4:22-cv-00218•BMSH I Katy TX, LLC v. Smith Seckman Reid, Inc.
Gesamter Gesetzestext
1 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION BMSH I KATY TX, LLC, Plaintiff, v. SMITH SECKMAN REID, INC., Defendant. § § § § § § § Case No. 4:22-CV-00218 JUDGE PALERMO’S REPORT AND RECOMMENDATION1 Pending before the Court is Defendant’s motion for summary judgment against Plaintiff. ECF No. 126. Defendant seeks summary judgment on all of Plaintiff’s claims, arguing that: (1) as assignee, Plaintiff is only entitled to recover the Architect’s damages, if any; (2) Plaintiff’s claims are barred by a release; (3) Plaintiff’s fraud claims are barred by Texas’ Anti-Fracturing Rule; (4) Plaintiff’s tort claims are barred by the Independent Injury Rule; (5) undisputed evidence establishes that Plaintiff’s fraudulent inducement and fraudulent concealment fail; and (6) Plaintiff’s negligence and breach of contract claims are time-barred. ECF No. 126. 2 1 The district judge to whom this case is assigned referred this matter for all pretrial purposes pursuant to 28 U.S.C. § 636. See Order, ECF No. 198. A summary judgment motion is dispositive and therefore is appropriate for a report and recommendation. 28 U.S.C. § 636(b)(1)(B). 2 Plaintiff filed a response, ECF No. 129, Defendant filed a reply, ECF No. 141, and Plaintiff filed a sur-reply, ECF No. 144. United States District Court Southern District of Texas ENTERED January 07, 2026 Nathan Ochsner, Clerk Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 1 of 55
2 After considering the briefing, the evidence, and the applicable law, the Court recommends Defendant’s motion for summary judgment, ECF No. 126, be granted as to the professional negligence claims which are time barred and denied in all other respects. I. BACKGROUND Plaintiff, the owner, contracted PRDG (“the Architect”) to design the Delaney Project (“the Project”), a senior living facility in Katy, Texas. Plaintiff’s agreement with the Architect was signed with the former owner on April 2, 2015, and the former owner subsequently assigned this agreement to Plaintiff. PRDG Agreement, ECF No. 126-7. The Architect provided Defendant with a Request for Proposal (“RFP”) and described the Project and engineering services requested—the request noted that “[m]akeup air will be preconditioned and provided as required by the Mechanical Code. Due to the climate, the design team will need to evaluate additional makeup air requirements to handle the humid environment.” Project Manager Christian Herr Affidavit, ECF No. 129-2 ¶¶ 16–21. The Architect subcontracted with Defendant for the mechanical, electrical, and plumbing design. 3 Defendant and PRDG Agreement, ECF No. 126-4. The agreement detailed the scope of Defendant’s services and stated 3 Lee Nordholm served as the engineer of record for Defendant for the mechanical design at the Project, and during the course of the Project, Darren Harvey, P.E. assumed the role as principal. Herr Affidavit, ECF No. 129-2 ¶¶ 13-14. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 2 of 55
3 that Defendant would “[p]rovide drawings and specification as stated in [the RFP]” and would perform its services in “a manner consistent with the degree of skill and care ordinarily exercised by practicing design professionals performing similar services in same locality, and under the same or similar circumstances and conditions.” ECF Nos. 129-2 ¶¶ 22-29; 129-3 ¶¶13-15. SSR was tasked with and contracted to design an HVAC system for the Project that could “handle the humid environment.” ECF No. 129-2 ¶ 44. On August 23, 2016, the Project was substantially complete, confirmed by a Certificate of Substantial Completion issued. Cert. of Completion, ECF No. 126-9. A Certificate of Occupancy was issued on October 18, 2017. Cert. of Occupancy, ECF No. 126-14. The Architect issued a letter confirming Project completion on December 11, 2017. Completion Letter, ECF No. 126-10. From January 2019 through December 2021, Plaintiff contacted Gregory Edwards, Inc., the original mechanical subcontractor for the Project, for maintenance and to make certain repairs on the Amana Vertical Terminal Air Conditioner (“VTAC”) units at the Project. Project Operator Dennis Tinker Affidavit, ECF No. 129-4 ¶5. In February 2021, Plaintiff hired Robert B. Elkins, Jr., P.E. to investigate the HVAC systems of the Project. Plaintiff’s Expert Edward Fronapfel Affidavit, ECF No. 129-5 ¶ 14. Through Elkins’ report, Plaintiff learned of defects in Defendant’s design of the HVAC systems. ECF No. 129-5 ¶¶ 17–19. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 3 of 55
4 Plaintiff raised design and construction claims related to the Project against the Architect and Defendant in arbitration. BMSH 1 Katy Tx, LLC v. Charles N. Wihte Construction Co., et al., American Arbitration Association Case No. 01-21- 0005-8435; Pl.’s Demand for Arb., ECF No. 126-5. Plaintiff alleged mechanical engineering design deficiencies against the Architect and Defendant for professional negligence, breach of contract, and breach of express warranty. ECF No. 126-5. Plaintiff also brought claims against the Architect for its contractual liability for the acts of the Architect’s subconsultants, including Defendant. ECF No. 126-5. Plaintiff settled with the Architect and signed a release of claims against the Architect. Settlement Agreement and Release, ECF No. 126-6. As part of the settlement, the Architect assigned its claims against Defendant to Plaintiff. ECF No. 126-6; Assignment, ECF No. 126-3. Plaintiff initiated the instant case against Defendant on January 1, 2022. Pl.’s Compl., ECF No. 1. During discovery in this case, Plaintiff learned that Defendant had an internal review of its designs for the Project, and in the review, identified potential humidity and mold issues. ECF No. 129-2 ¶¶ 47–49, 51–52, 54; Architect Paul Donaldson Affidavit, ECF No. 129-8 ¶¶ 7–9, 11–14; Engineer John Harris Deposition Transcript, May 20, 2024, ECF No. 129-10 at 105:17-22, 106:7-12; Fronapfel Affidavit, ECF No. 129-5 ¶¶ 25–26; Lee Nordholm Deposition Transcript, May 20, Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 4 of 55
5 2024, ECF No. 129-11 at 176:22-177:8. These concerns were not raised with the Architect or Plaintiff and so, Defendant’s design moved forward. ECF Nos. 129-2 ¶ 50; 129-8 ¶ 10; Plaintiff’s Representative Kathryn Sweeney Affidavit, ECF No. 129-3 ¶¶ 17, 18, 20; Plaintiff’s Counsel Patrick Casey’s Affidavit, ECF Nos. 129-9 ¶ 6. Plaintiff now brings claims against Defendant for professional negligence, fraud, and breach of contract. Pl.’s Amended Compl., ECF No. 105. As evidence supporting summary judgment, Defendant submitted: (1) Tim Priddy’s declaration, ECF No. 126-1; (2) Consent to Assignment of Contract, ECF No. 126-2; (3) Assignment of Contract, ECF No. 126-3; (4) Architect and Defendant agreement, ECF No. 126-4; (5) Plaintiff’s demand for arbitration, ECF No. 126-5; (6) settlement and release, ECF No. 126-6; (7) Plaintiff and the Architect’s agreement, ECF No. 126-7; (8) Edgar Stacy’s report, ECF No. 126-8; (9) Certificate of Substantial Completeness, ECF No. 126-9; (10) Project Completion Letter, ECF No. 126-10; (11) summary of resident complaints/maintenance logs, ECF No. 126- 11; (12) Plaintiff’s emails regarding VTAC equipment failures, ECF No. 126-12; (13) Plaintiff’s emails regarding defective VTAC units, ECF No. 126-13; (14) Fort Bend County Certificate of Occupancy, ECF No. 126-14; (15) Robert Skeels’ declaration, ECF No. 126-15; (16) excerpts from Lee Lyles’ deposition, ECF No. 126-16; (17) excerpt of the Project’s Schematic Design Narrative, ECF No. 126- 17; (18) excerpt from contract regarding VRF replacement, ECF No. 126-18; Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 5 of 55
6 (19) excerpts from Michael Rabena’s report, ECF No. 126-19; (20) Plaintiff’s email to Defendant regarding VRP, ECF No. 126-20; (21) excerpt of the Delaney Waco’s Schematic Design Narrative, ECF No. 126-21; (22) excerpt of the Delaney Georgetown’s Schematic Design Narrative, ECF No. 126-22; (23) excerpt of the Delaney League City’s Schematic Design Narrative, ECF No. 126-23; (24) excerpts from Chris Manning’s deposition, ECF No. 126-24; (25) excerpts from Kathryn Sweeney’s deposition, ECF No. 126-25; (26) excerpts from Michael Rabena’s deposition, ECF No. 126-26; and (27) excerpts from Lee Nordholm’s deposition, ECF No. 126-27. As evidence supporting its response, Plaintiff submitted: (1) excerpts of the scheduling conference transcript, ECF No. 129-1; (2) Christian Herr’s affidavit, ECF No. 129-2; (3) Kathryn Sweeney’s affidavit, ECF No. 129-3; (4) Dennis Tinker’s affidavit, ECF No. 129-4; (5) Edward Fronapfel’s affidavit, ECF No. 129-5; (6) Michael Rabena’s affidavit, ECF No. 129-6; (7) William McConnell’s affidavit, ECF No. 129-7; (8) Paul Donaldson’s affidavit; ECF No. 129-8; (9) Patrick Casey’s affidavit; ECF No. 129-9; (10) excerpts from John Harris’s deposition, ECF No. 129-10; (11) excerpts from Lee Nordholm’s deposition; ECF No. 129-11; (12) excerpts from Lee Lyles’ deposition, ECF No. 129-12; and (13) excerpts from Douglas Gregory’s deposition, ECF No. 129-13. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 6 of 55
7 II. LEGAL STANDARDS Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” FED. R. CIV. P. 56(a); see also Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986). The moving party bears the initial burden of identifying “the basis for its motion” and any portions of the record that “demonstrate the absence of a genuine issue of material fact.” Davis v. Fort Bend Cty., 765 F.3d 480, 484 (5th Cir. 2014) (quotations omitted). Where the moving party “bears the burden of proof on an issue,” such as a plaintiff or counter-plaintiff, it “must establish beyond peradventure all of the essential elements” for that claim to be entitled to summary judgment. Fontenot v. Upjohn Co., 780 F.2d 1190, 1194 (5th Cir. 1986) (emphasis in original). But where the moving party does not bear the burden of proof, summary judgment is available “simply by disproving the existence of any essential element of the opposing party’s claim.” Id. The burden then shifts to the non-moving party, who must “go beyond the pleadings and . . . designate ‘specific facts showing that there is a genuine issue for trial.’” Davis, 765 F.3d at 484 (quotations omitted). Summary judgment evidence “must be viewed in the light most favorable to the non-moving party, and reasonable inferences must be drawn in that party’s favor.” Warren v. Fed. Nat’l Mortgage Ass’n, 932 F.3d 378, 383 (5th Cir. 2019). Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 7 of 55
8 III. DEFENDANT’S EVIDENTIARY OBJECTIONS ARE OVERRULED. Defendant objects to various pieces of Plaintiff’s summary judgment evidence by including the following chart in its reply: ECF No. 141 at 11. The above objections are conclusory and lack specificity. 4 See Fed. Trade Comm’n v. Zaappaaz, LLC, No. 4:20-CV-2717, 2023 WL 5020618, at *4 (S.D. Tex. June 9, 2023), adopted sub nom. Fed. Trade Comm’n v. Zaappaaz, LLC, No. 4:20-CV-02717, 2023 WL 5018433 (S.D. Tex. Aug. 3, 2023) (overruling evidentiary objections that were either one-word without explanation or simply cited a rule). “Objections lacking specificity do not satisfy the requirements of Rule 103.” Id. (quoting Patton v. Meridian Sec. Ins. Co., 617 F. Supp. 3d 516, 526 (N.D. Tex. 2022)). “‘A loosely formulated and imprecise objection will not preserve error. 4 For example, the above chart does not identify the specific hearsay statements, instead citing entire paragraphs, one of which has numerous subparts. ECF No. 129-5. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 8 of 55
