DO-DECISION AND ORDER ON THE MERITS NUMBER OF PAGES 4 JUDGE LARSEN DECISION AND ORDER AFFIRMING DENIAL OF CERTIFICATION AND REMAND FOR POSSIBLE RECONSIDERATION - mb — 2027TLM00002

2027TLM00002Dol Oalj

Gesamter Gesetzestext

UNITED STATES DEPARTMENT OF LABOR
BOARD OF ALIEN LABOR CERTIFICATION APPEALS
Washington, D.C.
______________
Issue Date: 29 October 2026
BALCA Case No. 2027-TLM-00002
ETA Case No. C-500-26211-134187
In the Matter of:
JSN ENTERPRISES, INCORPORATION
dba GENERAL BUILDING MAINTENANCE,
Employer.
DECISION AND ORDER AFFIRMING DENIAL OF CERTIFICATION
AND REMAND FOR POSSIBLE RECONSIDERATION
Employer JSN Enterprises, Inc., doing business as General Building
Maintenance, requests administrative review of the Certifying Officer’s de-
nial of certification of a CW-1 application for temporary nonagricultural la-
bor certification for employment in the Commonwealth of the Northern
Marianas Islands under 20 C.F.R. §§ 655.432(d), 655.453(b), 655.454(b).
Under 48 U.S.C. § 1806, the Immigration and Nationality Act, 8 U.S.C. §§
1101 et seq., applies to the Commonwealth of the Northern Mariana Islands.
The Chief Administrative Law Judge has designated me, under 20
C.F.R. § 655.461(c), to decide this appeal. I must uphold the decision of the
Certifying Officer (CO) unless the employer shows that decision to be arbi-
trary, capricious, or an abuse of discretion, or otherwise not in accordance
with the law. 20 C.F.R. § 655.461(d)(2). In so doing, I cannot consider evi-
dence not before the CO at the time of the CO’s determination, even if such
evidence is in the Appeal File, request for review, or legal briefs. 20 C.F.R. §
655.461(e).
Statement of the Case
On July 29, 2026, Employer filed a CW-1 Application for Temporary
Employment Certification seeking 10 General Building Maintenance Work-
ers under the CW-1 labor certification program (AF pp. 51-73). After the
CO issued a Notice of Deficiency on August 12, 2026 (AF pp. 41-49), Em-
ployer agreed to a modification of the application (AF pp. 28-38).
- 2 -
On August 20, 2026, the CO issued a Notice of Acceptance directing
Employer to “read all instructions and information contained in this letter
carefully” (AF p. 18), and including this instruction:
In order for the Certifying Officer to make a final deter-
mination on the employer’s CW-1 application, the em-
ployer must prepare, sign, date and submit a written
Recruitment Report no later than September 28,
2026. This is the final due date for the Recruitment
Report, but employers are encouraged to submit the
Recruitment Report as soon as allowable.
The Recruitment Report must be submitted by email to
the OFLC CW-1 Program at OFTLC.TLC@dol.gov with the
subject “Attn.: CW-1: C-500-26211-134187 Recruitment
Report.”
If the Employer does not have Internet access it may
submit the Recruitment Report with the same caption
by mail to the following address:
U.S. Department of Labor
Employment and Training Administration
Office of Foreign Labor Certification
200 Constitution Avenue, NW, Room N-5311
Washington, D.C. 20210
Attn: CW-1 Program Certifying Officer
In order to assist with the timely processing of the ap-
plication, the Recruitment Report should be received by
the date it is due. While the FLAG portal system oper-
ates on the Easter U.S. Time Zone when issuing letters,
consideration is given to the difference of CNMI date
and time in Greenwich Mean Time (GMT) (emphasis in
original).
(AF p. 23.)
On September 29, 2026, the National Processing Center sent an e-
mail to Employer:
Dear Sir/Madam,
The CW-1 Program issued employer, JSN Enterprises
Incorporation (C-500-26211-134187) a Notice of Ac-
- 3 -
ceptance (NOA) letter on August 20, 2026, which in-
cluded a recruitment report due date of September 28,
2026. As of today, the CW-1 Program has not received
a copy of the employer’s recruitment report.
If the employer would like the CW-1 Program to con-
tinue to process its CW-1 application without further
delay, the recruitment report must be submitted no
later than October 2, 2026, by e-mail to oflc.tlc@dol.gov.
If the employer would like to withdraw its application,
the employer must submit a written response to the
CW-1 Program by e-mail at oflc-tlc@dol.gov. In the
subject line of the email, please include the program
designation (e.g. CW-1) and the title: “Withdraw Appli-
cation.” In the body of the email, please state that you
wish to withdraw the application and include the case
number.
Sincerely,
CW-1 Program
National Processing Center
(AF p. 17.)
On October 7, 2026, the CO sent a Final Determination to Employer
denying the application (AF pp. 13-16). The CO based the denial on Em-
ployer’s failure to file the Recruitment Report even after the CO’s courtesy
email of September 29, 2026. See 20 C.F.R. § 655.453.
In its request for Administrative Review, Employer states it “inad-
vertently sent” the Recruitment Report on September 30, 2026, to the wrong
e-mail address (flag@dol.gov) instead of the correct one
(OFLC.TLC@dol.gov) (AF p. 1).
Standard of Review
The standard for administrative review is extremely strict. Under 29
C.F.R. § 655.461(e),
BALCA will . . . affirm, reverse, or modify the CO’s de-
termination, or remand to the CO for further action.
BALCA will reach this decision after due consideration
of the documents in the Appeal File that were before
the CO at the time of the CO’s determination, the re-
quest for review, and any legal briefs submitted.
- 4 -
BALCA may not consider evidence not before the CO at
the time of the CO’s determination, even if such evidence
is in the Appeal File, request for review, or legal briefs
(emphasis added).
The evidence that Employer sent the Recruitment Report to the
wrong e-mail address on September 30, 2026, is in the Employer’s request
for administrative review. Under the regulation cited above, I cannot con-
sider that evidence. Accordingly, I must affirm the Certifying Officer’s de-
nial of the application.
What this means, in practical terms, is that no one will consider the
Employer’s explanation. This may be a harsh result, but I cannot do other-
wise. I remand this matter to the Certifying Officer for such consideration
and action as she may deem appropriate, but she has no obligation to give
further consideration or take any action.
SO ORDERED.
CHRISTOPHER LARSEN
Administrative Law Judge
FOR THE BOARD