CourtListener 10109189•Skyrise Construction Group, LLC v. Global Water Center II, LLC
Skyrise Construction Group, LLC v. Global Water Center II, LLC
CourtListener 10109189Wisctapp22.01.2020
Gesamter Gesetzestext
COURT OF APPEALS
DECISION NOTICE
DATED AND FILED This opinion is subject to further editing. If
published, the official version will appear in
the bound volume of the Official Reports.
January 22, 2020
A party may file with the Supreme Court a
Sheila T. Reiff petition to review an adverse decision by the
Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10
and RULE 809.62.
Appeal No. 2019AP425 Cir. Ct. No. 2018CV7391
STATE OF WISCONSIN IN COURT OF APPEALS
DISTRICT I
SKYRISE CONSTRUCTION GROUP, LLC,
PLAINTIFF-APPELLANT,
V.
GLOBAL WATER CENTER II, LLC,
DEFENDANT-RESPONDENT.
APPEAL from an order of the circuit court for Milwaukee County:
TIMOTHY M. WITKOWIAK, Judge. Affirmed.
Before Brash, P.J., Kessler and Fitzpatrick, JJ.
¶1 FITZPATRICK, J. Global Water Center II, LLC, engaged Catcon,
Inc. to act as general contractor for a renovation project at a building owned by
Global. Catcon entered into a subcontract with Skyrise Construction Group, LLC,
for Skyrise to perform some services for that project. After several months of
No. 2019AP425
work by Skyrise, Catcon terminated its subcontract with Skyrise. Skyrise then
sued Global in the Milwaukee County Circuit Court for damages allegedly related
to Skyrise’s work on the renovation project. The circuit court granted Global’s
motion to dismiss and entered an order dismissing Skyrise’s causes of action.
Skyrise appeals, and we affirm the order of the circuit court.
BACKGROUND
¶2 The following allegations are gleaned from Skyrise’s first amended
complaint.1
¶3 Global contracted with Catcon for Catcon to serve as general
contractor for renovation of Global’s five-story building in Milwaukee.2 In turn,
Catcon entered into a subcontract with Skyrise for Skyrise to perform services of
carpentry, metal framing, and drywalling for the Project.3
¶4 Several months after Skyrise began performing services for the
Project, Catcon issued to Skyrise a written notice terminating the Subcontract due
to what Catcon contended were material contractual defaults by Skyrise. That
notice directed Skyrise to cease work and vacate the Project work site. Skyrise
refused to accept that direction from Catcon and continued sending its workers to
the Project work site. Skyrise contended that, because it disagreed with the
1
For convenience, we will refer to that pleading as “the complaint.”
2
We will now refer to that renovation work as “the Project” and the real estate where the
renovation work took place as “the Project work site” or “the site.”
3
We will now refer to the written subcontractor agreement between Catcon and Skyrise
as “the Subcontract.” Skyrise attached to the complaint a document Skyrise alleges is a copy of
the Subcontract, and Global does not dispute that allegation on appeal.
2
No. 2019AP425
reasons given by Catcon to terminate the Subcontract, the termination of the
Subcontract by Catcon was “void,” and Skyrise had the right to continue work at
the Project work site. Skyrise ultimately stopped sending its workers to the
Project work site after Global sent Skyrise written notice that Skyrise must “cease
and desist” sending its workers to the site.
¶5 Skyrise brought suit against Global in the circuit court for damages
purportedly caused by Global related to Skyrise’s work on the Project. Global
filed a motion to dismiss Skyrise’s complaint because it failed to state a claim
upon which relief can be granted. See WIS. STAT. § 802.06(2)(a)6. (2017-18).4
The circuit court granted Global’s motion, and Skyrise appeals.
¶6 We will mention other material facts in the discussion that follows.
DISCUSSION
¶7 Skyrise argues that the circuit court erred in concluding that each
cause of action in the complaint failed to state a claim upon which relief can be
granted. See WIS. STAT. § 802.06(2)(a)6. Skyrise also argues that the circuit court
erred in not granting Skyrise’s request for discovery. For the reasons discussed
below, we reject Skyrise’s arguments.