9 Rather, a trial court judge must be fully apprised of the grounds of an objection.’” Id. (quoting Patton, 617 F. Supp. 3d at 526 (quoting United States v. Polasek, 162 F.3d 878, 883 (5th Cir. 1998)); citing In re Slamdunk Enterprises, Inc., No. 17- 60566, 2021 WL 389081, at *24 (Bankr. E.D. Tex. Jan. 29, 2021) (“Where a hearsay objection is conclusory and scant at best, such objection is not properly made and should be summarily overruled.”)). “[I]t is not the Court’s responsibility to comb through the record to determine the basis for [Defendant’s] cursory objections or to make arguments on [their] behalf.” Id. (quoting Gilmour v. Intertek USA, Inc., No. 3:16-CV-00266, 2018 WL 3059682, at *3 (S.D. Tex. May 30, 2018), adopted, No. 3:16-CV-00266, 2018 WL 3055749 (S.D. Tex. June 20, 2018) (quoting Hoffman v. Bailey, 257 F. Supp. 3d 801, 824 (E.D. La. 2017) (overruling party’s objection where they failed to provide an explanation))). These objections are overruled. Moreover, the Court overrules Defendant’s objection that Sweeney’s affidavit is a sham affidavit. “‘[T]he court should not weigh evidence or make credibility findings’ at the summary judgment stage.” Garcia v. San Benito Consol. Indep. Sch. Dist., No. 1:21-CV-20, 2022 WL 19830659, at *8 (S.D. Tex. Nov. 14, 2022), adopted, No. 1:21-CV-020, 2023 WL 2987563 (S.D. Tex. Apr. 18, 2023) (quoting Seigler v. Wal-Mart Stores Texas, L.L.C., 30 F.4th 472, 476 (5th Cir. 2022)). The Court may not choose “which testimony to credit and which to discard” at the summary judgment stage because that would resolve disputed facts. Id. (quoting Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 9 of 55
10 Heinsohn v. Carabin & Shaw, P.C., 832 F.3d 224, 245 (5th Cir. 2016)). “In considering a motion for summary judgment, a district court must consider all the evidence before it and cannot disregard a party’s affidavit merely because it conflicts to some degree with an earlier deposition.” Id. (quoting Seigler, 30 F.4th at 477). But, under the “sham affidavit doctrine,” if it is “inherently inconsistent” with the witness’s deposition testimony, then the Court must ignore an affidavit. Id. (quoting Seigler, 30 F.4th at 477). The nonmovant cannot create a genuine issue of material fact by expressly contradicting his own prior testimony. Id. (quoting Seigler, 30 F.4th at 477). Importantly, this is a “‘high’ hurdle to clear for the movant.” Id. (quoting Seigler, 30 F.4th at 477). “The inquiry, as a whole, is aimed at gleaning whether the later affidavit is ‘so markedly inconsistent with the affiant's prior deposition as to constitute an obvious sham.’” Equal Employment Opportunity Comm’n v. Modern Group, Ltd., 725 F. Supp. 3d 577, 600 (E.D. Tex. 2024) (quoting Sabre Indus. Inc. v. Module X Sols., L.L.C., 845 F. App’x 293, 298 (5th Cir. 2021) (quoting Clark v. Resistoflex Co., 854 F.2d 762, 766 (5th Cir. 1988))); citing Winzer v. Kaufman County, 916 F.3d 464, 472 (5th Cir. 2019), cert. denied, 141 S. Ct. 85 (2020)). Defendant argues that Sweeney was deposed on an identical affidavit submitted in this briefing, and in her deposition, “Sweeney made admissions directly contradicting her affidavit testimony, including that she lacked personal knowledge Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 10 of 55
11 and that she did not know whether several statements in the affidavit were truthful.” ECF No. 141 at 11. Defendant’s objection is not specific enough—Defendant objects to a seven-page affidavit, ECF No. 129-3, but does not identify which statements should be disregarded as false—numerous statements are statements included in Defendant’s own recitation of the facts. See ECF No. 129-3. Defendant also attaches 34 pages of deposition testimony as proof of conflicting testimony. ECF Nos. 141-1, 141-2. Even so, the Court does not find that Sweeney’s affidavit is inherently inconsistent with her deposition testimony so as to render her affidavit a sham. Upon review of the affidavit and deposition testimony, the proper course is to allow the jury to evaluate Sweeney’s credibility. Defendant’s objection to Sweeney’s affidavit is overruled. IV. DEFENDANT’S MOTION FOR SUMMARY JUDGMENT SHOULD BE DENIED. In its motion, Defendant seeks summary judgment on all of Plaintiff’s claims. ECF No. 126. Defendant argues that: (1) as assignee, Plaintiff is only entitled to recover the Architect’s damages, if any; (2) Plaintiff’s claims are barred by a release; (3) Plaintiff’s fraud claims are barred by Texas’ Anti-Fracturing Rule; (4) Plaintiff’s tort claims are barred by the Independent Injury Rule; (5) undisputed evidence establishes that Plaintiff’s fraudulent inducement and fraudulent concealment fail; and (6) Plaintiff’s negligence and breach of contract claims are time-barred. ECF No. 126. The Court considers each of these arguments below. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 11 of 55
12 A. The Court Again Rejects Defendant’s Argument that Plaintiff Failed to Allege Sufficient Injury. Defendant argues that, because Plaintiff’s claims all arise by virtue of the agreement between the Architect and Defendant, Plaintiff’s damages, as the Architect’s assignee, are limited to the Architect’s damages—but Plaintiff’s complaint does not seek damage or injury to the Architect, and instead, seeks Plaintiff’s own damages. ECF No. 126 at 12–13. 5 Plaintiff responds that the Court already considered and rejected this argument when it ruled on Plaintiff’s motion for leave to file an amended complaint to add fraud claims, finding that Plaintiff’s proposed amended complaint, now the operative complaint, properly alleged injury. ECF No. 129 at 17 (quoting ECF No. 104 at 14). Plaintiff asks the Court to hold to its prior ruling and provides evidence of the Architect and Plaintiff’s injury, demonstrating that the Architect and Plaintiff relied on Defendant’s misrepresentations and nondisclosures by continuing to perform and move forward with Defendant’s designs. ECF No. 129 at 18–19. Although made in the context of a motion to leave and not a summary 5 Defendant alternatively argues that Plaintiff’s damages must be capped at the total amount of the settlement because this is the most the architect could have pursued from Defendant in a contractual indemnity claim. The Court reject this two-sentence argument from Defendant as improperly supported by argument or authority. See Judge Tipton’s Court Procedures 16(f) (“Citations. Provide pinpoint citation for all legal authority. Do the same for evidence. For instance, cite to page and line for depositions, to page and paragraph number for affidavits and pleadings, and to page and section number for contracts and similar materials. Use Bates numbers as the page reference where available.”). Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 12 of 55
13 judgment motion, the Court’s prior analysis controls, largely because Defendant argues that Plaintiff’s operative complaint fails to plead injury to the Architect, utilizing an argument more suitable for a motion to dismiss as opposed to a motion for summary judgment. ECF No. 126 at 12 (“BMSH’s complaint does not seek damage or injury to [the Architect] at all.”), 13 (“Summary judgment on all claims is appropriate because BMSH failed to plead any legally recoverable damages.”). The Court disagreed that Plaintiff’s claims failed because Plaintiff had “not alleged any injury to [the Architect],” and explained: even in light of the contract assignment, BMSH’s injury is relevant to its new fraud claims because those claims are not limited to the breach of the assigned contract but are separate and independent of those contract claims. And even if the Court’s view were limited to the contract PRDG assigned to BMSH, BMSH’s amended complaint repeatedly references how SSR’s actions caused PRDG to rely on the misrepresentations or nondisclosures, induced PRDG to continue performing under its contract with SSR and caused PRDG to move forward with SSR’s faulty designs. (See Dkt. No. 81-2 at 43–45). 6 Viewing the factual allegations in the light most favorable to BMSH, the Court agrees with BMSH that “PRDG would be able to bring these fraud claims against SSR for damages PRDG would itself owe to BMSH as a result of SSR’s design defects.” (Dkt. No. 93 at 8). And, at the very least, SSR has failed to show otherwise. Accordingly, SSR’s standing arguments fail. ECF No. 104 at 14. To the extent Defendant rehashes its motion to dismiss argument that Plaintiff failed to sufficiently plead a claim for relief, that issue has already been 6 In the order granting leave to amend, the Court addressed Plaintiff’s proposed amended complaint, ECF No. 81-2, which is now the operative complaint, ECF No. 105. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 13 of 55
14 decided and is not proper summary judgment argument. Furthermore, Plaintiff has provided sufficient evidence to demonstrate a genuine issue of material fact as to whether Defendant’s misrepresentations and nondisclosures injured both the Architect and Plaintiff. Defendant performed an internal review of the MEP drawings and the engineer who completed this review, John Harris, informed Defendant of numerous concerns and issues with the mechanical design. Herr Affidavit, ECF No. 129-2 ¶ 47 (“John Harris, an SSR engineer, was tasked with the in-house review, and he informed Nordholm and others at SSR via email on September 15, 2015” of concerns with the mechanical design); Donaldson Affidavit, ECF No. 129-8 ¶ 7 (same); Casey Affidavit, ECF No. 129-9 ¶ 5 (“On May 3, 2024, [Defendant] produced as part of its Rule 26 Disclosures an internal emails dated September 17, 2015”); Harris Deposition, ECF No. 129-10 at 100:3-7 (Harris determined the major design problems based on his experience in commercial design). Harris and Nordholm exchanged several emails on this subject, with Harris pointing out a “major design problem” and suggesting that the owner of the Project be consulted on these issues. ECF No. 129-2 ¶¶ 48, 49 (excerpts of the email exchange between Harris and Nordholm); ECF No. 129-8 ¶¶ 8, 9 (same); ECF No. 129-9 ¶ 5 (“On May 3, 2024, [Defendant] produced as part of its Rule 26 Disclosures [] internal emails dated September 17, 2015”). Harris also prepared an internal Mechanical Review on September 18, 2015, Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 14 of 55
15 memorializing his concerns and addressing “two major mechanical design issues that need to be addressed,” noting that “if the Owner directed us to utilize the current design (i.e. spaces negative), someone from the design team needs to sit down with the Owner and explain the consequences (mold issues are sure to follow in Katy TX).” ECF No. 129-2 ¶ 51 (“on September 18, 2015, Harris published an internal Mechanical Review”); ECF No. 129-8 ¶ 11 (same); ECF No. 129-9 ¶ 6 (“On April 8, 2022, [Defendant] produced as part of its Rule 26 Disclosures an internal mechanical review dated September 18, 2015”); Fronapfel Affidavit, ECF No. 129- 5 ¶¶ 25, 26 (“[Defendant] issued an internal Mechanical/Plumbing Design Review for the Project on [September 18, 2015], wherein [Defendant] advised ‘there are two major mechanical design issues that need to be addressed’ and admitted to known design failure at the Project.”); Sweeney Affidavit, ECF No. 129-3 ¶ 17 (“During the course of this litigation through the production of a document from [Defendant], [Plaintiff] learned that [Defendant] was aware of its flawed designs for the Project’s HVAC systems as early as September 18, 2015 based on an internal Mechanical/Plumbing Design Review that [Defendant] issued for the Project on that date.”); ECF No. 129-10 at 161:18-162:5 (Harris testified it would be important for the owner to understand that mold issues were sure to follow). The evidence further shows that Defendant never shared the in-house review, these emails, these concerns, or Harris’s Report with the Architect or Plaintiff. ECF Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 15 of 55
