UNITED STATES DEPARTMENT OF LABOR BOARD OF ALIEN LABOR CERTIFICATION APPEALS Washington, DC ______________ Issue Date: 20 July 2026 BALCA Case No.: 2026-TLN-00103 ETA Case No.: H-400-26048-644207 In the Matter of C&C LAWN & LANDSCAPING, INC., Employer. Certifying Officer: Susan Storch, National Processing Center Appearances: Kevin Lashus, Esq. KJ Partnes, LLP, Austin, Texas For the Employer Rebecca Nielsen, Esquire Office of the Solicitor U.S. Department of Labor Washington, DC For the Certifying Officer Before: Steven D. Bell Administrative Law Judge DECISION AND ORDER AFFIRMING DENIAL OF TEMPORARY LABOR CERTIFICATION This case arises from the request of C&C Lawn & Landscaping, Inc. (“Employer”) for review of the Certifying Officer’s (“CO”) decision to deny an application for temporary alien labor certification under the H-2B non-immigrant program.1 The H-2B program permits employers to hire foreign workers to perform temporary nonagricultural work within the United States on a one-time occurrence, seasonal, peakload, or intermittent 1 20 C.F.R. §655.6(b). On April 29, 2015, the Department of Labor (the “Department”) and the Department of Homeland Security jointly published an Interim Final Rule (“IFR”) amending the standards and procedures that govern the H-2B temporary labor certification program. 80 Fed. Reg. 24042 (Apr. 29, 2015). In this Decision and Order, all citations to 20 C.F.R. Part 655 pertain to the IFR.
2 basis, as defined by the United States Department of Homeland Security 2 Employers who seek to hire foreign workers under this program must apply for and receive labor certification from the United States Department of Labor (“Department” or “DOL”) using a Form ETA-9142B, Application for Temporary Employment Certification (“Form 9142”). A CO in the Office of Foreign Labor Certification (“OFLC”) of the Employment and Training Administration reviews applications for temporary labor certification. Following the CO’s denial of an application under 20 C.F.R. § 655.53, an employer may request review by the Board of Alien Labor Certification Appeals (“BALCA” or “the Board”).3 I. STATEMENT OF THE CASE Employer, located in Pacific, Missouri, is a landscaping company.4 On February 16, 2026, Employer filed: (1) Form ETA-9142B, Application for Temporary Employment Certification (“Application”); (2) Appendix A; (3) Signed Appendix B; (4) Job Order; (5) Prevailing Wage Determination P-400-25230-249139.5 Employer requested certification for 25 landscapers6 from May 2, 2026 to November 30, 2026, based on an alleged peakload need during that period.7 On May 8, 2026, the CO issued a Notice of Deficiency (“NOD”) based on the fact that Employer had filed two applications for the same positions during the same time period and worksite. It required Employer to either withdraw one of the applications, establish that the job opportunities in each application were not the same, or show a need for 50 total landscapers during the requested dates of need and that the need was not present when the first application was filed.8 Employer filed a response on May 11, 2026 withdrawing its earlier application.9 On May 27, 2026, the CO issued a second NOD based on (1) a failure to justify nature of temporary need under 20 C.F.R. § 655.6(a) and (b); and (2) failure to establish temporary need for the number of workers requested under 20 C.F.R. §§ 655.11(e)(3)-(4) 655.1(a)(1), 655.6.10 Employer submitted a response to the NOD on June 4, 2026,11 stating that although the start date is usually April 1, it was requesting workers starting May 2 due to the application cap. It stated that it has a peakload need because: 2 The definition of temporary need is governed by 8 C.F.R. § 214.2(h)(6)(ii)(B). Consolidated Appropriations Act, 2016, Pub. L. No. 114-113, Division H, Title I, § 113 (2015). This definition has remained in place through subsequent appropriations legislation, including the current legislation. See Consolidated Appropriations Act, 2026, Pub. L. No. 119-75, Division B, Title I, § 111 (2026). 3 20 C.F.R. § 655.61(a). 4 AF 62. In this Decision and Order, “AF” refers to the Appeal File. 5 AF 61-81. 6 SOC (O*Net/OES) occupation title “Landscaping and Groundskeeping Workers” and occupation code 37-3011.00. 7 AF 62. 8 AF 55-60. 9 AF 53. 10 AF 45-52. 11 AF 15-43.
