts to overcompensation and is therefore
prohibited.’” (Id. at p. 702.) There, the jury found the plaintiff
suffered economic and noneconomic damages for three different
causes of action. The court determined the noneconomic damages
31
were “‘hopelessly ambiguous’” because it was “impossible to
determine to a reasonable degree of certainty” whether and if the
three noneconomic damages figures overlapped. Roby did not
hold a new trial was required in every instance in which a jury
reached an inconsistent verdict. (Id. at pp. 703, 705.)
B. The Trial Court Properly Included Question 5 in the Special
Verdict Form and Instructed the Jury With Instruction
No. 39
The jury determined in Question 5 that Suffolk did not
substantially comply with the prime contract’s notice and claim
procedures when it submitted COP 199.3. Suffolk argues it was
deprived of a fair trial on delay damages because Question 5 and
accompanying Jury Instruction No. 39 were legally incorrect and
duplicative of other special verdict questions and jury
instructions.13 According to Suffolk, Question 5 and Jury
Instruction No. 39 were “legally problematic” because the
doctrine of substantial performance in construction law applies
only to the contract as a whole, not to individual provisions
contained in the contract. In Suffolk’s view, that means the
prime contract’s notice and claim provisions were not conditions
precedent (which barred Suffolk from recovering any delay
damages if it failed to substantially comply) but were, instead,
mere covenants (which reduced Suffolk’s recovery if it did not
comply with them). We conclude Suffolk’s argument lacks merit.
13 Jury Instruction No. 39 instructed the jury that Suffolk
must prove it made a good faith effort to comply with the contract
and time extension procedures and that it “substantially achieved
the purpose of the claims procedure” to ensure the District had
notice and opportunity to review the issues raised in COP 199.3.
32
1. Standard of Review
A special verdict form must allow the jury to resolve every
controverted issue (see Saxena, supra, 159 Cal.App.4th at p. 325),
and we consider de novo the correctness of a special verdict (see
City of San Diego, supra, 126 Cal.App.4th at p. 678). Jury
instructions must be supported by the pleadings and evidence
developed in the specific case (see LeMons v. Regents of
University of California (1978) 21 Cal.3d 869, 875 (LeMons)), and
we also apply a de novo standard to decide whether a jury
instruction was properly given (see D.Z. v. Los Angeles Unified
School Dist. (2019) 35 Cal.App.5th 210, 232).
2. Suffolk’s Substantial Performance of the Prime
Contract Does Not Eliminate Its Duty To
Substantially Comply With the Contract’s Conditions
Precedent Relating to Claim Procedures
a. Background law
Three statutory provisions authorize the notice and claims
procedures in the prime contract. Civil Code section 1511
authorizes parties to a contract to require written notice of an
intention to claim an extension of time “within a reasonable time
after the occurrence of the event excusing performance . . .
provided the requirement of such notice is reasonable and just.”
(Civ. Code, § 1511, subd. (1).) Government Code sections 930.2
and 930.4 also authorize local public entities, such as the District,
to include a claims procedure in a contract that “exclusively
governs the claims to which it relates.” (Gov. Code, §§ 930.2,
930.4; see Arntz Builders v. City of Berkeley (2008)
166 Cal.App.4th 276, 290.)
33
The Court of Appeal in Greg Opinski Construction, Inc. v.
City of Oakdale (2011) 199 Cal.App.4th 1107, 1110 (Opinski) held
that the doctrine of substantial performance14 does not override
any contractual requirement to comply with a statutorily
authorized claim procedure. In Opinsky, the contractor
completed a project seven months late and failed to seek an
extension from its municipal client. The contract authorized
written requests for extensions of time if the delay was caused by
forces “‘beyond the control of the Contractor,’” including “‘acts of
neglect by Owner.’” (Id. at p. 1112.) At trial, the contractor was
found liable for liquidated damages. He argued on appeal that
such damages were precluded for “any portion of the delay that”
the city had caused. (Id. at p. 1115.)
Opinski rejected that argument and held that because the
contractor failed to comply with the contractual time-extension
provision, it made “no difference whether [the contractor’s] timely
performance was possible or impossible.” (Opinski, supra,
199 Cal.App.4th at p. 1118.) It reasoned that the purpose of such
contractual provisions authorized by Civil Code section 1511 “is
to allocate to the contractor the risk of delay costs—even for
14 The California Supreme Court set out the doctrine of
substantial performance in a construction case in Thomas
Haverty Co. v. Jones (1921) 185 Cal. 285. There, the high court
explained that a contractor was previously held to a standard of
“strict performance” before he or she could be paid. Under the
doctrine of substantial performance, by contrast, “the contractor
may, in an action upon the contract, recover the amount unpaid
of his contract price, less the amount allowed as damages for the
failure in strict performance.” (Id. at p. 289; accord, Murray’s
Iron Works, Inc. v. Boyce (2008) 158 Cal.App.4th 1279, 1291-
1292.)
34
delays beyond the contractor’s control—unless the contractor
follows the required procedures for notifying the owner of its
intent to claim a right to an extension.” (Ibid.)
b. Analysis
We conclude Question 5 and Jury Instruction No. 39 were
properly presented to the jury because they related to a
controverted issue raised by the pleadings and the evidence. As
we shall explain, they also accurately reflected California law on
conditions precedent and substantial compliance.
First, Suffolk’s complaint alleged the District breached the
prime contract by “failing to provide compensation for delays that
the District acknowledged are recoverable under the Prime
Contract, including those addressed in Plaintiff’s Government
Code claim dated December 27, 2013, failing to process and pay
change order requests and claims as required under the Prime
Contract, and failing and refusing to pay all sums due under the
Prime Contract.” In its opening statement, Suffolk’s counsel told
the jury that notice would be an issue at trial: “You’re also going
to hear that the contract requires that notice be given and claim
procedures be followed.”
At trial, the District presented testimony regarding why it
rejected COP 199.3 and required Suffolk to submit specific
information, such as schedule fragnets, to determine whether an
extension or additional payment was appropriate. The trial court
stated, “[a]n issue at trial was whether Suffolk was required to
show compliance with Article 12 and Sections 3.06 and 3.07 of the
Prime Contract related to the submission of the claim for
additional amounts . . . for acceleration and delay costs.” The
record thus demonstrates substantial compliance with the
35
contract claim procedure in the prime contract was a
controverted issue to be decided by the jury and that issue was
supported by the pleadings and evidence in the case. (See
LeMons, supra, 21 Cal.3d at p. 875; Saxena, supra,
159 Cal.App.4th at p. 325; City of San Diego, supra,
126 Cal.App.4th at p. 678.)
Next, Question 5 and Jury Instruction No. 39 also
comported with California law on conditions precedent. “A
condition precedent is one which is to be performed before some
right dependent thereon accrues, or some act dependent thereon
is performed.” (Civ. Code, § 1436.) Provisions “‘are not to be
construed as conditions precedent unless such construction is
required by clear, unambiguous language; and particularly so
where a forfeiture would be involved or inequitable consequences
would result. [Citations.]’ [Citations.] Because ‘such conditions
are not favored by the law, [they] are to be strictly construed
against one seeking to avail [it]self of them.’” (JMR Construction
Corp. v. Environmental Assessment & Remediation Management,
Inc. (2015) 243 Cal.App.4th 571, 594.)15
15 By contrast, “[a] covenant is a promise to render some
performance.” (1 Witkin, Summary of Cal. Law (11th ed. 2024)
Contracts, § 801.) “The unjustified failure to perform a material
promise or covenant, where the contract is entire, is a breach.”