16 No. 129-2 ¶¶ 50, 52, 54 (emails, concerns, or Report never provided to Architect); ECF No. 129-8 ¶¶ 10, 12, 13, 14 (same); ECF No. 129-3 ¶ 18 (“[Defendant] did not produce the SSR Memo, or communicate the design failures noted therein, to [Plaintiff] or to [the Architect] at any point during the design and construction of the Project.”); Lyles Deposition, ECF No. 129-2 at 218:2-5 (Lyles testified that at no time did Defendant bring their concerns about the mechanical system to the Architect or Plaintiff); Nordholm Deposition, ECF No. 129-11 at 44:11-20 (Nordholm did not recollect if he spoke to the client about concerns regarding the systems), 45:6-11 (Nordholm did not recollect if he wrote to the client about concerns regarding the systems), 176:22-177:8 (Nordholm did not speak to the client about humidity control issues, or potential mold issues), 183:6-20 (Nordholm saw the client on the same day as the email from Harris, but did not speak to the client about concerns regarding the systems), 184:7-11 (Nordholm did not send the mechanical report to the Architect and would not have sent it to the owner without sending it first to the Architect). Because the Architect was unaware of these issues and Defendant did not inform the Architect of any concerns about the ventilation or the needed alternative systems, the Architect proceeded with Defendant’s design choice. ECF No. 129-2 ¶ 57 (“Because [Defendant] did not raise concerns about the risk is [sic] using exclusively natural ventilation at the Project and did not inform [the Architect] that Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 16 of 55
17 the use of alternative systems . . . were necessary to ensure that humidity issues did not impact the Project, [the Architect] relied on [Defendant’s] design and assumed it was appropriate and safe for the Project.”); ECF No. 129-8 ¶ 16 (same); ECF No. 129-10 at 178:3-11, 178:21-179:3 (Harris testified that the Architect would not be aware of his concerns unless the design engineer communicated them to the Architect). Had this information been shared with the Architect, the Architect would have notified Plaintiff and recommended Defendant redesign the Project. ECF No. 129-2 ¶ 58 (“Had the communications . . . been provided to [the Architect] or any of the issues raised in those communications been raised with [the Architect], [the Architect] would have brought these issues to [Plaintiff] and would rely on [Defendant] to make recommendations.”); ECF No. 129-8 ¶ 17 (same). Plaintiff’s experts have opined that without a DOAS, the Project would fail. ECF No. 129-5 ¶¶ 27, 28 (“a DOAS system was necessary to provide a safe environment for the Project’s residents and to provide a thermally comfortable building mechanical system that would provide the reduction of the risk of bioorganic growth (i.e., mold)”). Defendant did not make any changes to the PTAC units or the toilet exhaust fans designs following the Report. ECF No. 129-11 at 178:3-12, 178:24-179:13 (Nordholm testified no changes were made to the design plan regarding the PTAC units or exhaust fans of the toilets in the units). PRDG relied on SSR’s Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 17 of 55
18 recommendations to its detriment. ECF No. 129-2 ¶ 56, 57 (“Plaintiff relied on [Defendant’s] recommendations to its detriment.”); ECF No. 129-8 ¶ 15 (same). The above evidence demonstrates that Plaintiff and the Architect both suffered injury. Therefore, summary judgment should be denied as to Defendant’s injury argument. B. The Settlement Agreement’s Release Does Not Bar Plaintiff’s Claims. Defendant argues that because Plaintiff released all claims against the Architect, Plaintiff’s claims in this case are barred. ECF No. 126 at 13–14. Defendant argues that the release settled all claims against the Architect and Defendant. ECF No. 126 at 15. Defendant argues that, in the arbitration, Plaintiff asserted the same claims as here, against the Architect and Defendant, in addition to claims for the Architect’s breach of its obligation to indemnify Plaintiff for acts of subconsultants, including Defendant. Therefore, because the release “released all conceivable claims the subject of this suit,” the release bars Plaintiff’s claims brought here. ECF No. 126 at 16. Plaintiff contends that when deciding the motion for leave, the Court decided that Plaintiff’s settlement with the Architect did not bar the claims against Defendant, or alternatively, there were questions of fact as to the scope of the release. ECF No. 129 at 19. Plaintiff further asserts that it only settled its Architectural claims against the Architect, so as a result, the release covered only Plaintiff’s claims Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 18 of 55
19 against the Architect in the arbitration proceedings, specifically stating that the release shall not “inure to the benefit of a no-signatory,” like Defendant. ECF No. 129 at 19–20. Plaintiff points out that as part of the settlement, the Architect assigned Plaintiff any claims it had or may have against Defendant under the Architect and Defendant’s agreement. ECF No. 129 at 20. The Court agrees with Plaintiff. The Court’s prior order granting leave to amend addressed Defendant’s argument that Plaintiff settled all claims against it, finding: SSR asserts that BMSH “settled all claims, including design claims like those it makes here[,] against SSR.” (Dkt. No. 85 at 20) (emphasis added). Not so. The plain text of the settlement shows that BMSH settled “claims of construction defects, improper construction or design, . . . at the Project” against PRDG, not SSR. (Id.). And BMSH clarifies that “the PRDG settlement accounted only for PRDG’s architectural design defects, expressly excluding damages due to SSR’s faulty mechanical design—entirely separate injuries for which PRDG was liable and which BMSH did not settle or release.” (Dkt. No. 93 at 7) (emphases in original). As a result, the Court finds that BMSH has not settled its claims against SSR, and BMSH’s settlement with PRDG does not make its new fraud claims futile. Order, ECF No. 104 at 15. That ruling precludes any need for further analysis. Under Texas law, 7 “to effectively release a claim in Texas, the releasing instrument must ‘mention’ the claim to be released.” Barforough v. Nationstar Mortgage, LLC, No. 01-16-00266-CV, 2017 WL 4413430, at *3 (Tex. App.— 7 Texas law governs the settlement agreement. ECF No. 126-6 at V.7. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 19 of 55
20 Houston [1st Dist.] Oct. 5, 2017, pet. denied) (quoting Victoria Bank & Trust Co. v. Brady, 811 S.W.2d 931, 938 (Tex. 1991)). “Any claims not clearly within the subject matter of the release are not discharged.” Id. (citing Brady, 811 S.W.2d at 938; Sanus, 837 S.W.2d at 197). Further, “[a]lthough general releases are narrowly construed, broadly worded general releases are enforceable as long as the claim in question is included within the wording of the release.” Tempur-Pedic N. Am., LLC v. Mattress Firm, Inc., No. CV H-17-1068, 2018 WL 4108026, at *2 (S.D. Tex. July 23, 2018) (quoting Southmark Corp. v. F.D.I.C., 142 F.3d 1279, 1998 WL 224537, at *3 (5th Cir. 1998)). “However, a general release that is not limited to a specific cause of action or occurrence, and broadly releases all claims and causes of action between two parties, is valid and enforceable.” Id. (quoting Southmark Corp. v. F.D.I.C., 142 F.3d 1279, 1998 WL 224537, at *4). “When a contract’s meaning is unambiguous, [the Court’s] task is to determine the parties’ intentions as expressed in the written instrument.” Gabbanelli Accordions & Imports, LLC v. Hermes Music Co., 398 F. Supp. 3d 156, 161 (S.D. Tex. 2019) (quoting Apache Deepwater, LLC v. McDaniel Partners, Ltd., 485 S.W.3d 900, 906 (Tex. 2016)). The Court “must interpret contracts holistically,” meaning that “[n]o single provision of a contract is to be read alone; rather, ‘all provisions are “considered with reference to the whole instrument.”’” Id. (quoting Apache Deepwater, 485 S.W.3d at 906 (quoting J.M. Davidson, Inc. v. Webster, 128 Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 20 of 55
21 S.W.3d 223, 229 (Tex. 2003))). The Court must construe contracts “from a utilitarian standpoint, bearing in mind the particular business activity sought to be served.” Id. (quoting Apache Deepwater, 485 S.W.3d at 906–07 (quoting Lenape Res. Corp. v. Tenn. Gas Pipeline Co., 925 S.W.2d 565, 574 (Tex. 1996))). Here, the settlement agreement stated that Plaintiff: releases, acquits and forever discharges [the Architect] for any and all claims, demands, actions or causes of action of whatever kind or character, to the extent such claims are known or could have been known which [Plaintiff] may now have or hereafter have against [the Architect], growing out of or in any way connected with or which may have arisen or can arise as a result of [Plaintiff]’s purchase, occupancy, or claims of construction defects, improper construction or design, foundation and/or settlement, structural defects, warranty claims, warranty work or repairs at the Project. This Agreement and Release specifically includes, but is not limited to, all claims brought or claims that could be have been brought in the Action by BMSH against PRDG . . . . Nothing contained in this Agreement shall inure to the benefit of a non-signatory to this Agreement unless identified in Paragraphs I.A through B. of this Agreement. ECF No. 126-6 at III.2. As seen above, the only released claims were Plaintiff’s claims against the Architect and the agreement was not intended to release or benefit Defendant, a non-signatory. See id. Furthermore, other provisions of the settlement agreement indicate that Plaintiff did not release claims against Defendant—maintaining and then pursuing those claims were obviously an important part of the bargain between Plaintiff and the Architect. The terms of the settlement agreement set the assignment of the Architect’s claims against Defendant to Plaintiff as a condition precedent, stating Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 21 of 55