4
All references to the Wisconsin Statutes are to the 2017-18 version unless otherwise
noted.
3
No. 2019AP425
I. Standard of Review and Governing Principles
Regarding Motion to Dismiss.
¶8 Whether Skyrise’s complaint states a claim upon which relief can be
granted is a question of law which we review de novo. Data Key Partners v.
Permira Advisers, LLC, 2014 WI 86, ¶17, 356 Wis. 2d 665, 849 N.W.2d 693.
¶9 Global’s motion to dismiss requires this court to consider the legal
sufficiency of Skyrise’s complaint. Id., ¶19; see WIS. STAT. § 802.06(2)(a)6. The
pleading standard we apply is “grounded” in the requirement of WIS. STAT.
§ 802.02(1)(a) that a complaint must contain “[a] short and plain statement of the
claim, identifying the transaction or occurrence or series of transactions or
occurrences out of which the claim arises and showing that the pleader is entitled
to relief.” Sec. 802.02(1)(a); Cattau v. National Ins. Servs. of Wis., Inc., 2019
WI 46, ¶4, 386 Wis. 2d 515, 926 N.W.2d 756. “In order to satisfy …
§ 802.02(1)(a), a complaint must plead facts, which if true, would entitle the
plaintiff to relief.” Data Key, 356 Wis. 2d 665, ¶21. Put another way, a plaintiff,
such as Skyrise, must “allege facts that plausibly suggest they are entitled to
relief.” Id., ¶31.
¶10 In determining the sufficiency of a complaint, courts must “accept as
true all facts well-pleaded in the complaint and the reasonable inferences
therefrom.” Cattau, 386 Wis. 2d 515, ¶4 (citation omitted). However, “courts
cannot add facts to a complaint, and do not accept as true legal conclusions that
are stated in the complaint.” Id., ¶5. “[T]he sufficiency of a complaint depends
on substantive law that underlies the claim made because it is the substantive law
that drives what facts must be pled.” Data Key, 356 Wis. 2d 665, ¶31. To state a
4
No. 2019AP425
claim upon which relief can be granted, each element of a cause of action must be
satisfied by well-pleaded facts. See id., ¶21.
¶11 We now consider each claim in Skyrise’s complaint.
II. Tortious Interference with Contractual Relationship.
¶12 Skyrise contends that Global tortiously interfered with Skyrise’s
subcontractual relationship with Catcon. In this context, the elements of Skyrise’s
claim for tortious interference with a contract are: (1) Skyrise had a contractual
relationship with Catcon; (2) Global interfered with that contractual relationship;
(3) Global’s interference was intentional; (4) there was a causal connection
between the interference and Skyrise’s damages; and (5) Global was not justified
or privileged in the interference. See Briesemeister v. Lehner, 2006 WI App 140,
¶48, 295 Wis. 2d 429, 720 N.W.2d 531.
¶13 Skyrise’s argument can be summarized as follows.
In its Subcontract termination notice to Skyrise, Catcon directed
Skyrise to stop work on the Project and permanently remove its
workers from the Project work site.
Because Skyrise disagreed with Catcon’s bases to terminate the
Subcontract, the termination notice from Catcon was “void” and,
accordingly, “under its [S]ubcontract with Catcon, [Skyrise] had the
right (license) to enter the [Project work] site to finish the scope of
its work under its [S]ubcontract.”
Global later sent written notice to Skyrise that its workers must
“cease and desist” appearing at the Project work site, and any
5
No. 2019AP425
continued appearance at the Project work site by Skyrise personnel
would be “treated as criminal trespass.”
Skyrise stopped sending its workers to the Project work site.
“But for” the notice from Global, Skyrise would have finished its
work on the Project and been paid for that work pursuant to the
terms of the Subcontract.
¶14 Global argues that Skyrise’s cause of action fails because there is no
causal connection between its actions and any damages Skyrise alleges. More
specifically, Global asserts that Catcon’s written Subcontract termination notice to
Skyrise ended Skyrise’s license to have its workers at the Project work site and
complete work on the Project. Therefore, Global’s later notice to Skyrise to
“cease and desist” sending its workers to the Project work site could not have
interfered with the Catcon-Skyrise Subcontract because the notice from Catcon
had already ended Skyrise’s legal right to be at the site and continue work. We
agree with Global.
