CourtListener 10110507•Michael A. Schnaubelt v. Uecker Development LLC
Michael A. Schnaubelt v. Uecker Development LLC
CourtListener 10110507Wisctapp15.03.2022
Gesamter Gesetzestext
COURT OF APPEALS
DECISION NOTICE
DATED AND FILED This opinion is subject to further editing. If
published, the official version will appear in
the bound volume of the Official Reports.
March 15, 2022
A party may file with the Supreme Court a
Sheila T. Reiff petition to review an adverse decision by the
Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10
and RULE 809.62.
Appeal No. 2020AP2070 Cir. Ct. No. 2018CV992
STATE OF WISCONSIN IN COURT OF APPEALS
DISTRICT III
MICHAEL A. SCHNAUBELT AND RENAE L. SCHNAUBELT,
PLAINTIFFS-APPELLANTS,
V.
UECKER DEVELOPMENT LLC, RUCON CONSTRUCTION MANAGEMENT,
INC. AND ANDREW R. UECKER,
DEFENDANTS-RESPONDENTS.
APPEAL from a judgment of the circuit court for Outagamie
County: CARRIE A. SCHNEIDER, Judge. Affirmed in part; reversed in part and
cause remanded for further proceedings.
Before Stark, P.J., Hruz and Nashold, JJ.
Per curiam opinions may not be cited in any court of this state as precedent
or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3).
No. 2020AP2070
¶1 PER CURIAM. Michael and Renae Schnaubelt (“the Schnaubelts”)
appeal a grant of summary judgment dismissing their claims against Andrew
Uecker (“Uecker”), Uecker Development, LLC (“the Development Company”),
and Rucon Construction Management (“Rucon”).1 The Schnaubelts’ claims arose
out of their offer to purchase a newly built home (“the Agreement”). The
Schnaubelts contend that they properly pled a breach of contract claim against
Rucon, the construction company that built the home. They also argue that there
were genuine issues of material fact regarding whether the real estate broker who
drafted and negotiated the Agreement, Uecker, violated his statutory duties as a
real estate broker, and whether the seller of the home, the Development Company,
violated its implied duty of good faith and was unjustly enriched. In the
alternative, the Schnaubelts argue that the circuit court erroneously exercised its
discretion by denying them leave to amend their complaint.
¶2 We agree that, on this record, the circuit court erroneously exercised
its discretion by denying the Schnaubelts’ request to amend their complaint, but
we reject the Schnaubelts’ other arguments. Accordingly, we affirm in part,
reverse in part, and remand for further proceedings consistent with this opinion.
BACKGROUND
¶3 In October 2017, the Schnaubelts began having discussions with
Uecker regarding purchasing a residential home from the Development Company
that was in the process of being built by Rucon. Uecker was a licensed real estate
broker and had a financial and ownership interest in both the Development
1
When necessary, we refer to the Schnaubelts individually by their first names.
2
No. 2020AP2070
Company and Rucon. Uecker asked Renae whether the Schnaubelts had an
agency agreement with another real estate broker, and he suggested that Renae
check with the Schnaubelts’ previous real estate broker, Lindsey Walters. Uecker
also suggested, however, that he draft the Agreement “because of all of the
[specifications], construction contract[,] and other related documents related to
constructing a new home.”
¶4 On Friday, October 20, 2017, Renae contacted Walters about her
discussions with Uecker. After speaking to Renae, Walters called Uecker, and
Uecker told her that he would have to call her back on Monday, October 23.
Before that phone call could take place, however, the Schnaubelts met with
Uecker on Sunday, October 22, to “discuss the project.”
¶5 At that meeting, Uecker presented the Agreement that he had drafted
and told the Schnaubelts that “we need to keep things moving” and that if they
“wanted to make changes” to the construction plans, the Schnaubelts needed to
sign the Agreement. Uecker further stated that the Schnaubelts could not make
changes to the construction plans without signing the Agreement and that they
needed to decide right away to avoid project delays. At that time, the foundation
for the home had been poured, the framing was nearly complete if not complete,
and “the electrical and utilities were being roughed in.”
¶6 The Schnaubelts ultimately signed the Agreement that day, agreeing
to provide $50,000 in earnest money and to purchase the home for $900,000. The
Agreement did not contain either an inspection or financing contingency, but an
addendum did include an appraisal contingency. The Agreement also
incorporated specifications, designs and drawings for the home that had been
previously prepared by Rucon. Consistent with their discussions with Uecker, the
3
No. 2020AP2070
Schnaubelts were able to make changes to the fixtures and the design of the home.
They hired, at their own expense, a third-party interior designer who provided
design services during the remainder of the construction process.