22 that the settlement was not effective “unless and until” “binding if and only if” the assignment was effective. ECF No. 126-6 at III.1. 8 With the release of those claims, this provision would be meaningless. Additionally, the settlement agreement contained a provision for the assignment of the Architect’s claims against Defendant, stating that: [f]or the consideration set forth in this Agreement . . . , [the Architect] irrevocably assigns, transfers and conveys to [Plaintiff] all rights, title and/or interest to any claims, demands, causes of action [], damages and/or rights and obligations that [the Architect] may have or have against [Defendant] including claims under the SSR Agreement for the Project. . . . ECF No. 126-6 at III.8. If the settlement agreement and release released the Architect’s claims against Defendant as Defendant suggests, then the above provision is also meaningless. 9 8 Notably, Defendant consented to the assignment. ECF No. 126-6 at 12. As a condition precedent to the consent to the assignment, Plaintiff, the architect, and Defendant agreed “that any claim or cause of action against SSR arising out of or relating in any way to the SSR Contract and the Katy Senior Living Facility must be brought in litigation only, not arbitration, and “[b]efore bringing any such lawsuit against SSR, PRDG and BMSH agree to dismiss SSR as a party from the Arbitration and bear all costs that the AAA may charge against SSR.” ECF No. 126-6 at 1.b. 9 The recitals read together also support the reading that the settlement agreement did not release Plaintiff’s current claims against Defendant. The recitals explain that the architect hired Defendant pursuant to the SSR Agreement to provide mechanical, electrical, plumbing and fire protection engineering services and construction observations for the Project. The architect also promised to the owner (who later assigned the PRDG Agreement to Plaintiff) that the architect “will be fully responsible for the acts, errors, and omissions of its Subconsultants and shall fully indemnify, defend, and save harmless Owner, its agents, employees, and assigns from any and all claims which arise on account of Services rendered by Consultant’s Subconsultants.” ECF No. 126-6 at II. When read as a whole, these recitals provide necessary context for the relationship between Plaintiff, Defendant, and the architect, why the architect assigned claims to Plaintiff, and why Plaintiff would want the assignment as part of its settlement with the architect. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 22 of 55
23 Accordingly, the settlement agreement is unambiguous and demonstrates that Plaintiff’s instant claims against Defendant were not released in the settlement agreement. 10 C. Texas Anti-Fracturing Rule Does Not Bar Plaintiff’s Fraud Claims. Defendant argues that the Texas anti-fracturing rule, which “bars plaintiffs from recharacterizing a professional negligence claims as any other claim,” bars Plaintiff’s fraud claims. ECF No. 126 at 16. Plaintiff responds that its fraud claims are not barred because they are not repackaged professional malpractice claims— the fraud claims do not concern Defendant’s “failure to exercise its professional standard of care,” and the harm to Plaintiff stems from Defendant’s intentional withholding of knowledge of serious mechanical design defects. ECF No. 129 at 23. As an initial matter, the Court finds that Defendant’s briefing is sparse, which waives this argument. See United States v. Scroggins, 599 F.3d 433, 446–47 (5th Cir. 2010) (party who fails to adequately brief argument is deemed to have waived it); Flores-Ordones v. Holder, 348 F. App’x 12, 13 (5th Cir. 2009) (failure to adequately brief an argument constituted abandonment); Burton v. Comm’s of Social Security, No. 3:20-cv-266, 2021 WL 3674472, at *2 n.11 (N.D. Miss. Aug. 18, 2021) (“[F]ailure to brief an argument in the district court waives that argument in that 10 Because the Court finds that the contract is unambiguous, it need not reach the parties’ arguments about parol evidence. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 23 of 55
24 court.”) (internal quotation marks omitted) (quoting Magee v. Life Ins. Co. of N. Am., 261 F. Supp. 2d 738, 748 n.10 (S.D. Tex. 2003)). Even so, the anti-fracturing rule does not bar Plaintiff’s fraud claims. In Texas professional malpractice cases, the “anti-fracturing rule” “limits the ability of plaintiffs to recharacterize a professional negligence claim as some other claim—such as fraud or breach of fiduciary duty—in order to obtain a litigation benefit like a longer statute of limitations.” Pitts v. Rivas, 709 S.W.3d 517, 521 (Tex. 2025). “Under the anti-fracturing rule, if the crux or gravamen of the plaintiff’s claim is a complaint about the quality of professional services provided by the defendant, then the claim will be treated as one for professional negligence even if the petition also attempts to repackage the allegations under the banner of additional claims.” Id. at 524 (citing J.A. Green Dev. Corp. v. Grant Thornton, LLP, No. 05-15-00029-CV, 2016 WL 3547964, at *8 (Tex. App.—Dallas June 28, 2016, pet. denied); Won Pak v. Harris, 313 S.W.3d 454, 457 (Tex. App.—Dallas 2010, pet. denied)). Stated another way, “if the ‘gist of a client’s complaint’ or ‘the real issue’ is that the professional failed to exercise the degree of care, skill, or diligence that professionals of ordinary skill and knowledge would exercise, the anti-fracturing rule requires the claim to be litigated as one for professional negligence, and the plaintiff may not re- label the allegations under a different claim to obtain a litigation advantage.” Id. (citing Riverwalk CY Hotel Partners, Ltd. v. Akin Gump Strauss Hauer & Feld, LLP, Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 24 of 55
25 391 S.W.3d 229, 235 (Tex. App.—San Antonio 2012, no pet.); Kimleco Petroleum, Inc. v. Morrison & Shelton, 91 S.W.3d 921, 924 (Tex. App.—Fort Worth 2002, pet. denied)). “Importantly, the anti-fracturing rule does not categorically bar a client from pursuing multiple causes of action against a professional, including claims for fraud or breach of fiduciary duty,” but instead “prohibits plaintiffs from attaching these labels, and others like them, to their allegations when the gravamen of the allegations is that the defendant failed to exercise the requisite degree of care or skill in the provision of professional services.” Pitts, 709 S.W.3d at 525. So, “if the gravamen of the claim ‘goes beyond what traditionally has been characterized as [professional] malpractice,’ then additional claims beyond professional negligence may be viable.” Id. (quoting Duerr v. Brown, 262 S.W.3d 63, 70 (Tex. App.—Houston [14th Dist.] 2008, no pet.)). Plaintiff’s fraud claims are not barred by the anti-fracturing rule because the gravamen of these claims move past professional malpractice and into deceptive conduct. See Pitts, 709 S.W.3d at 525–26 (“Thus, if a plaintiff raises a genuine fact issue on the elements of additional claims that truly extend beyond the scope of what has traditionally been considered a professional negligence claim, then the additional claims may survive summary judgment under the anti-fracturing rule.”); see also Latham v. Castillo, 972 S.W.2d 66, 69 (Tex. 1998)). Plaintiff has not tried to artfully Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 25 of 55
26 recast negligence claims as fraud claims to gain a litigation advantage. The gravamen of Plaintiff’s fraud claim is Defendant was aware of design defects in the planning stages of the Project but withheld this information to encourage Plaintiff to continue with the design plans. ECF No. 105. Plaintiff’s fraud claims arise from Defendant withholding knowledge of the design defects before implementing plans—fraud—and not Defendant’s plan having design defects— professional negligence. Id. Pitts is inapposite to this case. In Pitts, the Texas Supreme Court found that the gravamen of the plaintiffs’ fraud claim was “that the Accountants failed to provide competent accounting services,” made accounting errors, overstated their competence, and attempted to hide their errors from the plaintiffs. The Texas Supreme Court found these claims were barred by the anti-fracturing rule because they were professional malpractice allegations and the harm to the plaintiffs stemmed from the accounting errors, not the alleged misrepresentations. See Pitts, 709 S.W.3d at 526–27. As noted above in the Court’s discussion on injury, the evidence at the very least raises a fact question as to whether Defendants knowingly and intentionally withheld its knowledge of the design defects to deceive Plaintiff into moving forward with its faulty plans. Defendant’s deception harmed Plaintiff—had Plaintiff known of the design defects, it would not have moved forward with the design plan Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 26 of 55
27 and at best, would have required Defendant to return to the drawing board. The anti- fracturing rules do not bar Plaintiff’s fraud claims. See Pitts, 709 S.W.3d at 526–27. D. The Economic Loss Rule Does Not Bar Plaintiff’s Tort Claims. Defendant argues that Plaintiff’s negligence and fraud claims are barred by the economic loss rule. ECF No. 126 at 17. Defendant argues that Plaintiff’s tort claims do not arise under a duty independent of the agreement and seek identical damages for identical injuries in tort and in contract. ECF No. 126 at 18. Defendant continues that the “primary rationale” for applying the economic loss rule, contractual allocation of risk, is satisfied here because the risk of loss was redressable in Plaintiff’s breach of contract claims against the Architect, who had agreed to indemnify and hold Plaintiff harmless from the acts or omissions of subconsultants like Defendant. ECF No. 126 at 19. “As a general rule, the failure to perform the terms of a contract is a breach of contract, not a tort,” and therefore, Texas’s economic loss rule “generally precludes recovery in tort for economic losses resulting from a party’s failure to perform under a contract when the harm consists only of the economic loss of a contractual expectancy.” Curtis v. Cerner Corp., 621 B.R. 141, 171 (S.D. Tex. 2020) (quoting Heller Fin., Inc. v. Grammco Computer Sales, Inc., 71 F.3d 518, 527 (5th Cir. 1996); Chapman Custom Homes, Inc. v. Dallas Plumbing Co., 445 S.W.3d 716, 718 (Tex. 2014); citing Lamar Homes, Inc. v. Mid-Continent Cas. Co., 242 S.W.3d 1, 12 (Tex. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 27 of 55
28 2007); LAN/STV v. Martin K. Eby Constr. Co., 435 S.W.3d 234, 235–36 (Tex. 2014)). Because a party’s actions may breach duties in tort or contract or both, “[t]he nature of the injury most often determines which duty or duties are breached”— “[w]hen the injury is only the economic loss to the subject of a contract itself the action sounds in contract alone.” Id. (quoting Sw. Bell Tel. Co. v. DeLanney, 809 S.W.2d 493, 495 (Tex. 1991) (quoting Jim Walter Homes, Inc. v. Reed, 711 S.W.2d 617, 618 (Tex. 1986)); citing Lamar Homes, 242 S.W.3d at 12–13 (“In operation, the rule restricts contracting parties to contractual remedies for those economic losses associated with the relationship, even when the breach might reasonably be viewed as a consequence of a contracting party’s negligence.”). However, “[a] party states a tort claim when the duty allegedly breached is independent of the contractual undertaking and the harm suffered is not merely the economic loss of a contractual benefit.” Id. (emphasis in original) (quoting Chapman Custom Homes, 445 S.W.3d at 718). In other words, the economic loss rule does not apply when the “duty was independent of any obligation in the [contract], and the alleged damages caused by the breach of that duty extended beyond the economic loss of any anticipated benefit under the . . . contract.” Hilburn v. Storage Tr. Props., LP, 586 S.W.3d 501, 508 (Tex. App.—Houston [14th Dist.] 2019, no pet.). To determine “whether a tort claim is merely a repackaged breach of contract Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 28 of 55