(Id. at § 874; see Los Angeles Gas & Electric Co. v. Amalgamated
Oil Co. (1909) 156 Cal. 776, 781; see also Woodard v. Glenwood
Lumber Co. (1915) 171 Cal. 513, 522.) The breach of a covenant
gives the other party a right of action for damages. (See Witkin,
at § 874.) “One of the distinctive features of a covenant which
distinguishes it from a condition precedent is that, when it goes
only to a part of the consideration, nonperformance is not a
defense if the breach of the covenant may be paid for in
36
Here, the prime contract required Suffolk to follow specific
procedures, in Article 12 and sections 3.06 and 3.07, to provide
notice to the District and to request an extension of the
construction deadline. Articles 12.4 and 12.5 required Suffolk to
report any issues that could result in delay within three working
days of the beginning and the end of that occurrence. Article 12.6
provided, “Should CONTRACTOR fail or refuse to submit a
Change Order Proposal as required by this Article 12.6 and/or
fail or refuse to comply with the notice and other requirements of
this Article 12, CONTRACTOR is not entitled to any adjustment
in the Contract Amount, Milestones, and/or Contract Time.” The
language of Article 12.6 is clear and unambiguous: adjustments
to the contract timeline are conditioned on the submission of a
COP and compliance with the other notice requirements in
Article 12.
Given this clear and unambiguous language, Article 12 and
its related provisions constitute a condition precedent to Suffolk’s
right to payment for extensions to the contractual deadline.
Here, Suffolk failed to fulfill a condition that was within its
power to perform, and its right to payment of the withheld
retention amounts therefore did not accrue. “A contrary
conclusion would undermine the law of contracts by vesting in
[Suffolk] the power to unilaterally convert the [District’s]
conditional obligation [to adjust the contract time] into an
independent, unconditional obligation notwithstanding the terms
damages.” (B.F. Schlesinger & Sons v. Kohler & Chase (1930)
103 Cal.App. 195, 199-200 (B.F. Schlesinger).)
37
of the [prime contract].” (Platt Pacific, Inc. v. Andelson (1993)
6 Cal.4th 307, 314.)16
Third, Suffolk’s argument that in construction cases
substantial performance of the contract excuses noncompliance
with specific contractual provisions is unpersuasive. The cases
Suffolk cites, Thomas Haverty Co. v. Jones (1921) 185 Cal. 285,
Murray’s Iron Works, Inc. v. Boyce (2008) 158 Cal.App.4th 1279,
and Kossler v. Palm Springs Developments, Ltd. (1980)
101 Cal.App.3d 88, do not abrogate the well-established rule that
a party must satisfy a condition precedent before “some right
dependent thereon accrues, or some act dependent thereon is
16 Suffolk relies on several cases for the proposition that
conditions precedent are disfavored and a contract will be strictly
construed against the party claiming a condition precedent. But
none of those cases contains a clear and unambiguous condition
precedent such as the one here. (See Colaco v. Cavotec SA (2018)
25 Cal.App.5th 1172, 1185 [“Nothing in the APA or the
Guidelines conditioned Cavotec’s obligation to make the second
Performance Earn-out Payment on Inet timely and properly
forwarding to Cavotec all postclosing customer payments.”];
Helzel v. Superior Court (1981) 123 Cal.App.3d 652, 663
[interpreting ambiguous contract to contain a covenant rather
than a condition precedent]; Yamanishi v. Bleily & Collishaw,
Inc. (1972) 29 Cal.App.3d 457, 463 [ambiguous contractual
provision did not create a condition precedent].)
Suffolk also argues, “Courts traditionally have construed
the kinds of notice provisions in the contract here as covenants,
not conditions precedent,” citing Milovich v. City of Los Angeles
(1941) 42 Cal.App.2d 364, 373-374 and B.F. Schlesinger, supra,
103 Cal.App. at pages 199 to 200. Again, neither case contained
the type of clear and certain provisions that are in the prime
contract.
38
performed.” (Civ. Code, § 1436.) None of these cases addressed,
much less held, that substantial performance of a contract
eliminates the requirement to satisfy a condition precedent in
that contract.
Further, even if the claim procedures in Article 12 were not
conditions precedent, Question 5 and Jury Instruction No. 39 still
comport with the law because, as the trial court correctly stated,
this case is “squarely within Opinski.” As in Opinski, the project
here was completed but delayed by many months and some part
of the delay was attributable to the owner. The prime contract
contains similar requirements for written time extension
requests as the contract in Opinski. The time extension provision
contained in Article 12 and sections 3.06 and 3.07 also similarly
allocated to the contractor the risk of delay costs unless the
contractor followed the claim procedure outlined in the contract.
And the claim procedure in the prime contract was statutorily
authorized under Civil Code section 1511 and Government Code
sections 930.2 and 930.4. Although the project in Opinski was
completed, meaning the contractor substantially performed on
the contract as a whole, the appellate court nevertheless held the
contractor to its promise to comply with the claim procedure
before it could recover any liquidated damages for the delay. (See
Opinski, supra, 199 Cal.App.4th at p. 1118.) The same result is
required here.
Finally, we reject Suffolk’s arguments that Question 5 and
Jury Instruction No. 39 were duplicative of Questions 1 to 4 and
Jury Instructions Nos. 18 and 30. According to Suffolk, by
finding for Suffolk on Questions 1 through 4, the jury necessarily
found Suffolk did “substantially all” of what was required under
the prime contract, which necessarily included Article 12 and
39
sections 3.06 and 3.07. Jury Instruction No. 18 required the jury
to find Suffolk “did all, or substantially all, of the significant
things that the contract required it to do” to recover damages for
its breach of contract claim. Additionally, Jury Instruction
No. 30 required the jury to find that Suffolk made a good faith
effort to comply with the prime contract and that the “District
received what the contract called for because Suffolk’s failures, if
any, were so trivial or unimportant that they could have been
easily fixed or paid for.” Given these special verdict questions
and jury instructions, Suffolk asserts Question 5 and Jury
Instruction No. 39 were unnecessary. Because they addressed
materially different issues, Question 5 and Jury Instruction
No. 39 were not duplicative of Questions 1 to 4 and Jury
Instructions Nos. 18 and 30. As stated, substantial performance
of the prime contract did not excuse Suffolk’s failure to comply
with the specific notice and claim procedures within it.