¶7 During the course of construction, the parties amended the
Agreement four times. The first amendment occurred in November 2017, and the
parties agreed, among other things, that: (1) the Schnaubelts would be responsible
for covering any difference between the appraised value and the final purchase
price; (2) the Schnaubelts would deposit $75,000 into an escrow account “for the
build of the home upon a completed amendment or change order signed by the
[parties]”; (3) funds dispersed from the escrow account would be nonrefundable;
and (4) the closing date would be February 23, 2018. The second, third and fourth
amendments all adjusted the purchase price, which eventually came to
$1,035,417.64. There is no evidence that Walters was ever involved in drafting,
reviewing or executing any of the amendments.
¶8 Sometime around when the last amendment was executed in late
January 2018, the Schnaubelts started expressing their displeasure regarding the
lack of detail supporting the changes to the purchase price. Around that same
time, they also began voicing concerns over what they perceived to be defects in
the home’s construction. In particular, the Schnaubelts identified issues with the
home’s siding, windows and flashing. Although the Agreement did not contain an
inspection contingency, the parties verbally agreed to have an inspection
performed on February 13, 2018, ten days before the closing date.
¶9 Prior to the scheduled inspection, Uecker sent the Schnaubelts a
proposed fifth amendment to the Agreement, which would have changed the final
purchase price again, provided a right to inspect the property, and moved the
4
No. 2020AP2070
closing date to March 2, 2018. On February 12, Renae informed Uecker by email
that the Schnaubelts would not be “comfortable signing anything further until we
discuss the final numbers at your office.” The next day, after the Schnaubelts did
not sign the proposed amendment, Uecker cancelled the scheduled inspection and
informed the Schnaubelts that “[w]e’re unable to accommodate your request for a
home inspection until the amendment is signed.”
¶10 On February 20, 2018, the Development Company’s counsel
notified the Schnaubelts that the fifth amendment to the Agreement needed to be
signed by the following day, otherwise closing would proceed as scheduled on
February 23. The Development Company’s counsel also demanded that the
Schnaubelts be present for a walkthrough of the home on February 22, and that
only the Schnaubelts and their inspector would be allowed on the property at that
time. The Schnaubelts did not attend the scheduled closing on February 23.
¶11 Uecker subsequently sent the Schnaubelts a “Cancellation
Agreement & Mutual Release” that included provisions cancelling the Agreement
and allowing the Development Company to retain the earnest and escrow money.
The Schnaubelts did not sign that agreement but, in turn, demanded that the
Development Company immediately refund their earnest money, return “the
advanced funds used for upgrades,” and reimburse their out-of-pocket expenses.
In May 2018, the Development Company sold the home to a third-party buyer for
$1,025,000.
¶12 After the parties failed to agree on the terms of cancelling the
Agreement, the Schnaubelts filed this lawsuit. The Schnaubelts alleged that
Rucon breached the Agreement by failing to complete construction in a timely and
proficient manner. They also alleged that Uecker breached his statutory duties as
5
No. 2020AP2070
a real estate broker by “pressuring [them] into signing one-sided provisions” and
by advancing his own interests over their interests. Finally, the Schnaubelts
alleged that the Development Company was unjustly enriched by their fixtures and
design work, and that it breached the Agreement—specifically, its implied duty of
good faith and fair dealing—by cancelling the inspection.2 Rucon, Uecker, and
the Development Company all moved for summary judgment on the Schnaubelts’
claims.
¶13 In a written decision, the circuit court granted summary judgment
and dismissed all of the Schnaubelts’ claims, except for their unjust enrichment
claim against the Development Company. As for the unjust enrichment claim, the
court granted the Schnaubelts partial summary judgment on that claim and ordered
that they “provide proof of their actual costs for the installed fixtures ….” The
court noted, however, that the Development Company did not use the
Schnaubelts’ landscaping plan and that a portion of their design work was
subsequently changed to accommodate the third-party buyer. It therefore
concluded that no genuine issues of material fact existed on those claims of unjust
enrichment. The court also denied the Schnaubelts’ request for leave to amend
their complaint as an alternative to the court granting summary judgment.
¶14 The Schnaubelts later filed a motion for reconsideration of the
circuit court’s summary judgment decision, which the court denied. After the
Schnaubelts submitted documentation regarding their unjust enrichment claim, the
2
The Schnaubelts also alleged a conversion claim against the Development Company.
The circuit court granted summary judgment on that claim, and the Schnaubelts do not make any
arguments on appeal regarding that decision. We therefore do not address the conversion claim
further.
6
No. 2020AP2070
court awarded them a judgment of $14,516.69 for the fixtures in the home. The
Schnaubelts now appeal.3 Additional facts will be provided in the discussion
below.
DISCUSSION
¶15 We review a circuit court’s summary judgment decision de novo,
applying the same methodology as the circuit court. Springer v. Nohl Elec.
Prods. Corp., 2018 WI 48, ¶9, 381 Wis. 2d 438, 912 N.W.2d 1. First, we examine
the pleadings to determine whether a claim for relief has been stated. Id., ¶10. A
complaint must contain “[a] short and plain statement of the claim, identifying the
transaction or occurrence or series of transactions or occurrences out of which the
claim arises and showing that the pleader is entitled to relief.” WIS. STAT.