¶15 Before continuing our analysis, we address two preliminary matters.
First, Skyrise argues that we must accept as true its allegations in the complaint
that: (1) the Subcontract termination notice from Catcon was “void”; and (2) as a
result, Skyrise had the right to continue entering the Project work site and finish its
work on the Project. Those are legal conclusions, and legal conclusions need not
be accepted as true in determining whether to grant a motion to dismiss for failure
to state a claim. See Cattau, 386 Wis. 2d 515, ¶5; Data Key, 356 Wis. 2d 665,
¶19. Second, Skyrise’s allegations in the complaint and arguments in this court
profess to rely on the terms of the Subcontract. However, in the complaint and in
the briefing before us, Skyrise does not cite to any specific provisions of the
6
No. 2019AP425
Subcontract. In other words, Skyrise does not explain which particular portions of
the Subcontract support its contentions. Therefore, we can reject Skyrise’s
arguments regarding the terms of the Subcontract because Skyrise fails to cite to
the record in any meaningful way, and because we need not attempt to develop
arguments for a party. See State v. McMorris, 2007 WI App 231, ¶30, 306 Wis.
2d 79, 742 N.W.2d 322 (court of appeals may choose not to consider arguments
that lack proper citations to the record, and “it is not this court’s duty to develop
legal arguments on behalf of” a party). Instead, we opt to consider the merits of
the parties’ arguments.
¶16 As noted, Skyrise contends that, under the terms of the Subcontract,
it had a “license” to enter the Project work site and continue its work after
receiving the Subcontract termination notice from Catcon. The undisputed terms
of the Subcontract belie that contention. The only provision in the Subcontract
which grants Skyrise any permission to have its workers at the site is Section 4.3
which reads, in relevant part: “Unless otherwise directed by CATCON, [Skyrise]
shall … perform its Work consistent with the Project Schedule during CATCON’s
regular work hours of 7:00 a.m. to 3:30 p.m., Monday through Friday….”
(Emphasis added.) That provision of the Subcontract establishes that Catcon
“directed” and controlled when Skyrise could be at the Project work site.5
¶17 As a result, when Catcon gave the direction to Skyrise not to have its
workers at the Project work site any longer, Skyrise’s license to be at the site
ended. That proposition inevitably leads to the conclusion that Global’s “cease
5
To confirm this point, in briefing in this court, Skyrise concedes that Global, “by
contracting with general contractor Catcon, granted Catcon the right to control access to the
[Project work] site.”
7
No. 2019AP425
and desist” notice to Skyrise to vacate the Project work site could not have caused
any damage to Skyrise. Put another way, because Catcon had already validly
exercised its Subcontract authority to order Skyrise to no longer have its workers
at the Project work site, the “cease and desist” notice from Global to Skyrise can
not be a cause of Skyrise’s legal inability to be at the site, finish work on the
Project, and be paid for that work.
¶18 Another necessary premise for this cause of action is Skyrise’s
assertion that Catcon’s termination notice to Skyrise was “void” and, therefore,
that notice was not a valid basis for Catcon’s direction to Skyrise to vacate the
Project work site. However, under the terms of the Subcontract, Skyrise did not
have the option of continuing its work at the Project work site while disputing
Catcon’s termination.
¶19 Catcon terminated the Subcontract pursuant to Section 11.2 of the
Subcontract, which states:
11.2 Termination by CATCON for Cause: If
Subcontractor a) fails to supply an adequate number of
properly skilled workers, b) disregards laws, ordinances,
rules, regulations or orders of any government authority
having jurisdiction, c) fails to carry out Work in
accordance with the Subcontract Documents, and/or
d) fails to commence and continue correction of defective
or deficient Work, then CATCON, without prejudice to any
other remedies it may have, upon three (3) days written
notice to Subcontractor, may terminate this Subcontract,
and use any equipment, materials and supplies at the
Project Site furnished by or belonging to Subcontractor,
employing such workers or contractors as CATCON deems
necessary to properly and timely complete Subcontractor’s
Work.