C. Suffolk Is Not Entitled To Recover Attorney Fees as
Contractual Damages17
Suffolk argues the trial court erred by ruling it was not
entitled, as a matter of law, to recover “as contract damages” its
17 The District contends Suffolk did not timely identify this
issue pursuant to California Rules of Court, rule 8.130(a)(2) and
we should not consider the issue. Rule 8.130(a)(2) provides: “If
the appellant designates less than all the testimony, the notice
must state the points to be raised on appeal; the appeal is then
limited to those points unless, on motion, the reviewing court
permits otherwise.” On November 18, 2021, Suffolk filed a notice
designating the record that included less than all the testimony,
which listed three points on appeal. These identified issues did
40
attorney fees incurred in defending against the subcontractor
actions.18 We review this legal determination de novo. (See
Looney v. Superior Court (1993) 16 Cal.App.4th 521, 531.)
1. Additional Proceedings
As stated, subcontractors QPS and Best, among others,
filed suit against Suffolk for extra work they did on the project.
The contracts between Suffolk and its subcontractors contained
attorney fee provisions. Additionally, Suffolk was required by
statute to obtain a payment bond that included an attorney fee
provision. (See Civ. Code, §§ 9554, subd. (b) [“The payment bond
shall provide that if the direct contractor or a subcontractor fails
to pay [listed categories], the surety will pay the obligation and, if
an action is brought to enforce the liability on the bond, a
reasonable attorney’s fee, to be fixed by the court[.]”]; 9564,
subd. (c) [“In an action to enforce the liability on the bond, the
court shall award the prevailing party a reasonable attorney’s
fee.”].)
The subcontractors settled their claims against Suffolk.
Pursuant to the settlements, Suffolk agreed to pay guaranteed
not include attorney fees as damages. On February 4, 2022,
Suffolk filed a second record designation notice that added this
issue. The District filed its respondent’s brief on July 26, 2023,
over one year after it received notice of all the points to be raised.
Accordingly, we address the issue. (See Cox v. Griffin (2019)
34 Cal.App.5th 440, 448 [rejecting respondent’s rule 8.130(a)(2)
forfeiture argument].)
18 Suffolk abandoned two claims it raised below:
(1) entitlement to attorney fees paid to the subcontractors, and
(2) entitlement to attorney fees incurred in defense against the
subcontractor actions under a theory of implied indemnity.
41
amounts to the subcontractors and litigate their claims in a pass-
through action against the District. In the second phase of trial,
the jury awarded amounts to Suffolk for extra work done by the
subcontractors as part of the pass-through action (Questions 4A
and 4B).
In the third phase of trial (tried to the court), Suffolk
sought as contract damages the attorney fees it paid to defend
itself against the actions brought by the subcontractors, as well
as the fees it paid to them pursuant to the contractual and
statutory fee provisions. Suffolk’s theory was that the fees were
an item of damages recoverable on its successful breach of
contract claim against the District and that it was entitled to
recover those fees under implied contractual indemnity. The
court ordered the parties, as part of a bifurcated bench trial, to
brief the issue of Suffolk’s entitlement to fees and whether
Suffolk could make a prima facie case for damages. Although the
court ultimately found Suffolk had made a prima facie showing
that it incurred fees to defend against the subcontractor actions,
the court determined Suffolk could not recover those fees under a
breach of contract theory against the District. The court
determined there was no persuasive authority to deviate from
Code of Civil Procedure section 1021 (section 1021), which
provides that each party is to pay its own attorney fees unless fee
shifting is authorized by statute or agreement.
2. Background Law
“California follows what is commonly referred to as the
American rule, which provides that each party to a lawsuit must
ordinarily pay his own attorney fees.” (Trope v. Katz (1995)
11 Cal.4th 274, 278 (Trope).) The American rule is codified in
42
section 1021: “Except as attorney’s fees are specifically provided
for by statute, the measure and mode of compensation of
attorneys and counselors at law is left to the agreement, express
or implied, of the parties; but parties to actions or proceedings
are entitled to their costs, as hereinafter provided.” “[T]here is a
sharp demarcation in the law between damages and costs
incurred in bringing suit, including attorney fees.” (Chan v.
Curran (2015) 237 Cal.App.4th 601, 624.)
In 1963, the Supreme Court in Prentice v. North American
Title Guaranty Corp. (1963) 59 Cal.2d 618, 620 (Prentice)
identified an exception to the American rule in section 1021: “A
person who through the tort of another has been required to act
in the protection of his interests by bringing or defending an
action against a third person is entitled to recover compensation
for the reasonably necessary loss of time, attorney’s fees, and
other expenditures thereby suffered or incurred.” (Prentice, at
p. 620.) Prentice has generally been limited to tort cases. (See,
e.g., Brandt v. Superior Court (1985) 37 Cal.3d 813, 815 [insured
alleging tort claims against insurer could recover attorney fees
reasonably necessary to collect the benefits due under the policy];
Vanguard Recording Society, Inc. v. Fantasy Records, Inc. (1972)
24 Cal.App.3d 410, 413-414, 419 [when record company
interfered with exclusive recording contract by releasing bootleg
recording, the artist and her record company could recover
attorney fees incurred in bringing injunctions to prevent the
distribution and sale of bootleg record].)
In 1978, the Supreme Court stated, in a products liability
case, that “the Prentice exception was not meant to apply in every
case in which one party’s wrongdoing causes another to be
involved in litigation with a third party. If applied so broadly,
43
the judicial exception would eventually swallow the legislative
rule that each party must pay for its own attorney. [Citation.]
To avoid this result, Prentice limits its authorization of fee
shifting to cases involving ‘exceptional circumstances.’” (Davis v.
Air Technical Industries, Inc. (1978) 22 Cal.3d 1, 7 (Davis)
[disallowing attorney fees].)
3. Analysis19
At the outset, we note that Suffolk does not seek to recover
fees it incurred in the subcontractor actions based on the prime
contract, which has no attorney fees provision and no contractual
indemnity provision. Instead, Suffolk argues the attorney fees it
incurred by defending against the subcontractor actions were the
foreseeable and natural consequence of the District’s breach of
contract. As such, according to Suffolk, these attorney fees were
recoverable as damages under Prentice and its progeny. Suffolk’s
argument lacks merit.
First, Suffolk cites no California Court of Appeal case
extending Prentice to a contract action, and we decline to do so.
It remains the law in California that each party to a lawsuit must
ordinarily pay its own attorney fees, except as specifically
provided for by statute or contract. (See Trope, supra, 11 Cal.4th
at p. 278; see also § 1021.) To extend Prentice to contract cases
would allow the exception to swallow the rule. (See Davis, supra,
22 Cal.3d at p. 7.) Indeed, the Supreme Court cautioned that
Prentice’s exception to the American Rule that each side pays its
19 Because we conclude Suffolk is not entitled to attorney fees
as a matter of law, we need not address the District’s claim that
the prime contract bars Suffolk’s claim for attorney fees as
contractual damages.