§ 802.02(1)(a) (2019-20).4 “[T]he sufficiency of a complaint depends on [the]
substantive law that underlies the claim made because it is the substantive law that
drives what facts must be pled.” Data Key Partners v. Permira Advisers LLC,
2014 WI 86, ¶31, 356 Wis. 2d 665, 849 N.W.2d 693.
¶16 If a claim for relief has been stated, we then determine whether any
material factual issues exist. Springer, 381 Wis. 2d 438, ¶11. Summary judgment
must be granted if the pleadings, depositions, answers to interrogatories,
admissions and affidavits establish that there is no genuine issue as to any material
3
On December 23, 2021, the Schnaubelts moved this court to supplement the record to
show that the Department of Safety and Professional Services (DSPS) had reopened an
investigation into Uecker’s conduct as a real estate broker in the transaction at issue in this case.
We denied that motion on January 7, 2022, because such information was not before the circuit
court when it made its summary judgment decision.
4
All references to the Wisconsin Statutes are to the 2019-20 version unless otherwise
noted.
7
No. 2020AP2070
fact and that the moving party is entitled to a judgment as a matter of law. WIS.
STAT. § 802.08(2).
I. Claims against Rucon
¶17 The Schnaubelts argue that contrary to the circuit court’s
conclusions, they properly pled a breach of contract claim against Rucon, or
alternatively, that they were third-party beneficiaries of a construction agreement
between Rucon and the Development Company. They contend that their
complaint met Wisconsin’s notice pleading standards by alleging “that
construction was deficient and [that] Uecker and his development company had
breached multiple promises.”
¶18 We reject the Schnaubelts’ arguments. To state a breach of contract
claim, a plaintiff must first allege facts that suggest a contract existed between the
plaintiff and the defendant. See Brew City Redev. Grp., LLC v. Ferchill Grp.,
2006 WI App 39, ¶11, 289 Wis. 2d 795, 714 N.W.2d 582. Here, the Schnaubelts’
amended complaint alleged that Rucon “agreed to construct a home on the
Property” as part of the Agreement. But the plain language of the Agreement,
which the Schnaubelts attached to their amended complaint, clearly shows that
Rucon was not a party to the Agreement and had no obligations under it. The only
parties to the Agreement were the Development Company and the Schnaubelts.
“When the allegations of a pleading are inconsistent with the terms of a document
attached as an exhibit, the terms of the document fairly construed, prevail over
averments differing in the complaint.” Friends of Kenwood v. Green, 2000 WI
App 217, ¶11, 239 Wis. 2d 78, 619 N.W.2d 271. The plain language of the
Agreement therefore prevails over any suggestion in the amended complaint that
Rucon was a party to the Agreement; it was not.
8
No. 2020AP2070
¶19 Although the Schnaubelts also suggest that Rucon “was an implicit
party to the offer to purchase” because Rucon’s drawings and specifications for
the home were incorporated into the Agreement, the plain language of the
Agreement again establishes that Rucon was not a party. The Development
Company, an actual party to the Agreement, merely chose to use Rucon’s
drawings and specifications as part of its transaction with the buyers. The
Schnaubelts also fail to identify any legal authority supporting the proposition that
a third party can become subject to a contract because another party attached the
third party’s work product to that contract. The Schnaubelts’ argument is
undeveloped, and we need not address it further. See State v. Pettit, 171 Wis. 2d
627, 646-47, 492 N.W.2d 633 (Ct. App. 1992) (we need not address undeveloped
arguments supported by no legal authority).
¶20 In addition, to the extent the Schnaubelts argue that they properly
stated a claim for breach of an oral contract with Rucon, we conclude they have
not. The Schnaubelts did not allege any facts regarding an oral agreement
between them and Rucon, and they have therefore failed to plead a necessary
“transaction or occurrence” that would give rise to a breach of an oral contract
claim. See WIS. STAT. § 802.02(1)(a); see also Data Key, 356 Wis. 2d 665, ¶31.
The Schnaubelts did explicitly allege that Rucon agreed to construct the home
under the Agreement. But, as we have already discussed, Rucon was not a party
to the Agreement; rather, its work was being used by the Development Company,
a true party to the Agreement. In short, the Schnaubelts’ amended complaint
contains no allegations that suggest that they had an oral or written contract with
Rucon.
¶21 The Schnaubelts’ third-party beneficiary argument fails for similar
reasons. “[I]n order to state a claim based on third-party beneficiary status, the
9
No. 2020AP2070
complaint must allege facts sufficient to show that the agreement that was
breached was entered into primarily and directly for plaintiff’s benefit or the
complaint must have attached a copy of the agreement that demonstrates that
purpose.” Hoida, Inc. v. M&I Midstate Bank, 2006 WI 69, ¶19, 291 Wis. 2d 283,
717 N.W.2d 17. The Schnaubelts did not attach a copy of any agreement between
Rucon and the Development Company to their amended complaint, and their
amended complaint does not allege any facts suggesting an agreement between the
Development Company and Rucon existed, let alone an agreement “entered into
primarily and directly for [the Schnaubelts’] benefit.” See id.