(Emphasis added.) The Subcontract also sets out the sole path for dispute
resolution in Section 12, which states in pertinent part:
8
No. 2019AP425
12.1 Good Faith Negotiation: As a condition
precedent to arbitration, any issue, dispute, or other matter
in question arising out of or related to this Subcontract
(“Claim”) shall be subject to good faith negotiations by
senior representatives of both parties having authority to
compromise and settle the Claim. At least one (1) week
before such a meeting, the party seeking resolution of a
Claim shall submit to the other party a brief written
statement identifying the issues in dispute and itemizing the
amount of the Claim, along with supporting documentation
necessary to understand the nature of the Claim. The
parties shall share the cost of meeting at a neutral location
for these negotiations. Agreement reached as a result of
these negotiations shall be reduced to writing, signed by the
parties, and shall be enforceable as a settlement agreement
in any forum having jurisdiction thereof. If CATCON
asserts or defends a claim against the Owner that relates to
the Work of the Subcontractor, the Subcontractor shall
promptly make available to CATCON all information
relating to the portion of the claim that relates to the Work
of the Subcontractor.
12.2 Arbitration: The Subcontractor shall
participate in and be bound by any dispute resolution
process of the Prime Contract if named therein or if
CATCON requires Subcontractor’s assistance or testimony.
All other Claims that cannot be resolved by good faith
negotiations, shall, at CATCON’s sole option, be resolved
by binding arbitration.
(Emphasis added.)
¶20 As established by those provisions of the Subcontract, any disputes
between Catcon and Skyrise were to be resolved by negotiations and, if that was
unsuccessful, then by binding arbitration. The Subcontract does not include an
option, after written notice of termination of the Subcontract by Catcon, for
Skyrise to continue work at the Project work site because it disagrees with the
stated basis for the termination.
¶21 For those reasons, Skyrise did not have a license to continue to have
its workers go to the Project work site, and continue work on the Project, after
9
No. 2019AP425
receiving notice of termination of the Subcontract by Catcon. Accordingly,
Global’s “cease and desist” notice to Skyrise was not a cause of any alleged
damages to Skyrise, and Skyrise’s intentional interference with a contractual
relationship cause of action fails.
III. Unjust Enrichment.
¶22 Skyrise alleges that Global has been unjustly enriched because
Skyrise has performed subcontractor services that have improved the Project
worksite owned by Global, and Skyrise has not been paid for those services.
Global asserts that this cause of action must be dismissed because, in these
circumstances, Global, an owner, cannot be liable to Skyrise, a subcontractor,
under the theory of unjust enrichment.
¶23 In this context, the elements of an unjust enrichment cause of action
are: (1) a benefit was conferred upon Global by Skyrise; (2) there was an
appreciation or knowledge by Global of the benefit; and (3) the acceptance or
retention by Global of the benefit under these circumstances makes it inequitable
for Global to retain the benefit without payment of its value. See Puttkammer v.
Minth, 83 Wis. 2d 686, 688-89, 266 N.W.2d 361 (1978); Gebhardt Bros., Inc. v.
Brimmel, 31 Wis. 2d 581, 584, 143 N.W.2d 479 (1966). Our supreme court has
underscored that a plaintiff, such as Skyrise, must show that the defendant’s
actions are inequitable. “It is not enough to establish that a benefit was conferred
and retained; the retention must be inequitable.” Puttkammer, 83 Wis. 2d at 690.
¶24 Material to this appeal, the supreme court has also held, “we find no
equity in favor of the plaintiff when the relationship of the plaintiff to the
defendant is that of subcontractor to owner and when the evidence indicates that
the owner has either paid the general contractor for the benefits furnished or is
10
No. 2019AP425
obligated to do so.” Gebhardt, 31 Wis. 2d at 585 (emphasis added); see also
Puttkammer, 83 Wis. 2d at 690. The parties agree that Global is the owner,
Catcon is the general contractor, and Skyrise is a subcontractor. So, to survive
Global’s motion to dismiss, Skyrise must plausibly plead both of two allegations.