29 claim,” the Court considers: “(1) whether the claim is for breach of duty created by contract, as opposed to a duty imposed by law; and (2) whether the injury is only the economic loss to the subject of the contract itself.” Curtis, 621 B.R. at 171 (quoting Stanley Indus. of S. Fla., Inc. v. J.C. Penney Co., No. 3:05-CV-2499L, 2006 WL 2432309, at *5 (N.D. Tex. Aug. 18, 2006)). “The burden is on the plaintiff to establish evidence of an independent injury.” Id. at 171–72 (quoting McDaniel v. JPMorgan Chase Bank, N.A., No. 1:12-CV-392, 2012 WL 6114944, at *7 (E.D. Tex. Dec. 10, 2012) (citing Esty v. Beal Bank S.S.B., 298 S.W.3d 280, 302 (Tex. App.—Dallas 2009, no pet.), Sterling Chems., Inc. v. Texaco Inc., 259 S.W.3d 793, 797 (Tex. App.—Houston [1st Dist.] 2007, no pet.)). 1. The economic loss rule does not bar Plaintiff’s negligence claims. Plaintiff alleged a claim for professional negligence against Defendant. ECF No. 105. Plaintiff alleges that independent of any contractual duties, Defendant had a duty to conduct its operations and perform its services related to the Project’s design with due care, caution, and skill, and to exercise reasonable care in its retention of design professionals, consultants, subconsultants and employees, and in its supervision, inspection, design, observations and/or quality control relating to the Project. ECF No. 105 ¶¶ 228–29. Plaintiff alleged that Defendant’s breach of these duties caused Plaintiff “resultant and consequential property and other damages.” ECF No. 105 ¶ 231. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 29 of 55
30 “One exception to the economic loss rule is professional malpractice, or negligence.” Paradyme Asset Mgmt., LLC v. Figurd, LLC, No. SA-24-CV-00737- XR, 2025 WL 515319, at *4 (W.D. Tex. Jan. 20, 2025) (citing LAN/STV v. Martin K. Eby Const. Co., 435 S.W.3d 234, 243–44 (Tex. 2014)). As “[c]ertain professional relationships create duties separate and independent from a contract between a professional and his or her client,” they “can form the basis for negligence claims against professionals, including for services performed under a contract.” Id. (quoting Dunn v. Marine, No. H-12-CV-03643, 2015 WL 12778390, at *13 (S.D. Tex. Oct. 13, 2015) (citing LAN/STV, 435 S.W.3d at 243–44))). “The exception recognizes that standards governing the professions that ‘are deeply developed and their application uniform and well-settled,’ reduc[e] the need to defer to the parties’ contractual allocation of duties and risk,” and in situations like this, a party “can recover purely economic losses.” Id. (quoting Dunn, 2015 WL 12778390, at *13 (citing LAN/STV, 435 S.W.3d at 244)). The exception has not been extended to “allow nonparties to a contract between a contracting party and a professional to recover economic losses caused by the professional’s negligent performance of the contract.” Id. (quoting Dunn, 2015 WL 12778390, at *13). Instead, “[a] nonparty to a contract may recover for a professional’s negligence only if the professional directed its actions to a ‘known party for a known purpose.’” Id. (quoting Dunn, 2015 WL 12778390, at *13 (citing Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 30 of 55
31 LAN/STV, 435 S.W.3d at 245)). This “avoid[s] . . . unlimited and uncertain liability for economic losses in cases of professional mistake.” Id. (quoting Grant Thorton LLP v. Prospect High Income Funds, Ltd., 314 S.W.3d 913, 920 (Tex. 2010)). Defendant argues that the professional malpractice exception to the economic loss rule does not apply here because Plaintiff and Defendant do not have a direct contractual relationship and the later assignment only created “privity after the fact.” ECF No. 126 at 19–20. Defendant contends that it may have an independent duty to the Architect, it does not owe an independent duty to Plaintiff. ECF No. 126 at 20. Defendant also contends that there is no “injury independent of the contractual undertaking.” ECF No. 126 at 18. Plaintiff responds that “[o]nce privity was established through the valid assignment, [Plaintiff] as assignee is entitled to bring any and every claim that [the Architect] as assignor could bring against the obligor,” Defendant, and so the professional malpractice exception applies here. ECF No. 129 at 24–25. Plaintiff continues that it seeks property damages beyond the mere loss of a contractual benefit. ECF No. 129 at 25. Defendant is a licensed professional engineering firm and therefore falls under the professional malpractice exception to the economic loss rule. See Dunn v. Marine, No. CV H-12-03643, 2015 WL 12778390, at *14 (S.D. Tex. Oct. 13, 2015) (“Licensed professional engineers, such as Edward Turner, and the firms at which they practice, such as AMASE, fall within the professional malpractice exception to Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 31 of 55
32 the economic loss rule.”) (citing Tex. Civ. Prac. & Rem. Code § 150.001–003 (governing negligence suits against “licensed or registered professionals,” defined to include a “licensed professional engineer or any firm in which such licensed or registered professional practices”); LAN/STV, 435 S.W.3d at 244 & n.42 (citing Tex. Civ. Prac. & Rem. Code § 150.001–03 in discussing “negligence actions against other professionals”)). Defendant owed a duty to the Architect outside of the agreement. See id. As Plaintiff established, Plaintiff now stands in the shoes of the Architect by virtue of the assignment. See In re Enron Corp. Sec., Derivative & ERISA Litig., 279 F.R.D. 395, 405 n. 12 (S.D. Tex. 2011) (“An assignment functions as a contract between assignor and assignee and is therefore interpreted according to the law of contracts. In a valid assignment, the assignee steps into the shoes of the assignor and is considered under the law to have suffered the same injury as the assignors and have the same ability to pursue the claims.”) (quoting Southwestern Bell Tel. Co. v. Mktg. on Hold Inc., 308 S.W.3d 909 (Tex. 2010)). Defendant argues that, because the assignment took place after the claims accrued, Plaintiff cannot rely on this exception. Defendant has not provided any authority that the timing of an assignment is relevant to the application of the exception. ECF No. 126 at n.6. Moreover, Defendant arguably directed its actions to a known party, Plaintiff as the owner of the project Defendant designed for, for a known purpose. As pointed out in Dunn, cited by Defendant: Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 32 of 55
33 For example, if a company contracted with an accounting firm to prepare financial statements, the firm may be liable to a current trade creditor of the company for negligent misrepresentations in the financial statements if the firm knew that the creditor would rely on the statements. Blue Bell, Inc. v. Peat, Marwick, Mitchell & Co., 715 S.W.2d 408, 412 (Tex. App.—Dallas, 1986, writ ref’d n.r.e.). But the accounting firm would not be liable for negligently preparing financial records to potential investors who had no previous connection to the corporation and were not known to the accounting firm. Grant Thornton, 314 S.W.3d. at 921, 923–26. Dunn, 2015 WL 12778390, at *14. Here, Plaintiff, the owner of the project, hired the architect, who then hired Defendant to provide mechanical designs for the project. In other words, Defendant was aware that it was hired to draft designs for Plaintiff. This case is distinguishable from LAN/STV. In LAN/STV, the Dallas Area Rapid Transit Authority (“DART”) contracted with an Architecture firm to draw up plans for a light rail system and then independently contracted with a construction company to build the system. LAN/STV, 435 S.W.3d at 236. The construction company built the system based on the Architecture firm’s plans, but the plans were faulty and increased the construction company’s costs of performing. Id. at 236–37. The construction company sued the Architecture firm for negligently preparing the plans. Id. at 237. The Texas Supreme Court acknowledged that the Architecture firm could fall within the professional exception to the economic loss rule, but the exception did not apply because the construction company was a stranger to the Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 33 of 55
34 Architectural firm’s contract with DART and did not “choose the Architect, or instruct it, or pay it—the Architecture firm had not directed its contract performance to the construction company. Id. at 244, 247. Here, Plaintiff is not a stranger to the agreement—as discussed above, Plaintiff stepped into the shoes of the Architect, with whom Defendant contracted. Accordingly, Defendant owed Plaintiff a duty as a firm of licensed professional engineers. Furthermore, permitting Plaintiff to recover against Defendant is consistent with the rationale and policy behind the economic loss rule—Defendant’s concerns about liability to third parties is not present here. 11 2. The economic loss rule does not bar Plaintiff’s fraud claims. Defendant argues that the economic loss rule bars Plaintiff’s fraud claims. ECF No. 126 at 21. 12 Defendant argues that the source of duty for Plaintiff’s fraud 11 Insofar as Defendant argues Plaintiff’s requested damages fail to establish independent injury, the Court is unconvinced. Plaintiff has claimed losses suffered that were not the subject of the agreement between the architect and Defendant. See Constance Joy II, LLC v. Stewart & Stevenson FDDA LLC, No. 4:20-CV-02967, 2024 WL 4008094, at *7 (S.D. Tex. Aug. 30, 2024) (“Just like the fire in Scharrenbeck and the flooding in Chapman, the FDDA technician's duty not to flood the ship was “independent of the contractual undertaking” in the May 29, 2018 SRO.”) (citing Montgomery Ward & Co. v. Scharrenbeck, 204 S.W.2d 508 (Tex. 1947); Chapman Custom Homes, Inc. v. Dall. Plumbing Co., 445 S.W.3d 716, 718 (Tex. 2014) (per curiam)). Plaintiff has shown that it suffered property damage outside of the contract undertaking between Defendant and the architect. See Fronapfel Affidavit, ECF No. 129-5 ¶¶ 21–24; Rabena Affidavit, ECF No. 129- 6 ¶¶ 6–9. 12 Plaintiff raises a fraudulent inducement claim and a fraudulent concealment claim against Defendant. ECF No. 105. Regarding fraudulent inducement, Plaintiff alleged that Defendant knowingly misrepresented that the mechanical systems for the Project would include makeup air that is preconditioned and that the design team would evaluate additional makeup air requirements to handle the humid environment in its request for proposal. ECF No. 105 ¶¶ 234–36. Plaintiff alleges that Defendant intended for Plaintiff to rely, and Plaintiff did rely, to permit the Project to Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 34 of 55