44
own attorney fees was limited to “cases involving ‘exceptional
circumstances.’” (Davis, at p. 7; see Howard v. Schaniel (1980)
113 Cal.App.3d 256, 267 [“the Davis case has been read, and we
think properly, to have confined Prentice to its own facts”];
Harbor City Discount Auto Center, Inc. v. Firestone Tire & Rubber
Co. (1979) 95 Cal.App.3d 886, 891 [Davis reaffirmed “the rule
that, absent ‘exceptional circumstances,’ section 1021 means just
what it says and litigants are liable for their own attorney’s
fees”].) A dispute between two sophisticated parties operating
under a complex, negotiated prime contract does not present the
exceptional circumstances justifying a departure from the
American Rule envisioned by Prentice.
Suffolk’s cases, De La Hoya v. Slim’s Gun Shop (1978)
80 Cal.App.3d Supp. 6, 10 (De La Hoya), Copenbarger v. Morris
Cerullo World Evangelism, Inc. (2018) 29 Cal.App.5th 1, 11
(Copenbarger), Monster, LLC v. Superior Court (2017)
12 Cal.App.5th 1214, 1228 (Monster) and Mai v. HKT Cal, Inc.
(2021) 66 Cal.App.5th 504, 512 (Mai) are inapposite.20
De La Hoya, a case from the appellate division of the
superior court, stated there was “no reason” not to extend
Prentice to a breach of contract claim because other jurisdictions
had adopted the rule “that attorney fees incurred in litigation
with third parties may be recoverable as damages in an action for
breach of contract.” (De La Hoya, supra, 80 Cal.App.3d Supp. at
p. 10.) In De La Hoya, the innocent buyer of a stolen handgun
20 Suffolk asserts that other jurisdictions “have awarded
damages in various breach scenarios involving third party
litigation.” But “[w]e of course are not bound by rulings
of . . . [the] courts of other jurisdictions.” (Robertson v. Saadat
(2020) 48 Cal.App.5th 630, 649.)
45
sought to recover attorney fees he incurred to defend against an
arrest for receiving stolen property. (See id. at p. 8.) De La Hoya
reasoned it was reasonably foreseeable the buyer would be
arrested if his possession of the gun was questioned and the gun
turned out to be stolen. The buyer would then incur attorney fees
as “a natural and usual consequence” of the arrest. (Id. at p. 11.)
De La Hoya is neither persuasive nor binding. De La Hoya
preceded Davis’s limitation of Prentice and, as noted, it is from
the appellate division of the superior court. (See Velasquez v.
Superior Court (2014) 227 Cal.App.4th 1471, 1477, fn. 7
[“Appellate division decisions . . . are of debatable strength as
precedents and are not binding on higher reviewing courts.”].)
No published California Court of Appeal decision has followed
De La Hoya. Further, it is distinguishable because it did not
involve a contract negotiated between two sophisticated parties
involving potentially millions of dollars.
Next, Copenbarger, Monster, and Mai are unpersuasive.
None holds that attorney fees may be recovered as damages in a
contract action. Copenbarger stated in dicta that, “Although it
appears to us attorney fees may be recovered as damages for
breach of contract, we do not need to decide the issue.”
(Copenbarger, supra, 29 Cal.App.5th at p. 11.) Monster involved
contracts that contained attorney fees provisions in case of
breach. It did not hold that attorney fees were recoverable as
contract damages absent a contractual fee provision. (See
Monster, supra, 12 Cal.App.5th at p. 1227, fn. 4.) And Mai was
not a contract case at all. It fell squarely into Prentice’s “‘tort of
another’” theory of attorney fees as damages. (See Mai, supra,
66 Cal.App.5th at p. 512.) In short, Suffolk’s argument has no
support in law, and the trial court did not err by rejecting it.
46
D. The District’s Cross-appeal
The District raises three issues in its cross-appeal relating
to attorney fees and costs, and prejudgment interest. First,
although it acknowledges Suffolk achieved a “minor win” under
Public Contract Code section 7107, the District challenges the
trial court’s determination that Suffolk, rather than the District,
was the prevailing party.21 Next, the District challenges the trial
court’s denial of its request for attorney fees under Civil Code
section 9564 as the prevailing party in the third phase of trial.
Third, it challenges the award of prejudgment interest to Suffolk
for certain payments the District made before the jury rendered
its verdict. We conclude only the third argument has merit.
1. The Trial Court Did Not Abuse Its Discretion by
Concluding Suffolk Was the Prevailing Party Under
Public Contract Code Section 7107
a. Standard of review
De novo review applies to a trial court’s application and
interpretation of the statutory criteria for an award of attorney
fees. (See Connerly v. State Personnel Bd. (2006) 37 Cal.4th
1169, 1175; Yassin v. Solis (2010) 184 Cal.App.4th 524, 530-531.)
“‘We independently review any legal issue regarding the
appropriate criteria for a fee award. But once those criteria are
identified, we defer to the trial court’s discretion in determining
how they are to be exercised. [Citation.] . . . [T]he trial court is
21 While the District challenges how the court determined
which party was entitled to fees and costs, it does not challenge
the court’s calculation of those fees and costs.
47
in the best position to determine whether the criteria for a fee
award have been met. We will not disturb its judgment on this
issue unless we are convinced the court abused its discretion.
[Citation.] A trial court abuses its discretion only where its
action is clearly wrong and without reasonable basis.’” (Powell v.
Tagami (2018) 26 Cal.App.5th 219, 236-237; accord, Jones v.
Goodman (2020) 57 Cal.App.5th 521, 532-533.) “In reviewing the
trial court’s determination of whether a party prevailed in the
litigation, we apply the deferential abuse of discretion standard
of review.” (James L. Harris Painting & Decorating, Inc. v. West
Bay Builders, Inc. (2015) 239 Cal.App.4th 1214, 1221 (Harris).)
In short, while we review for an abuse of discretion the trial
court’s determination of entitlement to and amount of an
attorney fees award, we review de novo the legal question of the
interpretation of who is the “prevailing party” under
section 7107. (Graciano v. Robinson Ford Sales, Inc. (2006)
144 Cal.App.4th 140, 149 (Graciano).)
b. The trial court considered the proper legal
criteria
The District argues the trial court erred when it
determined Suffolk was the prevailing party under section 7107.
According to the District, section 7107 applies only to the
prevailing party in a cause of action for wrongful withholding of
retention proceeds in public contracts, and the trial court should
only have considered which party prevailed on that issue. The
District contends the trial court improperly considered the
parties’ relative success in the entire litigation.
As stated, retention amounts are amounts an owner may
withhold from its progress payments to a contractor as a hedge
48
against the contractor’s nonperformance and as an incentive for
completion. (See United Riggers, supra, 4 Cal.5th at p. 1087.)
Section 7107 is one of a series of “prompt payment” statutes that
require owners and general contractors to pay their contractors
and subcontractors within specified time periods or suffer
monetary penalties for violations. (FEI Enterprises, Inc. v. Yoon
(2011) 194 Cal.App.4th 790, 795.)
