UNBEATABLESALE.COM, INC. v. LJM SUPPLIES CORP.

3:25-cv-05389Njd29.01.2026

Gesamter Gesetzestext

Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 1 of 7 PageID:
<pageID>
Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 2 of 7 PageID:
<pageID>
Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 3 of 7 PageID:
<pageID>
Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 4 of 7 PageID:
<pageID>
Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 5 of 7 PageID:
<pageID>
Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 6 of 7 PageID:
<pageID>
Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 7 of 7 PageID:
<pageID>

OCR transcription for search; preserved printed pages are authoritative

Case 3:25-cv-05389-MAS-JBD Document 28 _ Filed 01/29/26 Page 1 of 7 PagelD:
<pagelD>

NOT FOR PUBLICATION

UNITED STATES DISTRICT COURT
DISTRICT OF NEW JERSEY

UNBEATABLESALE.COM, INC.,

Plaintiff,
Civil Action No. 25-5389 (MAS) (JBD)
Vv.
MEMORANDUM OPINION

LJM SUPPLIES CORP. d/b/a LIM GROUP,
INC.,

Defendant.

SHIPP, District Judge

This matter comes before the Court on Defendant LJM Supplies Corp.’s (“Defendant”)
Motion to Dismiss Plaintiff Unbeatablesale.com, Inc.’s (“Plaintiff”) Complaint. (ECF No. 12.)
After careful consideration of the parties’ submissions, the Court decides Defendant’s motion
without oral argument pursuant to Local Civil Rule 78.1(b). For the reasons outlined below,
Defendant’s motion is granted.

1 BACKGROUND!

Plaintiff is a direct-to-consumer retailer who contracted with Defendant in 2018 to reduce
certain shipping and billing expenses. (Compl. ff 1-2, 6, 7, 12, ECF No. 1.) The parties entered
into two agreements that year: (1) a “Client Service Agreement,” pursuant to which Defendant was
to provide Plaintiff with “freight auditing services” in exchange for 40% of any savings realized;

and (2) a “Consulting Agreement,” pursuant to which Defendant was to help lower Plaintiff’s

' For the purpose of considering the instant motion, the Court accepts all factual allegations in the
Complaint as true. See Phillips v. Cnty. of Allegheny, 515 F.3d 224, 228 (3d Cir. 2008).

AUTHENTICATED
U.S. GOVERNMENT
INFORMATION

GPO

Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 2 of 7 PagelD:
<pagelD>

shipping costs by negotiating more favorable contracts with UPS, FedEx, and other carriers. (/d.
qq 7-9, 12-13, 30.)

On November 6, 2018, Plaintiff sent e-mail correspondence to Defendant, providing
“official notice of 30 days to terminate our agreement.” (/d. §/ 16.) While Plaintiff’s correspondence
did not specify what agreement it was purportedly terminating, Plaintiff alleges this notice
terminated only the Consulting Agreement, and not the Client Service Agreement.’ (Id. §§ 16, 37;
Compl. Ex. 2, ECF No. 1-2.) In December 2018, Defendant ceased providing Plaintiff with freight
auditing services. (Ud. § 19.)

On March 12, 2019, Defendant commenced an action against Plaintiff in New York state
court alleging breach of contract (the “New York Action”). See UnbeatableSale.com v. LJM
Supplies, Index No. 603427/2019 (Sup. Ct. Nassau Cnty.).? In that action, Defendant alleges
Plaintiff breached the Consulting Agreement by purportedly terminating the contract via e-mail
correspondence, and by failing to pay Defendant 40% of its realized cost savings. (See generally
N.Y. Action, ECF No. 2.) The parties have litigated the New York Action for over six years, and
that case remains pending. (See id.; ECF No. 27 at 1.)

On May 23, 2025, Plaintiff filed the instant action, alleging that Defendant breached the

Client Service Agreement in December 2018 when it ceased providing its freight auditing

* Defendant disputes Plaintiff’s characterization of the November 2018 notice and contends that it
reasonably understood the notice as purporting to terminate the Client Service Agreement. (Def.’s
Moving Br. 3-4, ECF No. 12-1.)

3 Docket entries from the related matter, UnbeatableSale.com v. LJM Supplies, Index
No. 603427/2019 (Sup. Ct. Nassau Cnty.), are designated as “N.Y. Action, ECF No.”

Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 3 of 7 PagelD:
<pagelD>

services.’ (See generally Compl.) Defendant now moves to dismiss the Complaint as time-barred
and for failure to state a claim under Rule 12(b)(6). (See generally id.)