3 Our services for mowing, edging and debris cleanup more than doubles from our slower winter season, beginning in Spring until November 30th. This requires our workforce and labor needs to more than triple during this busy time as well, with early Spring clean-up, irrigation tune-ups, pruning, and fertilization increasing our need for labor beginning in Spring. This peak-season schedule of April to November 30 requires us to add at least 25 workers to our workforce immediately, which is not possible through the local workforce.12 It stated that it does not require these peak season workers from November through spring because grass does not grow or need much maintenance during that time and the workers are only needed during the growing season. It argued that the need for 25 workers is established by their contracts and letters of intent for the landscaping season attached to its response.13 We typically have 8 crews running in a given day all at the same time for an average of about 3 workers in each crew and most often an additional smaller crew of 2 workers depending on the project. While we understand that the inability to recruit and retain workers is not a basis of need as recognized by the Department of Labor, it is important for us to explain that we cannot find U.S. workers to take these seasonal positions and we have to resort to sub-contracting our work out since U.S. workers generally want year-round and better paying jobs.14 Employer submitted contracts and proposals for the “LAWN SEASON” from 2023- 2026.15 On June 12, 2026, the CO issued a Final Determination denying Employer’s application for temporary labor certification under the H-2B temporary non-agricultural program.16 The CO stated that although Employer asserted a difficulty finding workers, “a labor shortage alone does not indicate that the underlying need for labor is temporary.” The CO found that Employer failed to correct the first deficiency because did not provide sufficient information related to its business operations to show how it determined its requested dates of need and the unrequested time in which it does not have the need for the requested labor to meet the definition of peakload need. The CO stated that although Employer submitted service contracts and proposals for 2023-2026 the submitted documents did not provide evidence of a peakload need because employer did not provide any evidence of when the services in those contracts would be 12 AF 15. 13 AF 15-16. 14 AF 16. 15 AF 17-43. 16 AF 4-14.
4 performed, the number of workers for those projects, or when earlier services were provided. The CO stated that Employer failed to submit payroll information or documentation of any regularly employed permanent workers who perform the services or labor at the place of employment that it needs to temporarily supplement.17 The CO found that Employer failed to correct the second deficiency because the documentation submitted did not indicate the number of workers needed for the described work or to complete the projects. The CO also noted that Employer failed to submit payroll information documenting the number of full time permanent and temporary employees each month for the previous two calendar years as requested by the second NOD.18 On June 22, 2026, Employer requested administrative review of the CO’s denial as permitted by 20 C.F.R. § 655.61.19 On June 29, 2026, BALCA assigned this case to me. The same day I issued a Notice of Assignment and Order Setting Briefing Schedule, permitting counsel for the Certifying Officer (“Solicitor”) to file briefs within seven business days of receiving the Appeal File per 20 C.F.R. § 655.61(c). On July 7, 2026, I received the Appeal File from BALCA. The Solicitor did not file a brief. II. DISCUSSION AND APPLICABLE LAW BALCA’s standard of review in H-2B cases is limited. BALCA may only consider the Appeal File prepared by the CO, the legal briefs submitted by the parties, and Employer’s request for administrative review, which may only contain legal arguments and evidence that Employer actually submitted to the CO before the date the CO issued a final determination.20 After considering the evidence of record, BALCA must: (1) affirm the CO’s determination; (2) reverse or modify the CO’s determination; or (3) remand the case to the CO for further action.21 Employer bears the burden of proving that it is entitled to temporary labor certification.22 The CO may only grant Employer’s Application to admit H-2B workers for temporary nonagricultural employment if Employer has demonstrated that: (1) insufficient qualified U.S. workers are available to perform the temporary services or labor for which Employer desires to hire foreign workers; and (2) employing H-2B workers will not adversely affect the wages and working conditions of U.S. workers similarly employed.23 BALCA has adopted an arbitrary and capricious standard of review.24 17 AF 10-11. 18 AF 13-14. 19 AF 1-3. 20 20 C.F.R. § 655.61. 21 20 C.F.R. § 655.61(e). 22 8 U.S.C. § 1361; see also Cajun Constructors, Inc., 2011-TLN-00004, slip op. at 7 (Jan. 10, 2011); Andy and Ed. Inc., dba Great Chow, 2014-TLN-00040, slip op. at 2 (Sept. 10, 2014); Eagle Industrial Professional Services, 2009-TLN-00073, slip op. at 5 (July 28, 2009). 23 20 C.F.R. § 655.1(a). 24 Brook Ledge, 2016-TLN-00003 (May 10, 2016); Three Season Landscape Contracting Services, 2016-TLN-00045 (June 15, 2016).