¶22 The Schnaubelts contend that “the only possible inference” from
their complaint was that they “were the ultimate and intended beneficiaries of
Rucon’s construction.” They fail to recognize, however, that whether they were
the intended beneficiaries of Rucon’s construction of this “spec home”—which
started long before the Schnaubelts began transacting with the Development
Company—is irrelevant.5 The relevant question here is whether they were the
intended beneficiaries of an agreement between Rucon and the Development
Company at the time those two parties entered into a contract. Because the
amended complaint failed to allege any facts suggesting that Rucon and the
Development Company entered into an agreement primarily and directly for the
Schnaubelts’ benefit, the Schnaubelts failed to allege the necessary facts for a
breach of contract claim as a third-party beneficiary. See id.
5
A “spec home” is a home “built for sale by a developer with no specific purchaser in
mind” but in anticipation that someone will indeed purchase it. Jutting v. Hendrix, 2000 SD 25,
¶3 n.2, 606 N.W.2d 140, 141 n.2; see also Big Lake Lumber, Inc. v. Security Prop. Invs., Inc.,
836 N.W.2d 359, 361 n.2 (Minn. 2013).
10
No. 2020AP2070
II. Claims against Uecker
¶23 The Schnaubelts next argue that the circuit court improperly granted
summary judgment on their claim against Uecker for violating his duties under
WIS. STAT. § 452.133(1)(a)-(b) to provide brokerage services honestly, fairly, and
with reasonable skill and care. They contend, among other things, that
Uecker: (1) used “one-sided tactics throughout the transaction that benefited him
and his various companies to the detriment of the Schnaubelts”; (2) “drafted the
offer to purchase, even though he owned and operated the seller”; (3) “took steps
to preclude Ms. Walters from reviewing the offer to purchase by withholding
information about the October 22, 2017 meeting”; and (4) “eliminated a
pre-closing inspection” from the Agreement.6 The Schnaubelts argue that whether
Uecker complied with his statutory duties is a question of fact that “should not
have been determined on summary judgment.”
¶24 As relevant to this appeal, a real estate broker must provide
brokerage services “honestly and fairly” and “with reasonable skill and care” to all
parties to a transaction. WIS. STAT. § 452.133(1)(a)-(b), (4m)(a). The parties do
not dispute that Uecker provided brokerage services when he negotiated and
drafted the Agreement and when he negotiated and drafted subsequent
amendments to the Agreement. Based on the undisputed facts, we conclude, as a
6
The Schnaubelts list additional allegations regarding Uecker’s conduct in their reply
brief. Many of these allegations, however, are taken from an unsigned and unsworn complaint
that the Schnaubelts filed with DSPS. Although that complaint is evidence of what the
Schnaubelts asserted in that complaint, the underlying allegations in the complaint are not
evidentiary facts that would be admissible as evidence. See WIS. STAT. § 802.08(3). We
therefore decline to consider those allegations to the extent they are supported only by the
Schnaubelts’ complaint to DSPS.
11
No. 2020AP2070
matter of law, that Uecker did not violate his duties to provide brokerage services
honestly, fairly, and with reasonable skill and care.
¶25 The Schnaubelts have not identified any facts from which one could
reasonably infer that Uecker was dishonest, unfair, or acted without reasonable
skill and care while negotiating the Agreement. It is undisputed that Uecker
advised the Schnaubelts to speak with Walters to determine whether they had an
“agency agreement” with her. It is also undisputed that Renae texted Walters,
describing her interactions with Uecker and stating: “I’m uncertain how to
proceed forward? He had asked me to talk to you to see what your thoughts
were?” After speaking to Renae, Walters contacted Uecker, and Uecker told
Walters that he would call her back on Monday, October 23, 2017. Before that
could occur, however, the Schnaubelts met with Uecker on Sunday, October 22
and decided to sign the Agreement.
¶26 Although the Schnaubelts contend that Uecker purposefully
excluded Walters from negotiations on October 22, 2017, they do not identify any
actions that he took to prevent Walters from attending that meeting, beyond failing
to inform her of the meeting—which the Schnaubelts could have done themselves.
Furthermore, even if the Schnaubelts did not intend to sign an offer to purchase at
the October 22 meeting, they clearly knew Walters was not present and had not
been involved in drafting or reviewing the Agreement. If they wanted Walters’
help, they could have refused to sign the Agreement on October 22 and discussed
the matter further with Walters at a later time.