Section 7107 applies to contracts “relating to the
construction of any public work of improvement.” (Pub. Contract
Code, § 7107, subd. (a).) Subdivisions (b) through (e) of
section 7107 specify when and how retention amounts withheld
from the contractor must be released. As relevant here,
subdivision (c) authorizes the withholding of retention amounts
“[i]n the event of a dispute between the public entity and the
original contractor.” Section 7107, subdivision (f), states: “In the
event that retention payments are not made within the time
periods required by this section, the public entity or original
contractor withholding the unpaid amounts shall be subject to a
charge of 2 percent per month on the improperly withheld
amount, in lieu of any interest otherwise due. Additionally, in
any action for the collection of funds wrongfully withheld, the
prevailing party shall be entitled to attorney’s fees and costs.”
Harris, supra, 239 Cal.App.4th at page 1216, applied
section 7107 to determine which party in a construction breach of
contract case was the prevailing party entitled to attorney fees.
There, a jury found neither the subcontractor nor the contractor
had performed on the contract and thus it did not award damages
to either party. The trial court denied the parties’ cross-motions
for attorney fees under section 7107, finding there was no
prevailing party in the case. (See id. at p. 1217.) The contractor
49
appealed, arguing the trial court lacked discretion to deny
attorney fees under a fee shifting statute such as section 7107. It
argued the subcontractor sought prompt payment under
section 7107 in its lawsuit and because the jury found in favor of
the contractor on this issue, it was the prevailing party under
that statute. (See ibid.)
Harris rejected that argument and affirmed the trial court.
The appellate court reasoned that, “‘[t]he determination of
whether there is prevailing party is to be made “on a practical
level” after considering what each party accomplished via the
litigation.’ [Citation.] This means that ‘“[t]he prevailing party
determination is to be made only upon a final resolution of the
contract claims and only by ‘a comparison of the extent to which
each party ha[s] succeeded and failed to succeed in its
contentions.’”’” (Harris, supra, 239 Cal.App.4th at p. 1221.)
Harris explained the contractor’s “success on the prompt
payment statute claim did not render [it] victorious because the
prompt payment statute claim was encompassed within [the
subcontractor’s] breach of contract action. The prompt payment
statute violations were included within the complaint’s breach of
contract cause of action. Contrary to [the contractor’s]
characterization of the complaint, there was no separate cause of
action for the prompt payment statute violations. Thus, the
breach of contract and prompt payment violations were so
intertwined that the trial court’s statement about neither party
prevailing on the contract encompasses the whole of the
litigation. Accordingly, we conclude the trial court appropriately
looked at the litigation as a whole to determine there was no
prevailing party for purposes of attorney fees.” (Harris, supra,
239 Cal.App.4th at pp. 1222-1223; see Brawley v. J.C. Interiors,
50
Inc. (2008) 161 Cal.App.4th 1126 [similar as to private sector
construction contracts under former Civil Code section 3260 (now
section 8800)].)
Here, the District makes the same argument the Court of
Appeal rejected in Harris. The District asserts it is the
prevailing party on the sole issue relevant to section 7107—
prompt payment of retention proceeds—and therefore it is
entitled to attorney fees under that statutory provision.
According to the District, it successfully defended against
Suffolk’s claim the District wrongfully withheld $423,000 in
retention proceeds as liquidated damages. The District relies on
the jury’s answer to Question 5 to argue the jury found “Suffolk
was not entitled to a time extension, meaning the District legally
assessed liquidated damages and was entitled to keep [these
damages], as reflected in the trial court’s grant of JNOV.” The
District argues it was thus error for the trial court to determine
the prevailing party based on the entire jury verdict and award of
$856,429 in damages to Suffolk for the District’s breach of
contract.
We conclude, based on the plain language of section 7107
and Harris, that the trial court applied the correct legal criteria
in finding Suffolk was the prevailing party. As in Harris, there is
no separately pleaded cause of action for a violation of
section 7107; the claim for retention proceeds is intertwined with
Suffolk’s contract claim for failure to pay delay payments, change
order payments, and all other sums due.
The breach of contract cause of action in Suffolk’s
complaint alleged: “The District breached the Prime Contract by,
among other ways, failing to provide compensation for
delays . . . , failing to process and pay change order requests and
51
claims . . . , and failing and refusing to pay all sums due under
the Prime Contract. [¶] Pursuant to the Prime Contract and
California law, the District was required to timely make progress
payments and release retention amounts to Plaintiff for labor,
materials, equipment, and services provided by Plaintiff under
the Prime Contract. To the extent the District failed to promptly
pay such progress payments and/or release such retention
amounts to Plaintiff as required by the applicable California
prompt payment statutes, including but not limited to Public
Contract Code sections 10261 et seq. and 7107 et seq., Plaintiff
seeks recovery of penalties, attorney’s fees, interest, and costs
from the District for such improperly withheld amounts with the
amount to be determined at trial.”
Suffolk’s theory of recovery for its section 7107 claim is
predicated on its showing that the District breached the prime
contract. Without a breach of the contract, there is no showing
retention proceeds were wrongfully withheld. Accordingly,
although the District received a verdict in its favor on the
section 7107 retention proceeds issue due to the jury’s response to
Question 5, under Harris the trial court did not err by examining
the whole litigation to determine Suffolk was the prevailing
party.
Further, section 7107, subdivision (f), permits the
prevailing party “in any action for the collection of funds
wrongfully withheld” (italics added) to receive attorney fees and
costs. The plain text of section 7107, subdivision (f), does not
limit the award of attorney fees to the prevailing party, only in an
action for the collection of retention proceeds wrongfully withheld.
By contrast, the first sentence in subdivision (f) clearly limits the
interest penalty (rather than attorney fees and costs) to retention
52
payments that are not timely made. (See Pub. Contract Code,
§ 7107, subd. (f) [“In the event that retention payments are not
made within the time periods required by this section, . . . unpaid
amounts shall be subject to a charge of 2 percent per month on
the improperly withheld amount.”].) Section 7107 thus
contemplates a situation where a party may receive attorney fees
and costs when it prevails on claims for failure to pay funds that
are intertwined with retention proceeds claims.
The District cites several cases for the proposition the court
may only consider who prevails in an action for wrongfully
withheld retention proceeds. (See East West Bank v. Rio School
Dist. (2015) 235 Cal.App.4th 742 (East West Bank); Graciano,
supra, 144 Cal.App.4th 140; Denver D. Darling, Inc. v. Controlled
Environments Construction, Inc. (2001) 89 Cal.App.4th 1221
(Denver Darling).) But none of these cases addresses the issue in
this case involving intertwined retention proceeds and contract
claims, nor do they undermine Harris, which is directly on point.
First, the District cites East West Bank, supra,
235 Cal.App.4th at pages 749 to 750 for the general proposition
that the purpose of section 7107 is directed solely to retention
proceeds and that this purpose would not be served by
considering the impact of change orders unrelated to retention
proceeds to determine if a good faith dispute existed to withhold
retention proceeds. That portion of East West Bank is not
certified for publication and may not be cited as authority. (See
Cal. Rules of Court, rule 8.1115(a).)