Il. LEGAL STANDARD

Rule 8(a)(2) “requires only ‘a short and plain statement of the claim showing that the
pleader is entitled to relief,’ in order to ‘give the defendant fair notice of what the . . . claim is and
the grounds upon which it rests.’” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007) (quoting
Conley v. Gibson, 355 U.S. 41, 47 (1957)).

A district court conducts a three-part analysis when considering a motion to dismiss under
Rule 12(b)(6). See Malleus v. George, 641 F.3d 560, 563 (3d Cir. 2011). First, the court must
identify “the elements a plaintiff must plead to state a claim.” Ashcroft v. Iqbal, 556 U.S. 662, 675
(2009). Second, the court must identify all of the plaintiff’s well-pleaded factual allegations, accept
them as true, and “construe the complaint in the light most favorable to the plaintiff.” Fowler v.
UPMC Shadyside, 578 F.3d 203, 210 (3d Cir. 2009) (citation omitted). The court can discard bare
legal conclusions or factually unsupported accusations that merely state the defendant unlawfully
harmed the plaintiff. See Iqbal, 556 U.S. at 678 (citing Twombly, 550 U.S. at 555). Third, the court
must determine whether “the [well-pleaded] facts alleged in the complaint are sufficient to show
that the plaintiff has a ‘plausible claim for relief.’” Fowler, 578 F.3d at 211 (quoting Iqbal, 556 U.S.

at 679). A facially plausible claim “allows the court to draw the reasonable inference that the

* Plaintiff concedes that its breach of contract claim could have been brought as a permissive
counterclaim in the New York Action. (See ECF No. 26 at 2, 5.) The Court, accordingly, issued an
Order to Show Cause as to why this action should not be dismissed or stayed pursuant to the
abstention principles articulated in Colorado River Water Conservation District v. United States,
424 U.S. 800 (1976), and Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460
U.S. 1 (1983). (ECF No. 22.) Upon consideration of the parties’ briefing, and the strong
presumption in favor of exercising federal jurisdiction, the Court finds that abstention is not
warranted and therefore exercises its jurisdiction over this action.

Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 4 of 7 PagelD:
<pagelD>

defendant is liable for the misconduct alleged.” Jd. at 210 (quoting Jgbal, 556 U.S. at 678). On a
Rule 12(b)(6) motion, the “defendant bears the burden of showing that no claim has been
presented.” Hedges v. United States, 404 F.3d 744, 750 (3d Cir. 2005) (citing Kehr Packages, Inc.
v. Fidelcor, Inc., 926 F.2d 1406, 1409 (3d Cir. 1991)).

Ill. DISCUSSION

Defendant contends that Plaintiff’s breach of contract claim is untimely, and that Plaintiff
otherwise fails to state a claim upon which relief can be granted. (See generally Def.’s Moving
Br.) Because the statute of limitations presents a threshold issue, the Court addresses it first.°

Under New Jersey law, the statute of limitations for a breach of contract claim is six years
from the date the cause of action accrues. N.J. Stat. Ann. § 2A:14-1. As a general rule, a breach of
contract claim accrues on “‘the date on which the right to institute and maintain a suit’ first arose.”
County of Morris v. Fauver, 707 A.2d 958, 971 (N.J. 1998) (quoting Rosenau v. City of New
Brunswick, 238 A.2d 169, 172 (N.J. 1968)).

Plaintiff concedes that it did not bring this action until more than six years had elapsed after
Defendant’s breach of the Client Service Agreement. (Pl.s’ Opp’n Br. 9-11, ECF No. 20; see also
Compl. ¥ 19 (alleging Defendant breached the Client Service Agreement in December 2018); see
generally id. (indicating this action was filed on May 23, 2025).) Plaintiff, however, argues that its
claim falls under the “continuing breach” exception, under which claims can be brought outside
the statutory period if successive breaches occurred within a “continuing” contract. (PI.’s Opp’n

Br. 9-11); see Fauver, 707 A.2d at 971-72 (explaining that a new cause of action arises upon each

> A federal court exercising diversity jurisdiction must apply the substantive law of the state in
which the court sits. Erie R.R. Co. v. Tompkins, 304 U.S. 64, 72 (1938). Because the parties do not
dispute the application of New Jersey law to the instant matter, the Court need not engage in a
choice of law analysis at this stage and will apply New Jersey law to Plaintiff’s breach of contract
claim. See Williams v. BASF Catalysts LLC, 765 F.3d 306, 316-17 (3d Cir. 2014).

Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 5 of 7 PagelD:
<pagelD>

successive breach for such continuing contracts). Plaintiff argues that Defendant has “continuously
breached a nonpayment obligation,” and therefore Plaintiff’s claim is timely. (Pl.’s Opp’n Br.
10-11.) The Court disagrees.