35 claims arises from Defendant’s agreement with the Architect and Plaintiff only seeks contractual expectancy duties. ECF No. 126 at 21. Plaintiff responds that the Court has already analyzed and rejected Defendant’s arguments when deciding the motion for leave to amend discussed above, finding that Plaintiff seeks more than benefit of the bargain damages and Defendant had an independent duty to not commit fraud. ECF No. 129 at 26. As the Court previously found, “[b]oth [fraud] claims involve a duty separate from the contractual duties because there is “an independent legal duty not to commit the intentional tort of fraud.” Order, ECF No. 104 at 11 (quoting Eastman Chem. Co. v. Niro, Inc., 80 F.Supp.2d 712, 717 (S.D. Tex. 2000) (emphasis in original); Corporativo Grupo R SA de C.V. v. Marfield Ltd., Inc., No. 4:19-CV-01963, 2021 WL 5161736, at *3 (S.D. Tex. Sept. 16, 2021) (“[P]arties to a contract have an independent duty not to commit the intentional tort of fraud.”)). Indeed, Plaintiff’s “intentional fraud claims concern a separate, independent duty under Texas common law rather than a duty imposed solely under the contract.” Id. (emphasis in original) (citing Eastman Chem. Co., 80 F.Supp.2d at 717 (noting that the economic-loss rule proceed. ECF No. 105 ¶ 237. Plaintiff alleged that its reliance on the misrepresentation caused physical harm to the Project, “as well as economic loss to Plaintiff requiring repairs.” ECF No. 105 ¶ 240. Regarding fraudulent concealment, Plaintiff alleged that Defendant knew about design defects that it was obligated to disclose to Plaintiff but failed to and had the intent that Plaintiff rely on the non-disclosure and move forward with the Project. ECF No. 105 ¶¶ 245–47. Plaintiff relied on the non-disclosure, which caused physical harm to the Project and economic loss to Plaintiff, requiring repairs at the Project. ECF No. 105 ¶¶ 247–49. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 35 of 55
36 will only preclude a tort cause of action when “the claim is for breach of duty created solely by contract rather than a duty imposed by law” (emphasis in original))). Defendant has not pointed to a change in authority that should alter this finding— “parties to a contract [still] have an independent duty not to commit the intentional tort of fraud.” Corporativo, 2021 WL 5161736, at *3 (quoting United Health Prod., Inc. v. Animal Health Int'l, Inc., No. 4:20-CV-788, 2021 WL 930682, at *5 (S.D. Tex. Mar. 11, 2021)). Further, as the Court previously found, Plaintiff pursues damages outside the economic loss of a contractual benefit. Plaintiff seeks exemplary damages for its fraud claims. Order, ECF No. 104 at 11 (referring to mechanical design services and exemplary damages); see Am. Compl., ECF No. 105 at 45 (“an award of exemplary damages pursuant to Tex. Civ. Prac & Rem. Code § 41.008(b)); see also Gilbreath v. Horan, 682 S.W.3d 454, 507–08 (Tex. App.—Houston [1st Dist.] 2023, pet. denied), reh’g denied (Apr. 20, 2023) (“Exemplary damages may be awarded ‘only if the claimant proves by clear and convincing evidence that the harm with respect to which the claimant seeks recovery of exemplary damages results from: (1) fraud; (2) malice; or (3) gross negligence.’”) (quoting Tex. Civ. Prac. & Rem. Code § 41.003(a)). The evidence shows that exemplary damages and other punitive measures are not mentioned anywhere in the agreement between Defendant and the Architect. ECF No. 126-4. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 36 of 55
37 Thus, the economic loss rule does not bar Plaintiff’s fraud claims. E. Evidence Establishes a Genuine Issue of Material Fact As To Plaintiff’s Fraud Claims. Defendant argues that undisputed evidence negates elements of Plaintiff’s fraud claims. ECF No. 126 at 23. Plaintiff responds that its fraud claims cannot be determined on summary judgment because Plaintiff’s evidence creates a genuine issue of material fact on the elements of their fraud claims. ECF No. 129 at 26. “The basic elements of fraud are[:] (1) a material misrepresentation, (2) made with knowledge of its falsity or asserted without knowledge of its truth, (3) made with the intention that it should be acted on by the other party, (4) which the other party relied on, and (5) which caused injury.” Sugg v. Midwestern Univ., No. 2:20- CV-00274, 2022 WL 19039612, at *6 (S.D. Tex. Dec. 27, 2022), aff’d, 105 F.4th 345 (5th Cir. 2024) (citing Anderson v. Durant, 550 S.W.3d 605, 614 (Tex. 2018)). 1. Plaintiff’s fraudulent concealment claims should survive summary judgment. “Fraud by non-disclosure, a subcategory of fraud, occurs when a party has a duty to disclose certain information and fails to disclose it.” Bombardier Aerospace Corp. v. SPEP Aircraft Holdings, LLC, 572 S.W.3d 213, 219 (Tex. 2019) (citing Schlumberger Tech. Corp. v. Swanson, 959 S.W.2d 171, 181 (Tex. 1997)). “To establish fraud by non-disclosure, the plaintiff must show: (1) the defendant deliberately failed to disclose material facts; (2) the defendant had a duty to disclose Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 37 of 55
38 such facts to the plaintiff; (3) the plaintiff was ignorant of the facts and did not have an equal opportunity to discover them; (4) the defendant intended the plaintiff to act or refrain from acting based on the nondisclosure; and (5) the plaintiff relied on the non-disclosure, which resulted in injury.” See id. at 219-20. Generally, “there is no duty to disclose without evidence of a confidential 13 or fiduciary 14 relationship.” Id. at 220 (citing Ins. of N. Am. v. Morris, 981 S.W.2d 667, 674 (Tex. 1998). Defendant argues that Plaintiff cannot establish that Plaintiff was ignorant of the facts because Plaintiff and the Architect investigated the undisclosed options and rejected them. ECF No. 126 at 25. Defendant also argues that Plaintiff has no knowledge of communication between Defendant and the Architect and, therefore, cannot show that Defendant failed to inform the Architect. ECF No. 126 at 26. Plaintiff argues that the evidence confirms that the issues, risks, and alternative systems raised in Defendant’s internal report and emails were never raised to Plaintiff. Further, Plaintiff asserts that Defendant’s evidence that Plaintiff investigated and rejected the alternative options relate to a different Project and does not show that Plaintiff or the Architect were aware of the issues Defendant discussed 13 A confidential relationship is one in which the “parties have dealt with each other in such a manner for a long period of time that one party is justified in expecting the other to act in its best interest.” Id. (citing Morris, 981 S.W.2d at 674); Meyer v. Cathey, 167 S.W.3d 327, 331 (Tex. 2005) (per curiam) (recognizing that an informal relationship giving rise to a duty may also be created by a “special relationship of trust and confidence [which] exist[s] prior to, and apart from, the agreement”)). 14 A fiduciary duty arises “as a matter of law in certain formal relationships, including attorney- client, partnership, and trustee relationships.” Id. 220 (citing Morris, 981 S.W.2d at 674). Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 38 of 55
39 internally. ECF No. 129 at 27. Indeed, the evidence that Defendant cites to supports finding that Plaintiff and the Architect were familiar with alternative systems like VRF and DOAS systems and their costs but does not show that Plaintiff and the Architect were aware of the issues and consequences that Defendant discussed internally that could potentially be remedied with these alternative systems. See ECF No. 126-20 (email from the Architect to Defendant dated October 30, 2015 with the subject line “La Cantera meeting” stating “Thank you for being available for the La Cantera 15 Kick-off meeting. The group meeting will be pretty high level orientation to the Project. Currently, we are assuming the systems will be the same as the Katy Project. However, due to Owner preference and challenges with the energy code, we need to discuss alternate systems. For alternate systems, I’m thinking DX-split ilo VPACS. Previously we have done extensive studies on VRF systems and they are just too expensive for this client, so let’s not mention VRF on Monday. After the group meeting, Lee Lyles (owner) would like to spend a few minutes with you talking about options. If you can be prepared to talk about some of the challenges with the 2015 IECC that would be helpful too.”); ECF No. 126-16 at 167:18–168:21 (Plaintiff’s representative, Lee Lyles’ deposition testimony that the VRF system did not fit into the Project’s model, so to afford it, Plaintiff would have to eliminate other 15 There is no evidence that La Cantera’s climate or environment is similar to the project here. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 39 of 55
40 elements like the dining room or bar, and that was a decision Plaintiff was not willing to make because the rest of the market was not using the VRF system); 234:13– 234:22 (Lyles’ deposition testimony that DOAS was not a “generally accepted practice in these facilities”); 235:12–236:21 (Lyles’ deposition testimony that when the Project was designed, it would have been unusual to use a DOAS system). Furthermore, Plaintiff’s evidence demonstrates that there is genuine issue of material fact as to whether Plaintiff and the Architect were ignorant of the climate issues and risks Defendant’s designs posed that could be remedied by alternative systems raised in Defendant’s internal discussions. Defendant was to design an HVAC system to “handle the humid environment.” Herr Affidavit, ECF No. 129-2 ¶ 44. Defendant did an internal review of its designs for the Project and in the internal review, Harris noted that the current design would not provide sufficient humidity control, among other issues. ECF No. 129-2 ¶ 47 (Harris tasked with Defendant’s in-house review and found potential issues with humidity controls); Donaldson Affidavit, ECF No. 129-8 ¶ 7 (same). Nordholm responded to Harris that he could “get some de-humidification in the corridors but not a great deal.” ECF Nos. 129-2 ¶ 48; 129-8 ¶ 8. Harris again responded that “this is a major design problem” and “[i]f we were directed by the Owner to use these systems someone should have told him that they will not work and that he can expect to have humidity control issues and potential mold issues in the building or that he is going to have one hell of an Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 40 of 55
41 energy bill for us to make them work. Quite frankly I can’t believe that we are going thru this issue again. . . . in my humble opinion, we need to circle the wagons here and get George Johnson (or whoever the main Owner contact is for this Project) make sure we want to proceed down this path before we issue any CDs.” ECF Nos. 129-2 ¶ 49; 129-8 ¶ 9; Harris Deposition Transcript, May 20, 2024, ECF No. 129-10 at 105:17-22 (the design would not work for a commercial building); 106:7- 12 (Defendant needed to discuss potential humidity control issues and mold issues with the owner of the Project). These reports were not raised with the Architect. ECF Nos. 129-2 ¶ 50 (Defendant’s internal review emails and concerns not shared with the Architect); 129-8 ¶ 10 (same). Harris also published a Mechanical Review Report that echoed the concerns about the risk in using exclusively natural ventilation and did not inform the Architect that the use of alternative systems (such as DOAS or VRF) were necessary to ensure that humidity issues did not impact the Project. ECF Nos. 129-2 ¶¶ 51; 129-8 ¶¶ 11; Fronapfel Affidavit, ECF No. 129-5 ¶¶ 25–26; Nordholm Deposition Transcript, May 20, 2024, ECF No. 129-11 at 176:22-177:8 (Nordholm did not tell the Architect to expect humidity control issues). None of the above concerns were provided or communicated to Plaintiff or the Architect. ECF Nos. 129-2 ¶¶ 52, 54; 129-8 ¶¶ 12, 13, 14; Sweeney Affidavit, ECF No. 129-3 ¶¶ 17, 18. Plaintiff only learned of the Report when it was produced in discovery in this case. ECF Nos. 129- Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 41 of 55
