Question juridique clé
Whether a binding general-plan/execution contract for the project had been concluded on 24 June 1999.
Solution extraite
No. The parties had at most agreed to later conclude a written contract and never reached agreement on all essential terms, especially the contractual subject and the promised work result.
Motifs extraits
Contract formation requires consensus on all essential elements. The appellant did not establish what the allegedly agreed additional work result was, and the findings showed the parties remained divided over the cost ceiling and the scope of the project.