See Data Key, 356 Wis. 2d 665, ¶¶21, 31. First, Global has not paid Catcon for all
subcontractor services provided by Skyrise for the Project and, second, Global is
not obligated to pay Catcon for all subcontractor services provided by Skyrise for
the Project. See Puttkammer, 83 Wis. 2d at 690; Gebhardt, 31 Wis. 2d at 585.
¶25 Skyrise does not allege in its complaint, or argue on appeal, that
Global is not obligated to pay Catcon for the subcontractor services provided by
Skyrise. Without that allegation in the complaint, Skyrise’s cause of action fails
because it does not meet the pleading requirements set forth by our supreme court
for an unjust enrichment claim brought by a subcontractor against an owner.
¶26 Skyrise may argue, for the first time in its reply brief, that the
holdings of Puttkammer and Gebhardt discussed above are not controlling.
Without saying so directly, Skyrise appears to argue in its reply brief that, in
S & M Rotogravure Service, Inc. v. Baer, 77 Wis. 2d 454, 465, 252 N.W.2d 913
(1977), the Wisconsin Supreme Court eliminated the requirement of Gebhardt
that, to state a valid unjust enrichment cause of action against an owner, a
subcontractor must plead that the owner is not obligated to pay the general
contractor for the subcontractor services. We reject Skyrise’s argument for two
reasons.
¶27 As noted, Skyrise raises this argument for the first time in its reply
brief. In fact, in its initial brief in this court, Skyrise twice cited to the holding of
S & M Rotogravure as “Wisconsin courts have allowed subcontractors to recover
11
No. 2019AP425
directly from owners under [a theory of] … unjust enrichment when the owner has
not paid, and is not obligated to pay the general contractor for the work.”
(Emphasis added.) It would be inequitable to allow Skyrise to alter its argument
in reply in light of the fact that it took a directly contrary position in its initial
brief, and Global has not had a chance to respond to this new argument. See
Northern States Power Co. v. National Gas Co., Inc., 2000 WI App 30, ¶21 n.6,
232 Wis. 2d 541, 606 N.W.2d 613 (1999) (declining to consider arguments made
for the first time in a reply brief to which the respondent does not have the
opportunity to respond).
¶28 Next, we do not read the holding of S & M Rotogravure as does
Skyrise. The S & M Rotogravure opinion does not state that it is abrogating any
holding of Gebhardt as Skyrise implies. Indeed, S & M Rotogravure cited with
approval the “obligated to do so” language of Gebhardt. See S & M Rotogravure,
77 Wis. 2d at 463 (quoting Gebhardt, 31 Wis. 2d at 585). Moreover, the
following year, our supreme court in Puttkammer clearly stated the holding noted
above which included the “obligated to do so” language. See Puttkammer, 83
Wis. 2d at 690. Therefore, Puttkammer confirms Wisconsin law on this point.
¶29 Accordingly, Skyrise has failed to state a claim upon which relief
can be granted against Global for unjust enrichment.
IV. Equitable Lien.
¶30 Skyrise’s complaint requests the imposition of an equitable lien on
the Project work site owned by Global based on the subcontractor services
performed by Skyrise at that site. Under Wisconsin law, when a statutory lien is
available to a construction subcontractor such as Skyrise, an equitable lien is not
available to the subcontractor when the subcontractor has waived its statutory lien
12
No. 2019AP425
rights. See Industrial Credit Co. v. Inland G.M. Diesel, Inc., 51 Wis. 2d 520,
527, 187 N.W.2d 157 (1971); Utschig v. McClone, 16 Wis. 2d 506, 509-10, 114
N.W.2d 854 (1962). Skyrise’s complaint admits that Skyrise had available to it,
pursuant to WIS. STAT. ch. 799, a statutory lien for payment of its services.
Skyrise’s complaint concedes that, pursuant to WIS. STAT. § 779.05(1), Skyrise
granted lien waivers for those statutory liens.