In all events, the published portion of East West Bank is
consistent with Harris’s requirement that interrelated or
common issues may determine whether to consider causes of
action other than a section 7107 claim for purposes of
53
determining entitlement to attorney fees. East West Bank held
that attorney fees under section 7107 may be apportioned
between claims where there are no “common issues that must be
determined to resolve both a cause of action for which fees are
allowed and a cause of action for which fees are not allowed.”
(East West Bank, supra, 235 Cal.App.4th at p. 753.) But it held
that where “there are no such common issues, a defendant may
recover attorney fees relating solely to the cause of action for
which fees are allowed.” (Ibid.)
Graciano, supra, 144 Cal.App.4th at page 146, is inapposite
because it addresses the mandatory fee provisions of the
Automobile Sales Finance Act (ASFA) and the Consumer Legal
Remedies Act (CLRA), neither of which is at issue in this case
and both of which are tethered to their particular statutory
schemes. (See Civ. Code, §§ 2983.4 [ASFA providing for fees and
costs to be “awarded to the prevailing party in an action on a
contract or purchase order subject to the provisions of this
chapter”]; 1780, subd. (e) [CLRA requires court to award costs
and attorney fees to prevailing plaintiff “pursuant to this
section”].)
And Denver Darling addressed former Civil Code
section 3260, which contained an identical attorney fees provision
and was the equivalent to section 7107 for private construction
contracts. Denver Darling held the trial court properly found the
subcontractor was not entitled to attorney fees because the
parties were engaged in a bona fide dispute concerning the
retention amounts and neither party was chargeable with breach
of the contract. (See Denver Darling, supra, 89 Cal.App.4th at
p. 1241.) The court remanded the matter to the trial court to
consider whether the subcontractor was entitled to attorney fees
54
because the contractor appeared to have wrongfully withheld
more of the disputed amount than the statute allowed. (See id.
at p. 1242.) Denver Darling is not authority for the proposition
that a trial court is limited by the section 7107 retention proceeds
claim to determine the prevailing party. Denver Darling did not
address whether a trial court may consider the entire litigation
for a prevailing party determination and the District’s reliance on
dicta taken from the opinion is unpersuasive.
c. The trial court did not abuse its discretion when
it found Suffolk was the prevailing party22
We now examine whether the trial court, having considered
the proper legal criteria, abused its discretion when it decided
Suffolk was the prevailing party. In its statement of decision, the
trial court explained, “The jury found LAUSD breached the
contract by providing incorrect plans and specifications. It found
Suffolk was damaged as a result. While LAUSD succeeded in
persuading the jury that some of the delay was attributable to
Suffolk and that Suffolk did not comply with the claims
procedures respecting COP 199.3, thus relieving LAUSD of any
liability for wrongful retention [proceeds] based on its assessment
of liquidated damages, the jury expressly found that LAUSD did
wrongfully withhold retention [proceeds] in the amount of
$166,754. In addition, LAUSD paid $1,232,817 on the contract
after the action was filed. Whether measured by looking at the
litigation as a whole or the wrongful retention claim within the
22 Section 7107 allows a prevailing party to recover
“attorney’s fees and costs.” Because we determine Suffolk was
the prevailing party with regard to attorney fees, it was also
entitled to costs under section 7107.
55
breach of contract cause of action, Suffolk is the prevailing
party.”
The court did not abuse its discretion, and substantial
evidence supports its prevailing party determination. (See
Harris, supra, 239 Cal.App.4th at p. 1221.) Suffolk recovered
$856,429 on its breach of contract claim and $26,681 in prompt
payment penalties under section 7107. It also received
approximately $1.2 million from the District after Suffolk filed its
complaint, also pursuant to the requirements in section 7107.23
The trial court did not act arbitrarily, irrationally, or beyond the
bounds of reason when it decided Suffolk was the prevailing
party. (See ibid.; see also Pub. Contract Code, § 7107, subd. (f);
Maynard v. BTI Group, Inc. (2013) 216 Cal.App.4th 984, 994 [a
party who receives a net monetary recovery in an action is the
prevailing party in the “‘ordinary or popular sense’” of the term].)
The District’s alternate evaluation of the parties’ relative
recoveries is specious. The District argues it, and not Suffolk,
was the prevailing party because Suffolk recovered far less than
it sought at trial. Examining the litigation as a whole, Suffolk
sought $4,090,139 for failure to pay COP 199.3, $2,102,658 for its
other breach of contract damages, and over $1.3 million in
wrongful withholding of retention amounts, but it recovered
nothing for the failure to pay COP 199.3, and only $856,429 in
contract damages and $26,681 for wrongful withholding of
retention amounts. But a party’s recovery at trial of an amount
of damages less than what it sought does not mean it is not a
23 As explained below, during trial the District paid to Suffolk
$928,279 for Suffolk’s last payment application on the project,
plus two disbursements totaling approximately $300,000 for
previously approved amounts.
56
prevailing party. (See de la Cuesta v. Benham (2011)
193 Cal.App.4th 1287, 1295 [“the reality of litigation, almost
universally recognized,” is that “[a]ttorneys tend to err on the
side of overstating the extent of the claims being presented on
their client[s’] behalves”]; Bowman v. City of Berkeley (2005)
131 Cal.App.4th 173, 177-178 (Bowman) [attorney fees awarded
despite court’s acknowledgment that plaintiffs’ case was “largely
unsuccessful”]; cf. Buck v. Barb (1983) 147 Cal.App.3d 920, 926
[that a party recovered “less than the amount he prayed for does
not make his adversary the prevailing party within the meaning
of Civil Code section 1717”].)
2. The Trial Court Did Not Err by Denying Attorney
Fees Under Civil Code Section 9564 in the Third
Phase
As stated, the District challenges the trial court’s denial of
attorney fees to it under Civil Code section 9564 as the prevailing
party in the third phase of trial. The trial court did not err
because that statutory provision does not apply to the District.
Generally, a contractor like Suffolk that is awarded a
public works contract in excess of $25,000 is required to obtain a
payment bond to ensure payment to claimants if a direct
contractor or a subcontractor fails to pay. (Civ. Code, § 9550.) “A
claimant may maintain an action to enforce the liability of a
surety on a payment bond whether or not the claimant has given
the public entity a stop payment notice.” (See Civ. Code, § 9564,
subd. (a).) “In an action to enforce the liability on the bond, the
court shall award the prevailing party a reasonable attorney’s
fee.” (Id., subd. (c).) The District argues it is entitled to attorney
fees under Civil Code section 9564, subdivision (c), because the
57
third phase bench trial arose from “actions on the bond” and it is
the prevailing party in this phase of the litigation. We are not
persuaded.
Suffolk’s action against the District was not one to “enforce
the liability on the bond.” First, Suffolk is not a claimant
“authorized under Section 9100” of the Civil Code to maintain an
action to enforce the liability of a payment bond, such as an
employee, architect, project manager, or “other person having
charge of all or part of the public works contract.” (Civ. Code,
§§ 9100, subd. (a)(1), 9554, subds. (b)(1), (c).) Civil Code
section 9100, subdivision (a), does not include the owner of the
project, such as the District, as an authorized claimant and
subdivision (b) of that section expressly excludes a direct
contractor such as Suffolk from “assert[ing] a claim against a
payment bond under this title.” In short, the statutory scheme
does not contemplate recovery of attorney fees in a lawsuit
between a contractor and a public entity owner.