¶27 The Schnaubelts may have felt pressured into signing the
Agreement, but such pressure cannot reasonably be deemed the result of any
dishonest or unfair conduct by Uecker. Rather, Uecker told the Schnaubelts that
12
No. 2020AP2070
they needed to sign the Agreement before they could make changes to the
construction plans and that they “needed to decide right away so the project
avoided delays.” The Schnaubelts have not identified any facts suggesting that
those representations were dishonest or unfair. Indeed, it is undisputed that
construction had already begun, the foundation was complete, the framing was
nearly complete if not complete, and “the electrical and utilities were being
roughed in.” The Development Company was in a position to sell the home to any
potential willing buyer that came forward at that time. Ultimately, the Schnaubelts
have failed to present any facts showing that they signed the Agreement because
of Uecker’s dishonest or unfair conduct rather than because of their desire to buy
the home and to exert control over the design of the home.
¶28 Uecker also was not dishonest or unfair by seeking provisions that
favored the Development Company in the Agreement. The beginning of the
Agreement clearly states that it was drafted by the seller’s agent and that it was not
drafted by an agent representing the buyer. Uecker therefore disclosed that he
only represented the seller, the Development Company. Moreover, as the agent
for the Development Company, Uecker had a duty to loyally represent the
Development Company’s interests—a duty that does not extend to all parties to
the transaction. See WIS. STAT. § 452.133(2)(a). That duty, in part, requires that a
real estate broker
[p]lac[e] the client’s interests ahead of the interests of
persons in the transaction who are not the firm’s clients by
not disclosing to persons in the transaction other than the
firm’s clients information or advice the disclosure of which
is contrary to the interests of a client of the firm, unless the
disclosure is required by law.
Sec. 452.133(2)(a)2. Beyond the general duty to be honest and fair, the
Schnaubelts have not identified any law requiring Uecker to provide them with
13
No. 2020AP2070
objective information and advice or to draft the Agreement in a manner that is
favorable to them. Notably, the Schnaubelts do not identify any patently
unreasonable terms in the Agreement.
¶29 Uecker also expressly disclosed in the Agreement that he had an
interest in the Development Company. Although the Schnaubelts suggest that it
was improper for him to draft the Agreement while having an interest in the
Development Company, WIS. STAT. § 452.133(3)(b) permits a real estate broker to
act in a transaction on behalf of an organization in which the broker has an interest
when all of the parties to the transaction provide their written consent. It is
undisputed that the Schnaubelts gave their written consent for Uecker to act as
such in the Agreement. They cannot now complain that Uecker acted unfairly
when he drafted the Agreement while having an interest in the Development
Company.
¶30 Finally, the Schnaubelts have not identified any facts suggesting that
Uecker acted dishonestly, unfairly, or without reasonable skill and care while
negotiating and drafting subsequent amendments to the Agreement. The
Schnaubelts signed the first amendment, which included provisions regarding an
appraisal and an escrow account, on November 15, 2017—two days before the
November 17 deadline to accept that amendment. Thus, the Schnaubelts had
ample opportunity to consider the amendment and, if necessary, to contact
someone for advice.
¶31 In addition, the subsequent three amendments all pertained to the
final purchase price, and although the Schnaubelts argue that Uecker failed to
provide detailed information regarding those amendments before executing them,
they do not identify any discrepancies or improper charges. To be sure, Michael
14
No. 2020AP2070
did allege in an affidavit that the Schnaubelts “believe [they] were overcharged at
numerous points throughout construction,” but he did not identify any specific
charges that were improper or provide evidence supporting those allegations. The
Schnaubelts’ mere belief of there being improper charges, without any evidence to
support such belief, does not create a genuine issue of material fact. See Kraemer
Bros., Inc. v. United States Fire Ins. Co., 89 Wis. 2d 555, 571, 278 N.W.2d 857
(1979) (“[I]nformation and belief does not satisfy the statutory requirement that
the affidavit be made on personal knowledge and set forth evidentiary facts as
would be admissible in evidence.”).
¶32 In sum, the Schnaubelts have not identified any evidence showing,
or permitting a reasonable inference, that Uecker violated his duties under WIS.
STAT. § 452.133(1)(a)-(b) to provide brokerage services honestly, fairly, and with
reasonable skill and care.
III. Claims against the Development Company
A. Breach of contract
¶33 The Schnaubelts argue that the circuit court erred by granting the
Development Company summary judgment on their breach of contract claim.
They contend the Development Company breached the Agreement, including the
implied duty of good faith and fair dealing, by refusing to allow for an inspection
of the home after orally agreeing to do so. The Schnaubelts acknowledge that the
Agreement did not contain an inspection contingency, but they assert that the
Development Company “orally modified” the Agreement to allow for an
inspection.
