Shirley R. Hulsey v. Build Art, LLC

CourtListener 10844510Ala17 avr. 2026

Texte intégral

Rel: April 17, 2026

Notice: This opinion is subject to formal revision before publication in the advance sheets of Southern
Reporter. Readers are requested to notify the Reporter of Decisions, Alabama Appellate Courts,
300 Dexter Avenue, Montgomery, Alabama 36104-3741 ((334) 229-0650), of any typographical or other
errors, in order that corrections may be made before the opinion is printed in Southern Reporter.

SUPREME COURT OF ALABAMA
OCTOBER TERM, 2025-2026

_________________________

SC-2025-0564
_________________________

Shirley R. Hulsey

v.

Build Art, LLC

Appeal from Tuscaloosa Circuit Court
(CV-20-900281)

MENDHEIM, Justice.

Shirley R. Hulsey appeals from a summary judgment entered by

the Tuscaloosa Circuit Court in favor of Build Art, LLC ("Build Art"), in
SC-2025-0564

her tort action against Yellow Hammer Capital Management, LLC

("Yellow Hammer"), Build Art, and fictitiously named defendants.

In December 2011, Hulsey and her husband purchased their

residence in Tuscaloosa as joint tenants with the right of survivorship.

In August 2017, Yellow Hammer purchased the lot adjacent to Hulsey's

residence ("lot 22"). Lot 22 was at a higher elevation than and sloped

toward Hulsey's lot. Also, Hulsey's lot had a retaining wall along much

of its length, near or on the common boundary with lot 22. Between the

retaining wall and Hulsey's residence was a side yard that was several

feet wide.

According to an affidavit from Marcus Minges, the managing

member of Build Art, Yellow Hammer retained Build Art to construct a

residence on lot 22. Build Art is owned by Yellow Hammer and Minges.

In November 2017, Build Art applied for a building permit, which it

received. In approximately January 2018, Build Art began construction

on the residence with the assistance of a number of subcontractors.

According to Minges, "[t]here was no need for excavating and/or grade

work on Lot 22 because the lot was build ready when Build Art began

work." Minges also averred that "Build Art's employees did not perform

2
SC-2025-0564

excavations or grading on the project. Build Art did not supply

excavating equipment for use by any of its subcontractors. Build Art did

not exercise control over the manner in which any excavation, grading,

or landscaping of Lot 22 was performed." However, in Build Art's

interrogatory answers that Hulsey filed in opposition to its motion for a

summary judgment, it responded as follows:

"7. Please identify the persons or entities who designed,
reconfigured, constructed excavated, cut, filled and performed
work to Lot 22 Neptune's Cove at NorthRiver Phase One.

"ANSWER: [Build Art] object[s] to this Interrogatory as
being vague. Without waiving this objection, Marcus
Minges."

Construction on the lot-22 residence was completed, and a certificate of

occupancy was issued in August 2019.

A preconstruction picture of lot 22 reflects a slight downward slope

in the side yard from Hulsey's residence to near the bottom of the

retaining wall. According to Hulsey's deposition testimony, she had

never seen any water coming off of lot 22 onto her lot before construction

began on lot 22. Hulsey stated that lot 22 originally was not flat but was

"a turtle back … where the water would flow back to the front. … So

when they went in there to make that land level enough to do a

3
SC-2025-0564

foundation, it took that drainage away." She stated that she first noticed

water coming onto her lot from lot 22 in April 2018, "when the [silt fence]

screen … overloaded with mud and caused it to breach, and that's when

it dumped in my yard." Hulsey stated that when the silt fence collapsed,

"it dumped close to four inches of dirt in my backyard that flowed almost

all the way through my backyard," filling up the sloped area that drained

the side yard between the lots and her back yard and "creating a dam"

that restricted the water flow from her property. She stated that, after

the silt fence failed, she brought the issue to "the contractor's attention,"

but he did nothing about it. Hulsey stated that, after lot 22 was graded

and construction was completed, the silt fence was removed and water

continued to flow onto her property thereafter. Postconstruction pictures

of the side yard at issue reflect that the slope from the retaining wall was

toward, rather than away from, Hulsey's residence.

John Stevens, a civil engineer who had been retained by Hulsey,

testified in his deposition that he had experience on hydrology issues and

the "flow of water from rain." He stated that he had designed stormwater

systems and also had provided structural reports to various clients. He

stated that he did not consider himself an expert in the field of hydrology,

4
SC-2025-0564

but considered himself a "semi-expert," which he defined as meaning that

he did not take jobs that he did not understand. When asked about jobs

that he had taken on in the last 10 years regarding the flow of water,

Stevens stated that some were for businesses, "but most of them [were]

homes that they can't stop water from getting in" and "[t]here's damage

because of the water getting into the homes -- … -- either slabs or crawl

space."