Second, as discussed, Suffolk’s complaint against the
District was for breach of contract and breach of implied
contractual indemnity. Suffolk did not plead a cause of action
against the District to enforce liability of the bond under Civil
Code section 9564. Nor does Suffolk seek attorney fees under
that section. The District “acknowledges Suffolk did not sue it ‘on
the payment bond.’” But it asserts that “the Phase 3 trial
qualifies as ‘an action on the bond’ under Section 9654” because
“Suffolk tried to transfer its liability on the bond for
subcontractor attorney’s fees to the District.” Suffolk, however,
attempted to transfer its liability on the bond into a separate
action that asserted breach of contract and implied indemnity
causes of action. The District cannot bootstrap statutory
58
attorney fees provisions onto a separate action that does not
involve that statute.
Walt Rankin & Associates, Inc. v. City of Murrieta (2000)
84 Cal.App.4th 605, 630 (Rankin), is instructive. There, a
subcontractor brought an action against the surety of a payment
bond when the general contractor of a project failed to pay the
subcontractor. The subcontractor discovered the surety providing
the payment bond was not solvent or authorized to do business in
the state. (See id. at p. 611.) The subcontractor added the city as
a defendant in its action relating to the park project, alleging the
city was negligent for approving the payment bond without
verifying the surety was solvent or able to do business in the
state. (See id. at p. 612.) As relevant here, the appellate court
denied attorney fees to the subcontractor under a statutory fee
provision similar to Civil Code section 9564. Rankin held the
claim against the city was “in the nature of a tort action against
the City for failure to perform a mandatory duty” and “was not an
action on the bond, or an action to enforce payment of the bond.”
(Id. at p. 630.)
Here, Suffolk’s action was not on the bond or to enforce
payment on the bond. It did not sue the District based on Civil
Code section 9564. That Suffolk attempted to recover in this
action, as contract damages, its payment of attorney fees to the
subcontractors and the attorney fees it incurred in defending
against the subcontractor lawsuits does not transform this
contract action into an action to enforce a payment bond.
59
3. The Trial Court Erred When It Awarded $169,828 in
Prejudgment Interest
Lastly, the District argues the trial court erroneously
awarded Suffolk prejudgment interest of $169,828 pursuant to
Civil Code section 3287, subdivision (a) (section 3287(a)), on three
payments it voluntarily made to Suffolk before the jury’s verdict.
The District contends prejudgment interest on these payments
was not authorized by section 3287(a) because Suffolk failed to
demonstrate the payments met the statutory requirements (they
were “certain or capable of being made certain” and Suffolk had a
right to recovery that vested on a particular day), or that the
payments constituted damages that were awarded by a court or
jury.
a. Additional background
In the final amended judgment, the trial court granted
Suffolk prejudgment interest totaling $216,044, mostly arising
from three payments the District made to Suffolk after Suffolk
filed suit: a $928,279 payment for Suffolk’s final payment
application (Pay App 24), and two disbursements totaling
$304,538 for amounts that were owed to Suffolk under the prime
contract after completion of the project (phase 2 payments).24
At trial, the evidence demonstrated that on November 20,
2013, approximately one year after the substantial completion
date for the project, Suffolk submitted Pay App 24 to the District.
24 The total prejudgment interest award of $216,044 also
included prejudgment interest of $46,216 for the delayed
payment for change order T-643, which was a pass-through claim
submitted on behalf of QPS. The District does not challenge this
portion of the prejudgment interest award on appeal.
60
The District denied the application, citing “multiple calculation
errors regarding the Contract retention, total amounts earned,
amounts previously paid by the District, and the balance due.”
Suffolk made its final submission of Pay App 24 on March 21,
2014, after it had filed its lawsuit.
On May 30, 2014, the District paid $928,279 on Pay App 24
after “unilaterally” calculating the “accurate” amount due.25
(While Suffolk argues the District paid less than it owed, Suffolk
does not pursue additional monies for Pay App 24 in this appeal.)
During the jury trial, the District issued the phase
2 payments to Suffolk. On March 20, 2019, the District issued a
check to Suffolk for $292,569, representing Suffolk’s 50 percent
share of developer contingency savings.26 On April 15, 2019, the
District issued a check for $11,969, representing the amounts the
District had previously approved for an allowance draw and a
contingency draw.
The approvals for the phase 2 payments were not
discovered until the District’s manager overseeing the finance
and accounting department reviewed the accounting records in
25 The court observed Suffolk sought prejudgment interest on
$911,274 even though the evidence indicated the actual amount
paid was $928,279.06. The court awarded the amount sought by
Suffolk.
26 The prime contract provides for a “Construction
Contingency for the benefit of the Developer.” The provision
states, “In the event Developer completes the construction of the
School Improvements, without exhausting the Construction
Contingency, then the balance of the Construction Contingency
shall be shared in the percentage amounts shown in the
Developer’s Price Proposal,” which the District’s witness testified
was 50 percent to the District and 50 percent to Suffolk.
61
preparation for his deposition. He testified these draws were
approved “but they were never presented in an application for
payment and never paid.” It was his understanding the amounts
were not paid because “it was in litigation at the time and was
frozen.”
Suffolk moved for prejudgment interest on liquidated
claims paid by the District during trial pursuant to
section 3287(a) and on unliquidated claims (i.e., the jury’s
contract damages award) under subdivision (b) of section 3287.
Suffolk argued Pay App 24 and the phase 2 payments were
liquidated claims because they were damages certain, or capable
of being made certain, by calculation and should have been
disbursed at the latest by the time Suffolk submitted its final
version of Pay App 24 on March 21, 2014.
The trial court denied Suffolk’s request for prejudgment
interest under Civil Code section 3287, subdivision (b), but
awarded prejudgment interest under section 3287(a) of $216,044.
The court found the amounts were capable of being made certain
under section 3287(a) from the testimony of the District’s
accounting witness. The court rejected the District’s argument
that Suffolk was not entitled to prejudgment interest where the
amounts were not adjudicated or billed. The court also stated,
“Nor is it persuasive to argue that interest should not be paid on
Pay App 24 because the jury found that LAUSD did not
wrongfully withhold this progress payment. While this finding
excused LAUSD from prompt payment penalties it does not mean
the amount was unliquidated. LAUSD itself calculated the
amount.”
On appeal, the District challenges the following
prejudgment interest awards: (1) $17,476 in interest on the
62
District’s payment to Suffolk of $928,279 for Pay App 24
(prejudgment interest from March 21, 2014 to May 30, 2014); and
(2) $152,352 in interest on the two checks the District issued to
Suffolk during the second phase of the trial (prejudgment interest
for the five-year period from March 21, 2014 to March 20, 2019).
b. Standard of review and governing law
We review the court’s award of prejudgment interest for
abuse of discretion. (See A & M Produce Co. v. FMC Corp. (1982)
135 Cal.App.3d 473, 496.) The interpretation of the prejudgment
interest provisions of section 3287(a), however, is a question of
law subject to de novo review. (See Flethez v. San Bernardino
County Employees Retirement Assn. (2017) 2 Cal.5th 630, 639
(Flethez).)