15
No. 2020AP2070
¶34 As an initial matter, we decline to address the Schnaubelts’
arguments regarding an oral modification of the Agreement because they did not
make those arguments to the circuit court. The Schnaubelts stated in their brief
opposing summary judgment that “[they] have always admitted that the
[Agreement] does not contain an inspection contingency. The [Schnaubelts’]
claim, as it relates to an inspection, was for a breach of [the Development
Company’s] implied duty of good faith.” (Emphasis added.) It is a fundamental
appellate precept that we will not “blindside [circuit] courts with reversals based
on theories which did not originate in their forum.” See Schonscheck v. Paccar,
Inc., 2003 WI App 79, ¶11, 261 Wis. 2d 769, 661 N.W.2d 476 (citation omitted).
Therefore, we will only address those theories argued to the circuit court—i.e.,
whether there were genuine issues of material fact regarding a violation of the
implied duty of good faith.7
¶35 The Schnaubelts argue that the Development Company “defeated the
Schnaubelts’ performance” by cancelling the promised inspection. They contend
that if they had been allowed to perform the inspection, then “perhaps the
construction defects the Schnaubelts identified could have been remedied ….”
They also argue that the Development Company breached its duty of good faith
7
Our decision to address only the Schnaubelts’ implied duty of good faith argument is
further supported by the evolving nature of the Schnaubelts’ “oral modification” argument. After
the Development Company argued on appeal that the statute of frauds precluded oral
modification, the Schnaubelts argued for the first time in their reply brief that the Agreement—
though subject to the statute of frauds—could be orally modified “when equity requires it,” and
that equity required enforcing the oral promise to provide an inspection. The Development
Company, however, had no opportunity to respond to those additional arguments. Even if we
addressed the Schnaubelts’ oral modification argument, we would decline to address any
argument raised for the first time in their reply brief, including equitable arguments involving oral
modification. See A.O. Smith Corp. v. Allstate Ins. Cos., 222 Wis. 2d 475, 492, 588 N.W.2d 285
(Ct. App. 1998) (we need not consider arguments raised for the first time in a reply brief).
16
No. 2020AP2070
when Uecker proposed “last-minute amendments” to the Agreement and cancelled
the inspection “in retaliation for the Schnaubelts’ refusal to sign [the fifth
amendment to the Agreement].”
¶36 The implied duty of good faith requires that a party to a contract
“will not intentionally and purposely do anything to prevent the other party from
carrying out his or her part of the agreement, or do anything which will have the
effect of destroying or injuring the right of the other party to receive the fruits of
the contract.” Tang v. C.A.R.S. Prot. Plus, Inc., 2007 WI App 134, ¶41, 301
Wis. 2d 752, 734 N.W.2d 169 (citation omitted).
¶37 The Schnaubelts have failed to identify any facts suggesting that the
Development Company intentionally did anything to prevent them from carrying
out their obligations under the Agreement. The Schnaubelts seem to suggest that
they were unable to secure financing for closing, but they do not identify any
evidence showing that the cancelled inspection, or any other action by the
Development Company, interfered with their ability to secure financing. It is
undisputed that their lender walked through the home on February 9, 2018, to
complete the appraisal. The Schnaubelts appear to imply that their lender could
not finalize their loan without the final cost of the home, but it is undisputed that
the final purchase price of the home never changed after the fourth amendment to
the Agreement was executed on January 25, 2018. Regardless, it is also
undisputed that the Agreement did not contain a financing contingency, and the
Schnaubelts have not identified any evidence suggesting that they were otherwise
unable to pay for the home without financing.
¶38 The Schnaubelts have also failed to point to any facts demonstrating
that the Development Company’s actions injured their right to receive the fruits of
17
No. 2020AP2070
the Agreement. The Schnaubelts criticize Uecker for proposing “last-minute
amendments which were contrary to their interests and reduced his obligation and
responsibility for the quality of [construction] of the home ….” The Schnaubelts
also contend that Uecker cancelled the inspection “in retaliation for the
Schnaubelts’ refusal to sign [the fifth amendment to the Agreement].” Even if we
assumed these assertions were true, such actions did not injure the Schnaubelts’
rights to purchase and receive the home that they had bargained for under the
Agreement. It is undisputed that the Schnaubelts did not sign any amendments
after January 25, 2018, and that the Agreement had no inspection contingency. To
the extent the Schnaubelts contend that the earlier amendments violated the duty
of good faith, they had no obligation to sign those amendments. Ultimately, the
Schnaubelts were in no worse position after the cancelled inspection and after the
Development Company’s subsequent actions than they were in before the parties
ever informally agreed to an inspection.
¶39 In short, the circuit court did not err in granting summary judgment
on the Schnaubelts’ breach of contract claim against the Development Company.
B. Unjust enrichment
¶40 Although the circuit court granted the Schnaubelts partial summary
judgment on their unjust enrichment claim for their actual costs of the fixtures
installed in the home, the Schnaubelts argue that genuine issues of material fact
exist regarding whether the Development Company was also “unjustly enriched by
the Schnaubelts’ design efforts.” They assert that Renae and their interior
designer provided design work and that their designs were retained by the
third-party buyer. The Schnaubelts further argue that “[h]ad [the Development
18
No. 2020AP2070
Company] sold the home absent the Schnaubelts’ design work, the purchase price
received from a third party may well have been lower.”
