Question juridique clé
Whether the complainant had standing to challenge the permit and the scope of review before the Federal Supreme Court.
Solution extraite
The complaint was admissible only within the limits of the challenged building-permit proceeding; arguments concerning earlier proceedings and parking/traffic safety were outside the case.
Motifs extraits
Only the 2005 building application was at issue. Broader objections relating to earlier procedures were not part of the disputed decision.