Section 3287(a) provides:
A person who is entitled to recover damages certain, or
capable of being made certain by calculation, and the right
to recover which is vested in the person upon a particular
day, is entitled also to recover interest thereon from that
day, except when the debtor is prevented by law, or by the
act of the creditor from paying the debt. This section is
applicable to recovery of damages and interest from any
debtor, including the state or any county, city, city and
county, municipal corporation, public district, public
agency, or any political subdivision of the state.
“[I]n order to recover prejudgment interest under this
statute, ‘the claimant must show: (1) an underlying monetary
obligation, (2) damages which are certain or capable of being
made certain by calculation, and (3) a right to recovery that vests
on a particular day.’” (Flethez, supra, 2 Cal.5th at p. 640.) “[I]t
63
has long been settled that the primary purpose of section 3287(a)
‘is to provide just compensation to the injured party for loss of use
of the [underlying] award during the prejudgment period—in
other words, to make the plaintiff whole as of the date of the
injury.’” (Id. at p. 643.) Prejudgment interest under
section 3287(a) is thus considered a component of damages. (See
id. at p. 635, fn. 2.) Civil Code section 3281 defines damages as
follows: “Every person who suffers detriment from the unlawful
act or omission of another, may recover from the person in fault a
compensation therefor in money, which is called damages.” “[I]t
is clear that Civil Code section 3287 looks to the certainty of the
damages suffered by the plaintiff, rather than to a defendant’s
ultimate liability, in determining whether prejudgment interest
is mandated.” (Wisper Corp. v. California Commerce Bank (1996)
49 Cal.App.4th 948, 958.)
c. Analysis
The District contends the trial payments do not constitute
damages within the meaning of section 3287(a) and Civil Code
section 3281 because it voluntarily made the payments and the
amounts were not awarded by a court or jury. The District
further contends Suffolk failed to show the prerequisites for
prejudgment interest under section 3287(a); that is, damages
that were certain or capable of being made certain by calculation,
and a right to recovery that vested on a particular day.27 We
conclude the District is correct that Suffolk is not entitled to
27 The District does not dispute Suffolk showed an underlying
monetary obligation as to the payments at issue.
64
prejudgment interest on amounts the District voluntarily paid
that were not “damages” as defined by Civil Code section 3281.
An award of prejudgment interest under section 3287(a)
extends only to amounts adjudicated as damages by a jury or
trial court, as opposed to authorizing interest on voluntary
payments by a litigant during the course of trial which were not
part of any judgment. Under Civil Code section 3281, damages
must arise from “the unlawful act or omission of another.” In
Mass v. Board of Education (1964) 61 Cal.2d 612 (Mass), the
California Supreme Court reasoned that a finding of wrongful
action must precede the award of prejudgment interest. In Mass,
a local board of education wrongfully suspended a teacher, who
was thus entitled to reinstatement and back pay from the date of
suspension. (Id. at p. 616.) The Supreme Court determined the
teacher was also entitled to prejudgment interest pursuant to
section 3287(a) from the dates upon which his salary payments
were due. (Id. at p. 625.) The Court explained, “Each salary
payment in the instant case accrued on a date certain. Unless
the suspension itself can be sustained and the board thus
relieved of any obligation whatsoever, the salary payments
became vested as of the dates they accrued.” (Ibid.; see also
Meister v. Mensinger (2014) 230 Cal.App.4th 381, 396 (Meister)
[“‘Damages’ are the monetary compensation awarded to parties
who suffer detriment for the unlawful act or omission of another;
they are assessed by a court against wrongdoers for the
commission of a legal wrong of a private nature.”].)
Without a concession by the District or a finding that the
District acted unlawfully, the payments to Suffolk were not
65
damages to which prejudgment interest could attach.28 Indeed,
the jury answered “No” to Question 13, which asked, “Did
LAUSD wrongfully withhold the progress payment for Suffolk’s
Payment Application No. 24?” The jury’s finding means the
District’s payment to Suffolk for Pay App 24 may not be
characterized as damages arising from an unlawful act or
omission. We are not persuaded by the trial court’s attempt to
distinguish the jury’s finding in Question 13. The trial court
stated the jury’s finding “excused LAUSD from prompt payment
penalties [but] it does not mean the amount was unliquidated.”
This analysis does not account for the requirement of unlawful
conduct under Civil Code section 3281 and Mass. The trial court
thus abused its discretion by awarding prejudgment interest
under section 3287(a) as to this payment when the jury expressly
found no wrongful conduct. (See Horsford v. Board of Trustees of
California State University (2005) 132 Cal.App.4th 359, 393
[“judicial discretion must be measured against the general rules
of law and, in the case of a statutory grant of discretion, against
the specific law that grants the discretion”].)
The jury made no findings regarding the phase 2 payments,
much less that the District committed an “unlawful act or
omission” in failing to make these payments before trial. This is
because the phase 2 payments were never at issue. In its motion
for prejudgment interest, Suffolk acknowledged it was not aware
these amounts were owed: “To Suffolk’s surprise, LAUSD issued
28 We express no opinion on whether any interest due as
damages based on the amounts the District paid is recoverable
under a separate action for damages. (See Kawasho Internat.,
U.S.A., Inc. v. Lakewood Pipe Service, Inc. (1983) 152 Cal.App.3d
785.)
66
two more checks.” The District paid the amounts in question
before its obligation was reduced to a judgment, and Suffolk
accepted those payments, apparently without protest. After trial,
Suffolk cannot then go back to the trial court and request
payment of prejudgment interest on damages that were never
determined to have arisen from an unlawful act or omission. (Cf.
Meister, supra, 230 Cal.App.4th at p. 396.) Suffolk did not meet
its burden to show unadjudicated payments of money paid to
Suffolk for amounts that were not awarded or assessed by any
jury or court satisfies the definition of “damages” under
section 3287(a) and Civil Code section 3281. (See Flethez, supra,
2 Cal.5th at p. 640.)
Accordingly, we strike from the judgment the award of
prejudgment interest in the amount of $169,828, which is based
on amounts the District paid to Suffolk before judgment.
DISPOSITION
The judgment dated January 22, 2022 is modified to strike
the award of prejudgment interest to Suffolk from LAUSD in the
amount of $169,828, leaving an award of $46,216. The judgment
is otherwise affirmed as modified. The parties are to bear their
own costs on appeal.
MARTINEZ, P. J.
We concur:
FEUER, J. STONE, J.
67
Vous vous demandez comment ce texte s’applique à votre situation ?
Consultation gratuite, sans engagement
Décrivez votre situation. Notre équipe vous recontactera par e-mail pour votre consultation.
Poursuivez vos recherches dans ChatGPT ou Claude
Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.