¶41 Unjust enrichment requires proof of three elements: (1) a benefit
conferred on the defendant by the plaintiff; (2) appreciation or knowledge by the
defendant of the benefit; and (3) acceptance or retention of the benefit by the
defendant under circumstances making it inequitable to do so. Sands v. Menard,
2017 WI 110, ¶30, 379 Wis. 2d 1, 904 N.W.2d 789. “[U]njust enrichment is based
on equitable principles, with damages being measured by the benefit conferred
upon the defendant, not the plaintiff’s loss.” Management Comput. Servs., Inc. v.
Hawkins, Ash, Baptie & Co., 206 Wis. 2d 158, 188, 557 N.W.2d 67 (1996).
¶42 The Schnaubelts’ arguments are premised almost entirely on
Michael’s affidavit submitted in support of their motion for reconsideration. That
affidavit contained new evidence discussing their design work on the home and
the third-party buyer’s alleged statement that certain design elements were kept in
the home. The Schnaubelts’ reliance on that affidavit is misplaced. “A party may
not use a motion for reconsideration to introduce new evidence that could have
been introduced at the original summary judgment phase.” Koepsell’s Olde
Popcorn Wagons, Inc. v. Koepsell’s Festival Popcorn Wagons, Ltd., 2004 WI
App 129, ¶46, 275 Wis. 2d 397, 685 N.W.2d 853. The Schnaubelts’ affidavit fails
to explain why that new evidence could not have been introduced at the original
summary judgment phase, and we therefore decline to consider that evidence here.
¶43 When considering only the evidence before the circuit court during
its summary judgment decision, it was undisputed that the Schnaubelts’ design
work “had to be changed when the [home] was subsequently purchased by a
third-party [because] the design elements had obviously been catered to [the
19
No. 2020AP2070
Schnaubelts’] tastes.” Because the Schnaubelts failed to dispute that fact during
the summary judgment phase, they failed to show that they conferred any benefit
on the Development Company. See Sands, 379 Wis. 2d 1, ¶30.
¶44 Moreover, even if we did consider the Schnaubelts’ new evidence
and assumed that they could theoretically prove that they conferred some benefit
on the Development Company with their design work, they failed to produce any
evidence showing the monetary value of such benefit. At trial, damages must be
proven with reasonable certainty—i.e., evidence sufficient to enable the fact finder
“to make a fair and reasonable approximation.” Management Comput. Servs.,
206 Wis. 2d at 189. To establish damages with enough certainty to present a
genuine issue of material fact to prevent summary judgment, a party must show
that a reasonable jury could award the party damages in an amount that is
supported by the evidence. AccuWeb, Inc. v. Foley & Lardner, 2008 WI 24,
¶19 n.8, 308 Wis. 2d 258, 746 N.W.2d 447. At most, the Schnaubelts established
that they and their designer contributed to the design of the home and that certain
design elements may have been retained in the home. They did not present any
evidence, however, suggesting that their design efforts increased the value of the
home, such that the home was worth more with their design contributions than
with the original design. Accordingly, no reasonable fact finder could award the
Schnaubelts damages on this record.
¶45 For each of the foregoing reasons, the circuit court did not err by
dismissing the Schnaubelts’ claim that the Development Company was unjustly
enriched by their design work.
20
No. 2020AP2070
IV. Leave to amend the complaint
¶46 As an alternative argument, the Schnaubelts contend that the circuit
court erroneously exercised its discretion by denying their request to amend their
complaint to allege an oral contract with Rucon or to assert a claim regarding
construction defects against the Development Company. They contend that the
court erroneously concluded that there were no genuine issues of material fact
regarding the proposed amendments to their claims.
¶47 In response, Rucon and the Development Company do not directly
address the Schnaubelts’ arguments. Instead, they argue that the circuit court did
not erroneously exercise its discretion by denying the amendment of the complaint
because: (1) the Schnaubelts’ request to amend their complaint appeared in their
brief opposing summary judgment; (2) the Schnaubelts’ request was a “fallback
position rather than an actual motion for leave to file an amended complaint”; and
(3) significant time had passed since the Schnaubelts had sufficient facts to amend
their complaint.
¶48 Although Rucon and the Development Company have identified
some relevant considerations that a circuit court might consider when addressing a
motion to amend a complaint, see Mach v. Allison, 2003 WI App 11, ¶27, 259
Wis. 2d 686, 656 N.W.2d 766 (2002), those considerations were not the basis of
the court’s decision here. Rather, the court concluded that there would be no
genuine issues of material fact following the Schnaubelts making the proposed
amendments to their claims, and that they could not prevail on those claims. In
doing so, the court concluded that the home had been completed in a timely
manner because the appraiser walked through the home on February 9, 2018, and
because the City of Appleton issued a certificate of occupancy. The court also
21
No. 2020AP2070
concluded that the Schnaubelts had not suffered any damages as a result of any
alleged construction defects because their claims, in the court’s view, only related
to the siding of the home and because the siding had a ten-year warranty. In
essence, the court concluded that the Schnaubelts’ amendments would be futile.
