Question juridique clé
Whether the tender documents had to be interpreted as requiring an own construction schedule and more detailed comments on deadlines
Solution extraite
The cantonal courts' interpretation was not arbitrary; X AG could reasonably be expected to submit its own construction programme and address the timetable.
Motifs extraits
Item 221 of the tender documents expressly requested a construction programme and an assessment of the prescribed schedule. Even if the wording could have been clearer, the interpretation was still defensible; X AG could have clarified the requirement by inquiry with the listed contact office.