¶31 Therefore, because Skyrise waived its available statutory lien,
Skyrise does not have a valid request against Global for the remedy of an equitable
lien.6
V. Quantum Meruit.
¶32 Skyrise argues that it has stated a cause of action under the theory of
quantum meruit. “To establish an implied contract [such as quantum meruit], the
plaintiff must show that the defendant requested the services and that the plaintiff
expected reasonable compensation.” Ramsey v. Ellis, 168 Wis. 2d 779, 784, 484
N.W.2d 331 (1992). Global argues that it never requested services from Skyrise
and, for that reason, Skyrise’s cause of action fails. We agree.
¶33 To repeat, the complaint alleges that Global, a limited liability
company (“LLC”), contracted with Catcon, a corporation, for Catcon to act as
general contractor for the Project. Catcon entered into the Subcontract with
6
Because an equitable lien is not available to Skyrise in these circumstances, we need
not decide a separate argument from Skyrise that Skyrise should have been granted by the circuit
court the opportunity to obtain discovery on the equitable lien claim. See Sweet v. Berge, 113
Wis. 2d 61, 67, 334 N.W.2d 559 (Ct. App. 1983) (stating that if a decision on one point is
dispositive, we need not address other issues raised).
13
No. 2019AP425
Skyrise to provide subcontractor services for the Project. There is no allegation in
the complaint that Global entered into any contract with Skyrise.
¶34 Nonetheless, Skyrise alleges in the complaint that it provided “goods
and/or services” to Global “either directly or indirectly at [Global’s] request.”
(Emphasis added.) To support that contention, Skyrise alleges that there was an
“interconnected ownership and control relationship between the principals” of
Global and Catcon because, according to Skyrise’s complaint, “[o]n information
and belief, one or more owners and/or managers of [Global] are also owners or
managers of Catcon, Inc.”7 From those allegations, Catcon argues in this court
that “the reasonable inference is that a request by Catcon” to Skyrise to provide
construction services “is also a request by Global.” For Skyrise’s quantum meruit
cause of action to survive Global’s motion to dismiss, we would have to infer that,
in effect, Global is the same entity as Catcon or that Global completely controls
Catcon for the purposes of requesting services from Skyrise. No such reasonable
inference can be made based on the allegations of the complaint.
7
We pause to consider material attributes of LLCs under Wisconsin law and why some
allegations of Skyrise cannot have any basis. “An LLC is ‘an unincorporated association of
investors, members in LLC parlance, whose personal liability for obligations of the venture is
limited to the amount the member has invested.’” Marx v. Morris, 2019 WI 34, ¶22, 386 Wis. 2d
122, 925 N.W.2d 112 (citation omitted); see also WIS. STAT. ch. 183. An LLC is formed by the
filing of articles of organization. LLC members often adopt an “operating agreement” which
becomes the principal governing document of the LLC. Marx, 386 Wis. 2d 122, ¶26. The
complaint alleges that there are “owners” or “managers” of Catcon that took certain actions. That
allegation is not plausible because Catcon, a corporation, has “shareholders” rather than “owners”
or “managers.” See id., ¶23. In a similar vein, the complaint refers to “owners” of Global, an
LLC. “Owner” is not a defined term in ch. 183 and is not a term used for a person or legal entity
with an interest in an LLC. Granted, if there is an assignment of an interest in, or a merger of, an
LLC then the term “owner” is used in ch. 183 in light of the fact that the assignment to, or
merger, may be with another entity which may not be an LLC. See WIS. STAT. §§ 183.0404(4)(a)
and 183.1205-1207. But, Skyrise does not rely on those portions of ch. 183, and we conclude that
§§ 183.0404(4)(a) and 183.1205-1207 have no applicability to this issue.
14
No. 2019AP425
¶35 First, there is nothing in the complaint to plausibly suggest that a
group of shareholders, or any one shareholder, of Catcon affiliated in some way
with Global, and has such complete control of Catcon that it is, in effect, the same
legal entity as Global for purposes of requesting subcontractor services from
Skyrise. In support of that purported inference, Skyrise makes only conclusory
arguments which we reject based on the insufficient allegations in the complaint.