42 9 ¶ 6; 129-3 ¶¶ 17, 20. There are genuine issues of material fact to be determined at trial: the Architect relied on Defendant’s recommendations and because Defendant did not raise the above concerns with the Architect, the Architect believed the design to be safe and appropriate, ECF No. 129-2 ¶¶ 56; 57, ECF No. 129-8 ¶¶15, 16; and had these issues been brought to the Architect’s attention, then the Architect would have communicated to Plaintiff and the Architect and Plaintiff would have required Defendant to make new recommendations, ECF Nos. 129-2 ¶ 58; 129-8 ¶ 17; Plaintiff’s representative Lee Lyles Deposition Transcript, May 14, 2024, ECF No. 129-12 at 228:1–229:4 (no discussions where the Architect or Plaintiff informed the other that the VRF system was too expensive for this Project). Summary judgment should be denied as to Plaintiff’s fraudulent concealment claims. 2. Plaintiff’s Fraudulent Inducement Claims Should Survive Summary Judgment. “Fraudulent inducement is actionable when the misrepresentation is a false promise of future performance made with a present intent not to perform.” Id. (quoting Anderson, 550 S.W.3d at 614); see also Maciel Communications Contractors, LLC v. Lit Fiber, LLC, No. 1:23-CV-00128, 2025 WL 1825537, at *3 (S.D. Tex. Feb. 13, 2025) (“Plaintiff must establish all elements of the common law fraud claim, plus the added element that the fraud related to an agreement between the parties.”) (citing Haase v. Glazner, 62 S.W.3d 795, 798 (Tex. 2001)). “A promise Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 42 of 55
43 of future performance constitutes actionable fraud if the promise was made with no intention of performing at the time it was made.” Civelli v. Mulacek, No. CIVIL ACTION H-17-3739, 2025 WL 1009075, at *17 (S.D. Tex. Feb. 27, 2025), adopted, No. 4:17-CV-03739, 2025 WL 952968 (S.D. Tex. Mar. 31, 2025), and reconsideration denied, No. 4:17-CV-03739, 2025 WL 2411228 (S.D. Tex. Aug. 20, 2025) (quoting Formosa Plastics, Corp. USA v. Presidio Eng’rs &. Cont’rs, Inc., 960 S.W.2d 41, 48 (Tex. 1998)). Failure to perform alone is not evidence of fraud—Plaintiff must produce evidence that Defendant “made representations with the intent to deceive and with no intention of performing as represented” at the time the representation was made. Id. (quoting Formosa, 960 S.W.2d at 48). “A defendant’s intent to perform at the time of the agreement is generally an issue of fact, but ‘if the evidence of intent is so weak that it creates only a mere surmise or suspicion’ of the defendant’s ill intent, a fraud claim should not survive a motion for summary judgment.” Id. at *18 (quoting Fuller v. Wholesale Elec. Supply Co. of Houston, Inc., 631 S.W.3d 177, 187 (Tex. App.—Houston [14th Dist.] 2020, pet. denied)). Defendant argues that Plaintiff cannot prove fraudulent intent because there is no evidence that at the time of the agreement, Defendant had no intention of performing—instead, Plaintiff’s expert testified that Defendant’s natural ventilation could comply with the Mechanical Code, as promised in the agreement. ECF Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 43 of 55
44 No. 126 at 26–27. Plaintiff responds that Defendant misrepresents Plaintiff’s expert’s testimony and its evidence shows a genuine issue of material fact that Defendant knew its representation that its mechanical designs could handle the humid environment was false but made these representations to encourage the Architect and Plaintiff to rely on the misrepresentation and continue with Defendant’s design. ECF No. 129 at 27–28. Plaintiff’s evidence shows a genuine issue of material fact as to whether Defendant lacked the intent to perform at the time the representations to perform were made. At the beginning of their relationship on the Project, the Architect provided Defendant with a Request for Proposal (“RFP”) and described the Project and engineering services requested—the request noted that “[m]akeup air will be preconditioned and provided as required by the Mechanical Code. Due to the climate, the design team will need to evaluate additional makeup air requirements to handle the humid environment.” ECF No. 129-2 ¶¶ 16–21. The agreement between the Architect and Defendant detailed the scope of Defendant’s services and stated that Defendant would “[p]rovide drawings and specification as stated in [the RFP]” and would perform its services in “a manner consistent with the degree of skill and care ordinarily exercised by practicing design professionals performing similar services in same locality, and under the same or similar circumstances and conditions.” ECF Nos. 129-2 ¶¶ 22-29; 129-3 ¶¶13-15. SSR was tasked with and Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 44 of 55
45 contracted to design an HVAC system for the Project that could “handle the humid environment.” ECF No. 129-2 ¶ 44. Plaintiff’s expert, Robert Elkins, investigated the Project’s HVAC systems and found that the Project suffered from HVAC defects out of Defendant’s scope of mechanical design work—and specifically noted several design defects that were not code-compliant and/or did not compensate for the humid environment. Fronapfel Affidavit, ECF No. 129-5 ¶¶18-19; Tinker Affidavit, ECF No. 129-4 ¶ 6 (“[Plaintiff] did not have any knowledge of the design issues with the HVAC systems at the Project, including the sizing of the VTAC units or the lack of make-up air, until [Elkins] investigated the HVAC systems in early 2021.”). Elkins died in 2022, so Plaintiffs hired Edgar Stacy to continue the investigation—Stacy’s report reached conclusions consistent with Elkins’ conclusions. ECF No. 129-5 ¶¶ 21–24. Stacy died in 2023, so Plaintiff hired Michael Rabena. ECF No. 129-5 ¶ 24. Rabena’s reports reach conclusions consistent with Elkins and Stacy. Michael Rabena Affidavit and Reports, ECF No. 129-6 at 30 (“The Engineer designed a system that did not meet code requirements, and was insufficient in maintaining a facility wide, or individual unit, positive pressure. These failures, in my opinion, based upon my education and experience, fell below the standard of care for similar engineers in the same locale. As a result, the Project has had temperature and humidity issues.”). 16 16 Defendant cites to Rabena’s deposition testimony as proof that its design is code-compliant, Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 45 of 55
46 Furthermore, as noted above, Defendant internally discussed that the Project’s design was ill-suited for the humid environment, yet did not change their design or communicate these concerns and issues with the Architect or Plaintiff. Defendant seemingly did not do so because it intended for the Architect to rely on and move forward with its design. The evidence demonstrates a genuine issue of material fact as to whether Defendant intended to comply with the agreement at the time of agreement or whether Defendant falsely represented its design would include preconditioned makeup air and handle the humid environment. Summary judgment should be denied on Plaintiff’s fraudulent inducement claims. F. There is a Genuine Issue of Material Fact as to Whether Plaintiff’s Breach of Contract Claims are Time-Barred. Defendant argues that Plaintiff’s negligence and breach of contract claims are time-barred as they accrued before January 1, 2018 when completion occurred, but were not filed until 2025, 17 well after negligence’s two-year limitations period and breach of contract’s four-year limitations period. ECF No. 126 at 27–29. Defendant argues that the discovery rule does not save these claims because Plaintiff did not ECF No. 126-26 at 111:15–112:12 (natural ventilation as part of HVAC design is code-compliant under the International Mechanical Code), but this excerpt does not also demonstrate that Defendant’s design necessarily met the standard of care or could handle the specifically-noted humid environment. Rabena’s report lists dozens of other codes. ECF No. 129-6 at 13–14. 17 Although Plaintiff filed the operative complaint in 2025, Plaintiff originally brought these claims in their complaint on January 21, 2022. ECF No. 1 ¶¶ 64–69; 70–74. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 46 of 55
47 plead facts demonstrating applicability, comfort complaints are not inherently undiscoverable, and Plaintiff’s ignorance of the comfort complaints’ cause(s) does not amount to lack of discovery. ECF No. 126 at 28–29. Plaintiff responds that when it discovered or should have discovered its injury is a question of fact that should be determined by the factfinder. ECF No. 129 at 28. Plaintiff contends that it discovered the design failures that form the basis of its claims in 2021. ECF No. 129 at 29. The limitations period for a professional negligence claim in Texas is two years. Tex. Civ. Prac. & Rem. Code § 16.003(a). The limitations period for a breach of contract claim in Texas is four years. Tex. Civ. Prac. & Rem. Code § 16.051. “[I]t is well-settled that an action for breach of contract accrues immediately upon breach.” W. Power, Inc. v. TransAmerican Power Products, Inc., 316 F. Supp. 3d 979, 987 (S.D. Tex. 2018) (quoting Seureau v. ExxonMobil Corp., 274 S.W.3d 206, 227 (Tex. App.—Houston [14th Dist.] 2008, no pet.) (citing Barker v. Eckman, 213 S.W.3d 306, 311 (Tex. 2006))). “As a general rule, a cause of action accrues and the statute of limitations begins to run when facts come into existence that authorize a party to seek a judicial remedy.” Love & Joy Services, LLC v. Unity Nat’l Bank, No. 14-19-00082-CV, 2021 WL 1685192, at *6 (Tex. App.—Houston [14th Dist.] Apr. 29, 2021, pet. denied) (quoting Provident Life & Accident Ins. Co., v. Knott, 128 S.W.3d 211, 221 (Tex. 2003)). A cause of action “accrues when a wrongful act causes a legal injury, regardless of when the plaintiff learns of that injury or if all Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 47 of 55
48 resulting damages have yet to occur.” Id. (quoting Knott, 128 S.W.3d at 221). The wrongful acts or breaches that underlie Plaintiff’s professional negligence and breach of contracts claims all took place before completion on January 1, 2018. ECF Nos.126-9 (certificate of substantial completion issued August 23, 2016); 126- 10 (letter from the Architect dated December 11, 2017 noting “construction of the Delaney at Parkway Lakes is complete.”). Plaintiff filed these claims on January 21, 2022. ECF No. 1. Accordingly, neither Plaintiff’s breach of contract nor professional negligence was filed before the statute of limitations passed. Plaintiff avers that the discovery rule tolled its claims. ECF No. 129. Defendant argues that the complained of injury is “comfort complaints,” “being ‘too hot’ or ‘too cold,’” “are the very definition of an injury that is easily discoverable,” and therefore, the discovery rule does not apply. ECF No. 126 at 28. Defendant also argues that, if the discovery rule applies, the rule only tolled limitations upon discovery of the injury, not discovery of the cause, so because Plaintiff knew of its injuries by late 2017, its claims are still time-barred. ECF No. 126 at 29. Plaintiff responds that Defendant mistakenly emphasizes comfort issues but ignores that Plaintiff’s claims are based on Defendant’s design defects, which were undiscovered until 2021. ECF No. 129 at 29. When “the discovery rule applies, the statute of limitations does not begin to run ‘until the plaintiff knew or in the exercise of reasonable diligence should have Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 48 of 55