5 To obtain certification under the H-2B program, the Employer must establish that its need for workers qualifies as temporary under one of these four temporary need standards: one-time occurrence, seasonal, peakload, or intermittent.25 The definition of temporary need is governed by 8 C.F.R. § 214.2(h)(6)(ii)(B), which provides the following: Employment is of a temporary nature when the employer needs a worker for a limited period of time. The employer must establish that the need for the employee will end in the near, definable future. Generally, that period of time will be limited to one year or less, but in the case of a one-time event could last up to 3 years. The petitioner’s need for the services or labor shall be a one-time occurrence, a seasonal need, a peak load need, or an intermittent need. Employer in this case alleged that it has a peakload need from May 2, 2026 to November 30, 2026 for 25 landscapers.26 In order to establish a peakload need, Employer must establish: that it regularly employs permanent workers to perform the services or labor at the place of employment and that it needs to supplement its permanent staff at the place of employment on a temporary basis due to a seasonal or short-term demand and that the temporary additions to staff will not become a part of the petitioner’s regular operation.27 As the CO has correctly pointed out, the only documentary evidence Employer has submitted to show a temporary peakload need are its contracts and proposals, none of which include any timeline for when the work is required to be done during the year or the number of workers required for each for those projects.28 Although Employer asserts in its response to the second NOD that its “services for mowing, edging and debris cleanup more than doubles from our slower winter season, beginning in Spring until November 30th[,]” it has provided no evidence of when this increase in services begins and ends. Upon review of these records, Employer has not shown that it needs to supplement its permanent staff on a temporary basis due to a seasonal or short-term demand for its services. It thus has failed to establish a temporary peakload need from May 2, 2026 to November 30, 2026.29 25 See 20 C.F.R. § 655.6(b); 20 C.F.R. §655.11(a)(3). 26 AF 62. 27 8 C.F.R. § 214.2(h)(6)(ii)(B)(3). 28 AF 17-33. 29 8 C.F.R. § 214.2(h)(6)(ii)(B)(3).
6 After reviewing the evidence considered by the CO and all legal arguments, I agree that Employer has not provided sufficient information to overcome the first deficiency listed in the NOD. Further, I find that Employer has not demonstrated that the CO’s decision to deny certification under 20 C.F.R. § 655.6(a) and (b) was arbitrary, capricious, or otherwise not in accordance with the law. Therefore, Employer has not met its burden of showing that it is entitled to temporary labor certification.30 III. Order In light of the foregoing, it is ORDERED that the Certifying Officer’s decision denying certification be, and hereby is, AFFIRMED. For the Board: Steven D. Bell Administrative Law Judge 30 As I have found that Employer has not established entitlement to temporary labor certification, I need not consider any other issues in this claim.
Was bedeutet dieser Text für Ihre Situation?
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.