Question juridique clé
Whether SBB bore the risk of extra costs caused by deviation from the assumed K-factor
Solution extraite
Neither the contract nor SIA norms assigned SBB the risk; the consortium had to bear the extra costs.
Motifs extraits
The technical report did not allocate the risk to SBB, while the special contractual conditions expressly excluded compensation for changes to the blasting plan. No actual or interpreted consensus supported the plaintiffs' view.