49 known of the wrongful act and resulting injury.’” Alt Platform, Inc. v. Beckett Collectibles, LLC, No. 3:22-CV-02867-N, 2024 WL 4376156, at *2 (N.D. Tex. Oct. 1, 2024) (citing Marcus & Millichap Real Est. Inv. Servs. of Nev., Inc. v. Triex Tex. Holdings, LLC, 659 S.W.3d 456, 462 (Tex. 2023) (quoting S.V. v. R.V., 933 S.W.2d 1, 4 (Tex. 1996))). The discovery rule applies where Plaintiff’s injury is both inherently undiscoverable and objectively verifiable. See id. (citing Archer v. Tregellas, 566 S.W.3d 281, 290 (Tex. 2018)). “An injury is inherently undiscoverable if it is by nature unlikely to be discovered within the prescribed limitations period despite due diligence.” Id. at *3 (quoting Berry v. Berry, 646 S.W.3d 516, 524 (Tex. 2022) (quoting S.V., 933 S.W.2d at 7)). Courts determine “whether the injury is ‘the type of injury that could be discovered through the exercise of reasonable diligence.’” Id. (quoting Marcus & Millichap Real Estate Inv. Services of Nevada, Inc. v. Triex Tex. Holdings, LLC, 659 S.W.3d 456, 461 (Tex. 2023) (quoting BP Am. Prod. Co. v. Marshall, 342 S.W.3d 59, 66 (Tex. 2011))). “The touchstone of whether an injury is a relevant injury that will toll the statute of limitations is whether the injury would put the plaintiff on notice that he had been injured.” Id. (quoting Van Pelt v. Guild Mortgage Co., No. 1:21-CV-068-H, 2022 WL 2053181, at *4 (N.D. Tex. June 7, 2022)). 18 18 “Under Texas law, to prevail at summary judgment on a limitations defense, the defendant bears the burden of negating the discovery rule by conclusively establishing that: (1) the discovery rule does not apply, or (2) the summary judgment evidence negates it.” In re Zachry Holdings, Inc., Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 49 of 55
50 “While determination of whether an injury is inherently undiscoverable is a question of law, reasonable diligence is an issue of fact.” In re Zachry Holdings, Inc., No. 24-90377, 2025 WL 664936, at *5 (Bankr. S.D. Tex. Feb. 27, 2025) (emphasis in original omitted) (quoting Silo Rest. Inc. v. Allied Prop. & Cas. Ins. Co., 420 F.Supp. 3d 562, 586 (W.D. Tex. 2019)). “Some courts may determine reasonable diligence as a matter of law ‘when there is actual or constructive notice, or when information is readily accessible and publicly available.’” Id. (quoting Hooks v. Samson Lone Star, LP, 457 S.W.3d 52, 58 (Tex. 2015)). “The discovery rule ‘need not be specifically pleaded in federal court,’” rather “[i]t is enough that the plaintiff plead sufficient facts to put the defense on notice of the theories on which the complaint is based.” In re Zachry Holdings, Inc., No. 24- No. 24-90377, 2025 WL 664936, at *4 (Bankr. S.D. Tex. Feb. 27, 2025) (citing McGowan v. S. Methodist Univ., 715 F.Supp. 3d 937, 946 (N.D. Tex. 2024)). But, under Erie principles, federal courts must apply federal procedural law—although there is some uncertainty as to which party bears the burden to establish or negate the discovery rule’s application to the statute of limitations, the Court agrees with the federal courts that utilize the burden-shifting framework under federal procedural law to find Plaintiff, who bears the burden of establishing application of the discovery rule at trial, also bears this burden at the summary judgment stage. See id. (citing Compare Tex. Soil Recycling, Inc. v. Intercargo Ins. Co., 273 F.3d 644, 649 (5th Cir. 2001) (aligning with Texas law by placing the burden on the defendant to negate the discovery rule), with FDIC v. Shrader & York, 991 F.2d 216, 220 (5th Cir. 1993) (placing the burden on the plaintiff)); see also Ensley v. Genworth Life & Annuity Ins. Co., No. 3:22-CV-0183-S, 2023 WL 2605029, at *5 (N.D. Tex. Mar. 22, 2023) (“To carry its summary judgment burden, Defendant ‘must establish beyond peradventure that each cause of action in question accrued outside the applicable limitations period.’ If Defendant carries its burden, Plaintiff then bears ‘the burden to show a material factual dispute regarding the timeliness of [his] claims, which may include a showing that the claims are timely through the discovery rule.’”) (citing Silo Rest. Inc. v. Allied Prop. & Cas. Ins. Co., 420 F. Supp. 3d 562, 576 (W.D. Tex. 2019)). Even so, the outcome is the same—Plaintiff’s evidence demonstrates a genuine issue of material fact as to whether the discovery rule tolled limitations such that Plaintiff’s claims are timely, and Defendant’s evidence does not conclusively negate this. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 50 of 55
51 90377, 2025 WL 664936, at *3 (Bankr. S.D. Tex. Feb. 27, 2025) (quoting Brandau v. Howmedica Osteonics Corp., 439 F. App’x 317, 320 (5th Cir. 2011) (quoting TIG Ins. Co. v. Aon Re, Inc., 521 F.3d 351, 357 (5th Cir. 2008))). Plaintiff pled sufficient facts to put Defendant on notice of its discovery rule theory. See ECF No. 105. Here, the Court finds that the discovery rule is applicable. Although the breaches and wrongful acts necessarily took place before the completion of the Project, arguably injuries from those breaches and acts were not as “easily discoverable” as Defendant contends—arguably, these injuries could not reasonably be discovered until residents moved in, utilized the defective A/C and heating systems in hot and cold weather, and raised comfort complaints such that Plaintiff was on notice that it suffered from an injury. See In re Zachry Holdings, Inc., 2025 WL 664936, at *4 (utilizing latent injury analysis applicable to discovery rule and tort claims to breach of contract claims); Morningside Ministries v. Koontz McCombs Constr., Ltd., No. 08-23-00332-CV, 2025 WL 1508641, at *13–14 (Tex. App.—El Paso May 27, 2025, pet. filed) (“Among other defects, Morningside alleges improper construction outside the Architectural specifications, systemic structural issues, deviations from design requirements, and non-compliance with geo-technical recommendations concerning exterior grading. . . . Because of the very nature of the defects, the wrong and the injury were unknown to Morningside—and not due to any fault on its part.”) (citing S.V., 933 S.W.2d at 7; cf., Dallas Market Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 51 of 55
52 Center Hotel Co. v. Beran & Shelmire, 865 S.W.2d 145, 147 (Tex. App.—Corpus Christi 1993, writ denied) (noting policy considerations underlying discovery rule application are present in construction context where “aggrieved party frequently does not discover an injury until months or years after construction is completed”)); Holiday Inn Club Vacations, Inc. v. CBRE, Inc., No. 14-23-00976-CV, 2025 WL 383161, at *9 (Tex. App.—Houston [14th Dist.] Feb. 4, 2025, pet. filed) (discovery rule applied where alleged faulty construction resulting in water intrusion and other damages was inherently undiscoverable). But, the Court finds that Plaintiff’s argument that limitations did not run until experts discovered Defendant’s design defects causing comfort complaints is similarly off the mark—here, the application of the discovery rule is based on discovery of the injury caused by the design defects, not discovery of the design defects themselves. 19 See Diamond Beach Owners Ass’n v. Stuart Dean Co., Inc., No. 3:18-CV-00173, 2018 WL 7081232, at *3 (S.D. Tex. Dec. 19, 2018), adopted, No. 3:18-CV-00173, 2019 WL 245462 (S.D. Tex. Jan. 17, 2019) (“For limitation purposes, Plaintiff knew there were problems with the windows in 2011/2012 and that knowledge put Plaintiff on notice of actual or potential injury-causing conduct, even if it did not realize the full extent of its injury. Plaintiff therefore had an 19 Plaintiff does not provide any cases that show the discovery rule contemplates discovery of the design defect instead of the injury caused by the design defect. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 52 of 55
53 obligation to exercise reasonable diligence to investigate the suspected harm and file suit, if at all, within the limitations period.”) (internal quotations and citation omitted). Defendant’s cited evidence demonstrates that Plaintiff hired experts who allegedly discovered design defects after looking into comfort complaints, but this evidence does not provide a date of when the comfort complaints were discovered. 20 Rabena’s Expert Report, ECF No. 126-19; Summary of Work Orders dated December 13, 2017 to January 21, 2020, ECF No. 126-11. 21 Plaintiff asserts that it engaged the experts who discovered the design defects after it contacted Gregory Edwards, Inc., the original mechanical subcontractor, in January 2019 for maintenance and repairs on the VTAC units. ECF No. 129 at 9; Tinker’s Affidavit, ECF No. 129-4 ¶ 5 (“During the period of January 2019 through December 2021, [Plaintiff] contacted Gregory Edwards, Inc., the original mechanical subcontractor for the Project, for maintenance and to make certain repairs on the [VTAC] units at the Project. . . . The repairs included, but were not limited to, adding refrigerant, addressing coil issues, replacing fan motors, addressing electronic issues, and 20 Defendant also cites to “ECF 1-2, pp. 3:4-6, 4:18-22, 13:13-14,” but this citation does not make sense. ECF No. 1-2 is a 94-page compilation of several exhibits, so the pin-cites are useless. 21 Most of the summaries are too vague to demonstrate that Plaintiff had knowledge of injuries caused by the design defects and Defendant does not point out any specific entries as the date when Plaintiff discovered or should have discovered its injury. ECF No. 126-11 (e.g. “thermostat”). Without more, these entries do not conclusively establish tolling ended on January 1, 2018—but they do create a factual dispute as to whether Plaintiff could have discovered its injuries and subsequently the design defects through reasonable diligence before limitations expired. Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 53 of 55
54 repairing and replacing compressors.”). The evidence establishes that the discovery rule tolled limitations to January 2019 at the latest, when VTAC issues prompted Plaintiff to seek maintenance and repair. Accordingly, there is no genuine issue of material fact that Plaintiff’s professional negligence claims filed on January 21, 2022, ECF No. 1, are time- barred and filed more than two years after Plaintiff sought maintenance and repair in January 2019. However, there is genuine issue of material fact as to whether Plaintiff’s breach of contract claims, filed on January 21, 2022, ECF No. 1, were tolled by the discovery rule and filed within four years of discovery. Because there is a factual dispute regarding the application of the discovery rule to Plaintiff’s breach of contract claims, summary judgment on limitations grounds is not appropriate. V. CONCLUSION The Court RECOMMENDS that Defendant’s motion for summary judgment, ECF No. 126, be GRANTED IN PART, such that Plaintiff’s professional negligence claims be dismissed as time-barred, and in all other respects be DENIED. The Parties have fourteen days from service of this Report and Recommendation to file written objections. 28 U.S.C. § 636(b)(1)(C); F ED. R. C IV . P. 72(b). Failure to file timely objections will preclude appellate review of factual findings or legal conclusions, except for plain error. Ortiz v. San Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 54 of 55
55 Antonio Fire Dep’t, 806 F.3d 822, 825 (5th Cir. 2015). Signed on January 6, 2026, at Houston, Texas. ________________________________ Dena Hanovice Palermo United States Magistrate Judge ston, Texas. ___________________________ _ _ Dena Hanovice Palermo nited States Magistrate Judge Case 4:22-cv-00218 Document 159 Filed 01/07/26 in TXSD Page 55 of 55
Was bedeutet dieser Text für Ihre Situation?
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.