According to Stevens, the foundation of Hulsey's residence was

failing, the house was sinking, and he had recommended that helical

piers be used to shore up the side of the house nearest to lot 22. He also

had recommended that pressure grouting be used to support any hollow

area under the slab. Stevens testified that cracks on the side of Hulsey's

residence were "the type of cracks you see when the footing is moving."

According to Stevens, he did not think that there was any possible cause

for the cracks other than the soil being saturated under the slab.

In March 2020, Hulsey filed a complaint against Yellow Hammer,

Build Art, and numerous fictitiously named defendants, including those

persons "whose names [were] not yet known and who [had] performed

5
SC-2025-0564

services on all or part of Lot 22, or adjacent to Lot 22."1 Hulsey alleged

that Yellow Hammer, Build Art, and the fictitiously named defendants

had caused her and her residence to suffer damage based, in part, on the

defendants having

"knowingly, intentionally, recklessly, wantonly and/or
negligently effected demolition, clearing, grading,
development and construction as part of their efforts to
develop and sell a new house on Lot 22. The erection of the
house on Lot 22 (such work includes, but is not limited to[,]
design, demolition, construction clearing, grading, repair, and
the maintenance associated therewith) was done in such a
manner that such activity has caused the wrongful flooding of
surface waters, silt and debris onto the Hulsey Property via
surface water run-off."

Hulsey alleged against "all the defendants" claims of trespass, nuisance,

wrongful infliction of mental anguish and emotional distress, negligence,

wantonness, and a violation of her common-law right regarding the

natural flow of surface water as discussed in Sargent v. Lambert

Construction Co., 378 So. 2d 1153, 1155 (Ala. Civ. App. 1979). In addition

to requesting compensatory and punitive damages, Hulsey also

1Hulsey's husband also was a plaintiff. However, he died on
December 15, 2021. Pursuant to Rule 24, Ala. R. Civ. P., Build Art filed
a suggestion of death regarding Hulsey's husband. After no substitution
was made for him, Build Art filed a motion to dismiss his claims, which
the circuit court granted.
6
SC-2025-0564

requested permanent injunctive relief regarding the allegedly altered

water flow from lot 22 onto her lot.

Build Art filed an answer denying Hulsey's allegations and alleging

numerous affirmative defenses. Yellow Hammer filed a motion to

dismiss, which also included a statement denying Hulsey's allegations.

A hearing was set to be held on June 29, 2020, on the motion to dismiss.

On June 30, 2020, the circuit court entered an order that stated that

Yellow Hammer's motion to dismiss was moot.

In March 2025, Build Art filed a motion for a summary judgment,

along with supporting evidence, including an affidavit from Minges and

deposition testimony from Hulsey and Stevens. Hulsey filed a response

to Build Art's motion for a summary judgment. She argued that

summary judgment would be improper because, she said, material issues

of fact were in dispute. According to Hulsey, she had never experienced

water runoff from lot 22 before the construction on that lot, and, she said,

the evidence would support the conclusion that Build Art had interfered

with the natural drainage of water, causing damage to her property.

After conducting a hearing on Build Art's motion for a summary

judgment, the circuit court entered an order on May 13, 2025, granting

7
SC-2025-0564

Build Art's summary-judgment motion as to all the claims against it. The

May 2025 order stated that "[a]ll other claims remain pending." Hulsey

filed a motion to reconsider, which the circuit court denied. On July 1,

2025, the circuit court entered an order certifying the May 2025 order as

final pursuant to Rule 54(b), Ala. R. Civ. P. On July 31, 2025, Hulsey

filed a notice of appeal to this court.

Hulsey argues that the circuit court erred by entering a summary

judgment in favor of Build Art because, she says, there were genuine

issues of material fact that must be resolved by a jury. Hulsey also

references the issue whether the May 2025 order, as certified by the July

2025 order, is a final judgment that will support an appeal. Build Art

has not replied regarding the latter issue, and we agree with Hulsey's

finality concern.