New Jersey courts apply the continuing breach doctrine narrowly, most often in the context
of installment contracts or contracts that expressly require periodic performance. See Nat’l Util.
Serv. Inc. v. Cambridge-Lee Indus., Inc., 199 F. App’x 139, 142 (3d Cir. 2006) (citation omitted)
(“The standard is typically applied in installment contracts, so that ‘a new cause of action arises
from the date each payment is missed.””).

Here, Plaintiff states in a conclusory fashion that Defendant’s conduct constitutes a
“continuing breach of contract.” (Compl. § 21; see also id. § 22.) The Complaint, however, does
not plead facts from which the Court can plausibly infer that the Client Service Agreement was an
installment contract, or otherwise required periodic performance giving rise to “a series of
continuing breaches” over time. See Ballantyne House Assocs. v. City of Newark, 635 A.2d 551,
555 (App. Div. 1993); see also 9 Arthur L. Corbin, Corbin on Contracts § 956 (rev. ed. 2002)
(“[C]ontracts .. . that have been said to require continuing (or continuous) performance for some
specified period of time . . . are capable of a series of ‘partial’ breaches.”). Plaintiff, for example,
does not allege that Defendant’s freight auditing services required periodic performance, nor do
the terms of the Client Service Agreement delineate such obligations.® (See Client Service

Agreement, ECF No. 4 (providing generally that Defendant “will provide freight audit services to

° Although Plaintiff argues in opposition that the Client Service Agreement provided for a
“monthly auditing service,” (Pl.’s Opp’n Br. 11), the Complaint contains no such allegation (see
generally Compl.). It is well settled that a plaintiff may not amend its Complaint through arguments
raised in opposition to a motion to dismiss. Frederico v. Home Depot, 507 F.3d 188, 202 (Gd Cir.
2007). Moreover, the Court notes that Plaintiff’s assertion that the auditing service was “monthly”
is inconsistent with its allegations that Defendant breached the Client Service Agreement on a
“daily” and “weekly” basis. (P1.’s Opp’n Br. 11; see also Compl. § 22.)

Case 3:25-cv-05389-MAS-JBD Document 28 Filed 01/29/26 Page 6 of 7 PagelD:
<pagelD>

[Plaintiff]” without specifying periodic obligations));’ see Nat’l Util. Serv. Inc., 199 F. App’x at
143 (applying the continuing breach doctrine where the contract obligated defendant to perform
“every month during the contract term”). Rather, Plaintiff alleges that Defendant agreed to
“provide freight audit services,” and that Defendant ceased providing those services altogether in
December 2018. (Compl. { 19.) Such allegations describe a single alleged breach, not a series of
successive breaches which would make the continuing breach doctrine applicable. See Diakos v.
Rudnick, No. A-2468-15T2, 2017 WL 6398928, at *4 (N.J. Super. Ct. App. Div. Dec. 15, 2017)
(rejecting plaintiffs argument that the agreement was a continuing contract where the agreement
“[did] not call for a monthly or annual payment of profits or any other set periodic payment
structure”). Accepting Plaintiffs argument would effectively transform any contract containing a
performance obligation into a continuing contract, a result unsupported by New Jersey law.

The Court, accordingly, finds that the continuing breach doctrine does not apply to
Plaintiff’s breach of contract claim as currently alleged. Plaintiff was obligated to file this lawsuit
within six years of the breach of contract, and Plaintiff failed to do so. Plaintiff’s claim is therefore

dismissed as time-barred.

7 The Complaint relies on and attaches as exhibits the Client Service Agreement and the Consulting
Agreement. (ECF Nos. 4, 5.) Because the contracts are “integral to or explicitly relied upon in the
[C]omplaint,” and their authenticity is not disputed, the Court considers them in resolving the
instant motion to dismiss. Doe v. Univ. of Scis., 961 F.3d 203, 208 (3d Cir. 2020) (citation omitted).

Case 3:25-cv-05389-MAS-JBD Document 28 _ Filed 01/29/26 Page 7 of 7 PagelD:
<pagelD>

IV. CONCLUSION

For the foregoing reasons, the Court grants Defendant’s Motion to Dismiss. To the extent
that Plaintiff can set forth claims which are not time barred, and can cure the deficiencies outlined
herein, the Court will give Plaintiff an opportunity to file an amended complaint. The Court will

issue an Order consistent with this Memorandum Opinion.

ICHAEL A. SHIPP
UNITED STATES DISTRICT JUDGE

DATED: January 29, 2026