¶49 We review a circuit court’s decision to grant or deny a motion to
amend a complaint for an erroneous exercise of discretion. Hess v. Fernandez,
2005 WI 19, ¶12, 278 Wis. 2d 283, 692 N.W.2d 655. A court properly exercises
its discretion when it examines the relevant facts, applies a proper legal standard,
and, using a demonstrated rational process, reaches a reasonable conclusion. Id.
Where, as here, the circuit court’s decision depends on the application of summary
judgment methodology, we review the court’s application of that methodology
de novo. See Habermehl Elec., Inc. v. DOT, 2003 WI App 39, ¶12, 260 Wis. 2d
466, 659 N.W.2d 463; see also Springer, 381 Wis. 2d 438, ¶9.
¶50 We agree with the Schnaubelts that the circuit court erroneously
concluded that they could not prevail on their proposed claims as a matter of law.
In concluding that Rucon and the Development Company completed construction
in a timely manner, the court never addressed Uecker’s admission in his affidavit
that “certain things … needed to be finalized in warmer months,” including
“fixing nail holes in siding, landscaping, [and pouring the] driveway.” An issue of
fact therefore exists regarding the timely completion of construction.
¶51 Whether that issue of fact is “genuine” and “material” remains
unclear on this record. See Midwest Neurosciences Assocs., LLC v. Great Lakes
Neurosurgical Assocs., LLC, 2018 WI 112, ¶80, 384 Wis. 2d 669, 920 N.W.2d
767 (“A factual issue is ‘genuine’ if the evidence is such that a reasonable jury
could return a verdict in favor of the non-moving party. A ‘material fact’ is one
22
No. 2020AP2070
that is ‘of consequence to the merits of the litigation.’” (citations omitted)). The
circuit court never identified any provisions in the Agreement, or identified any
other law, that would permit certain projects to be completed after the closing
date. Likewise, Rucon and the Development Company have not identified any
governing law for these matters on appeal. As the parties moving for summary
judgment, Rucon and the Development Company had the burden of establishing
the absence of genuine issues of material fact. See id. Without any governing
facts or law on this point, we are unable to determine whether the unfinished
projects created a genuine issue of material fact regarding the merits of the
amended claims, and we must therefore resolve that reasonable doubt in favor of
the nonmoving parties, the Schnaubelts. See id.
¶52 In addition, the circuit court failed to consider all of the construction
defects identified by the Schnaubelts before considering whether the warranty for
the home’s siding would apply. Although the Schnaubelts’ response to an
interrogatory identified numerous concerns regarding the siding of the home, that
interrogatory also identified multiple construction defects that were unrelated to
the siding of the home, including: (1) improperly sealed window frames; (2) a
lack of flashing on lighting fixtures, electrical outlets, and a mortar joint; (3) a lack
of “kickout flashing” on gutters; (4) shingles that were not extended out far
enough over gutters; (5) an improperly sealed PVC vent; (6) the “stone veneer was
falling off the front steps”; and (7) the window trim had its backside grooves
showing.
¶53 The circuit court’s conclusion that the construction defects only
related to the home’s siding was therefore clearly erroneous. There is also no
evidence suggesting that the “ten-year full parts and labor warranty” for the
home’s siding would provide coverage for those construction defects.
23
No. 2020AP2070
Accordingly, the court erred by concluding that such warranty precluded the
Schnaubelts from proving damages.
¶54 Because the circuit court erroneously concluded that there were no
genuine issues of material fact regarding the Schnaubelts’ proposed amended
claims and that the Schnaubelts could not prevail on those claims as a matter of
law, we must conclude that the court erroneously exercised its discretion by
denying the Schnaubelts’ request to amend their complaint. We reverse the
court’s decision in that regard and remand for further proceedings consistent with
this opinion.8
By the Court.—Judgment affirmed in part; reversed in part and cause
remanded for further proceedings.
This opinion will not be published. See WIS. STAT.
RULE 809.23(1)(b)5.
8
We decline to address the factors potentially supporting the circuit court’s exercise of
discretion discussed by Rucon and the Development Company because the circuit court never
addressed those factors in exercising its discretion, instead concluding, in essence, that the
proposed amended claims would also fail on summary judgment as a matter of law. See Mach v.
Allison, 2003 WI App 11, ¶29, 259 Wis. 2d 686, 656 N.W.2d 766 (2002). The circuit court may
nonetheless consider those factors on remand should it choose to do so.