¶36 Second, the complaint states no plausible allegations regarding the
management of Global, the terms of any Global “operating agreement,” or which
persons or legal entity has an ownership interest in, or control of, Global. As a
result, there is no reasonable basis to infer from the complaint that there is any
“ownership” or “control” relationship between Global and Catcon.
¶37 Based on the allegations of the complaint, there is no plausible basis
to conclude that Global requested services of Skyrise. Therefore, one of the
elements of Skyrise’s quantum meruit cause of action fails as does that cause of
action.
VI. Constructive Trust.
¶38 Skyrise’s complaint requests that a constructive trust be imposed on
Global for payment of subcontractor services performed by Skyrise for the Project.
We conclude that this request fails for the following reasons.
¶39 Skyrise apparently considers this portion of its complaint to be a
separate cause of action of “constructive trust.” However, our supreme court
recently held that a constructive trust is a remedy only and not a separate cause of
15
No. 2019AP425
action. Tikalsky v. Friedman, 2019 WI 56, ¶22 (Kelly, J., lead), ¶45 (Ziegler, J.,
concurring), 386 Wis. 2d 757, 928 N.W.2d 502.8 Accordingly, to the extent
Skyrise attempted to state a separate cause of action based on “constructive trust,”
that claim fails.
¶40 In the alternative, it may be that Skyrise intended to request the
remedy of a constructive trust based on Skyrise’s purported causes of action in the
complaint. As an example, ¶67 of the complaint reads: “Defendant Global
Water II, LLC also owes a debt, duty or obligation to Plaintiff Skyrise
Construction as alleged in this … complaint … under one or more of Skyrise’s
claims for tortuous [sic] interference, unjust enrichment, quantum meriut [sic]
and/or in equity.” Skyrise’s request for the imposition of a constructive trust must
fail because each of Skyrise’s causes of action fails for reasons noted elsewhere in
this opinion.
¶41 In sum, we conclude that the circuit court properly dismissed each of
Skyrise’s claims.
VII. Discovery on All Causes of Action.
¶42 Finally, Skyrise argues that the circuit court erred because there was
“good cause” to allow discovery on all claims in Skyrise’s complaint. We reject
this argument because Skyrise did not raise this issue in the circuit court and,
therefore, Skyrise has forfeited the opportunity to raise this issue on appeal.
8
No one, of four, writings by the Justices of the Wisconsin Supreme Court gained a
majority of the Justices. However, at least four Justices concluded that constructive trust was a
remedy and not a cause of action. Tikalsky v. Friedman, 2019 WI 56, ¶22 (Kelly, J., lead), ¶45
(Ziegler, J., concurring), 386 Wis. 2d 757, 928 N.W.2d 502.
16
No. 2019AP425
¶43 WISCONSIN STAT. § 802.06(1)(b) states that, when a motion to
dismiss for failure to state a claim is filed in the circuit court:
[A]ll discovery and other proceedings shall be stayed for a
period of 180 days after the filing of the motion or until the
ruling of the court on the motion, whichever is sooner,
unless the court finds good cause upon the motion of any
party that particularized discovery is necessary.
Under that statutory subpart, because Global filed a motion to dismiss for failure
to state a claim, Skyrise was not allowed to conduct any discovery unless Skyrise
could show “good cause” for the circuit court to conclude that certain discovery
was “necessary.”
¶44 But, Skyrise never argued in the circuit court that there was “good
cause” to allow discovery under WIS. STAT. § 802.06(1)(b). Skyrise’s argument
concerning “good cause” was raised for the first time in this appeal. Therefore, we
conclude that this argument is forfeited because the circuit court never had an
opportunity to exercise its discretion regarding any request for discovery. See
State v. Rogers, 196 Wis. 2d 817, 826-29, 539 N.W.2d 897 (Ct. App. 1995) (a
failure to raise a specific challenge before the circuit court may forfeit the right to
raise that challenge on appeal).
CONCLUSION
¶45 For the foregoing reasons, the order of the circuit court is affirmed.
By the Court.—Order affirmed.
Not recommended for publication in the official reports.
17
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.