The circuit court adjudicated only the claims against Build Art,

which performed the work on lot 22 for Yellow Hammer, against whom

the same claims remain pending. Rule 54(b) provides, in pertinent part:

"When more than one claim for relief is presented in an action,
whether as a claim, counterclaim, cross-claim, or third-party
claim, or when multiple parties are involved, the court may
direct the entry of a final judgment as to one or more but fewer
than all of the claims or parties only upon an express

8
SC-2025-0564

determination that there is no just reason for delay and upon
an express direction for the entry of judgment."

Nevertheless, " '[t]he trial court cannot confer appellate jurisdiction upon

this [C]ourt through directing entry of judgment under Rule 54(b) if the

judgment is not otherwise "final." ' " Dzwonkowski v. Sonitrol of Mobile,

Inc., 892 So. 2d 354, 362 (Ala. 2004) (quoting Robinson v. Computer

Servicenters, Inc., 360 So. 2d 299, 302 (Ala.1978)). And this Court must

dismiss an appeal when we determine that the order appealed from is

not a final judgment, even when a trial court has entered a Rule 54(b)

certification. See Hammock v. Wal-Mart Stores, Inc., 8 So. 3d 939, 941

(Ala. 2008); see also, e.g., Harlan Home Builders, Inc. v. Hayslip, 58 So.

3d 102, 108 n.3 (Ala. 2010) ("[T]he summary judgment entered by the

trial court was not a final judgment that was properly appealable to this

Court at the time it was entered or at the time it was purportedly certified

as final by the trial court; therefore, this Court acquired no jurisdiction

over the purported appeal of that judgment.").

"This Court looks with some disfavor upon certifications
under Rule 54(b).

" 'It bears repeating, here, that
" '[c]ertifications under Rule 54(b) should be
entered only in exceptional cases and should not
be entered routinely.' " State v. Lawhorn, 830 So.
9
SC-2025-0564

2d 720, 725 (Ala. 2002) (quoting Baker v. Bennett,
644 So. 2d 901, 903 (Ala. 1994), citing in turn
Branch v. SouthTrust Bank of Dothan, N.A., 514
So. 2d 1373 (Ala. 1987)). " ' "Appellate review in a
piecemeal fashion is not favored." ' " Goldome
Credit Corp. [v. Player, 869 So. 2d 1146, 1148 (Ala.
Civ. App. 2003)] (quoting Harper Sales Co. v.
Brown, Stagner, Richardson, Inc., 742 So. 2d 190,
192 (Ala. Civ. App.1999), quoting in turn Brown v.
Whitaker Contracting Corp., 681 So. 2d 226, 229
(Ala. Civ. App. 1996)) (emphasis added).'

"Dzwonkowski v. Sonitrol of Mobile, Inc., 892 So. 2d 354, 363
(Ala. 2004). Also, a Rule 54(b) certification should not be
entered if the issues in the claim being certified and a claim
that will remain pending in the trial court ' "are so closely
intertwined that separate adjudication would pose an
unreasonable risk of inconsistent results." ' Clarke-Mobile
Counties Gas Dist. v. Prior Energy Corp., 834 So. 2d 88, 95
(Ala. 2002) (quoting Branch v. SouthTrust Bank of Dothan,
N.A., 514 So. 2d 1373, 1374 (Ala. 1987))."

Schlarb v. Lee, 955 So. 2d 418, 419-20 (Ala. 2006). See also, e.g., Scott v.

Advanced Pharm. Consultants, Inc., 84 F.4th 952, 962 (11th Cir. 2023)

(concluding that certification of finality was not proper when the

summary judgment adjudicated all counts against one defendant but left

the identical counts against the other defendant unadjudicated and that

adjudicating the same counts separately would be duplicative, waste

substantial judicial resources, and run the risk of inconsistent rulings in

different appeals).

10
SC-2025-0564

Based on the relationship between Yellow Hammer and Build Art

and the nature of the alleged claims, which arise from the same operative

facts, we conclude that the claims against Build Art and Yellow Hammer

are intertwined and should not be adjudicated separately, which would

be duplicative, waste judicial resources, and risk inconsistent rulings in

the circuit court and in any subsequent appeal. Thus, the circuit court

exceeded its discretion in certifying the partial summary judgment as

final.

" 'A nonfinal judgment will not support an appeal.' " Schlarb, 955 So.

2d 420 (quoting Dzwonkowski, 892 So. 2d at 363). Accordingly, this

appeal is dismissed.

APPEAL DISMISSED.

Stewart, C.J., and Shaw, Bryan, and McCool, JJ., concur.

11

Poursuivez vos recherches dans ChatGPT ou Claude

Connectez Omnilex pour rechercher dans le corpus juridique depuis votre assistant IA.