DO-DECISION AND ORDER ON THE MERITS NUMBER OF PAGES 7 JUDGE CALIANOS DECISION AND ORDER AFFIRMING THE CERTIFYING OFFICER’S DENIAL OF CERTIFICATION — 2026TLN00104

2026TLN00104Dol Oalj

Gesamter Gesetzestext

UNITED STATES DEPARTMENT OF LABOR
BOARD OF ALIEN LABOR CERTIFICATION APPEALS
WASHINGTON, D.C.
__________ Issue Date: 16 July 2026
BALCA CASE NO.: 2026-TLN-00104
ETA CASE NO.: H-400-26048-644200
In the Matter of:
LOD, LTD. d/b/a
LAWNSCAPE OF DALLAS,
Employer.
Before: Jonathan C. Calianos
Administrative Law Judge
Appearances: Kevin Lashus, Esq.
KJ Partners, LLP
Austin, Texas
For Employer1
DECISION AND ORDER AFFIRMING
THE CERTIFYING OFFICER’S DENIAL OF CERTIFICATION
The above-captioned claim arises under 8 U.S.C. § 101(a)(15)(H)(ii)(b) of the Immigration
and Nationality Act and the H-2B regulations governing temporary labor certification. The H-2B
program permits employers to hire foreign workers to perform temporary nonagricultural work
within the United States on a one-time occurrence, seasonal, peakload or intermittent basis, as
defined by the United States Department of Homeland Security (“DHS”). See 8 U.S.C. §
1101(a)(15)(H)(ii)(b); 8 C.F.R. § 214.2(h)(6);2 20 C.F.R. § 655.6(b).3
1 There was no appearance on behalf of the Office of Foreign Labor Certification.
2 The definition of temporary need is governed by 8 C.F.R. § 214.2(h)(6)(ii)(B). See Consolidated Appropriations Act,
2026, Pub. L. No. 119-75, Division B, Title I, § 111 (2026).
3 On April 29, 2015, the Department of Labor (“DOL”) and the Department of Homeland Security jointly published
an Interim Final Rule (“IFR”) amending the standards and procedures that govern the H-2B temporary labor
certification program. See Temporary Non-Agricultural Employment of H-2B Aliens in the United States; Interim
Final Rule, 80 Fed. Reg. 24,042 et seq. (Apr. 29, 2015). The rules provided in the IFR apply to applications “submitted
on or after April 29, 2015, and that ha[ve] a start date of need after October 1, 2015.” IFR, 20 C.F.R. § 655.4(e). All
citations to 20 C.F.R. Part 655 in this decision and order are to the IFR.
- 2 -
Employers who seek to hire foreign workers under this program must apply for and receive
labor certification from the United States Department of Labor using a Form ETA-9142B,
Application for Temporary Employment Certification. A Certifying Officer (“CO”) in the Office
of Foreign Labor Certification of the Employment and Training Administration reviews
applications for temporary labor certification. Following the CO’s denial of an application under
20 C.F.R. § 655.53, an employer may request review by the Board of Alien Labor Certification
Appeals (“BALCA” or “the Board”). 20 C.F.R. § 655.61(a).
For the reasons set forth below, the CO’s denial of temporary labor certification in this
matter is affirmed.
I. STATEMENT OF THE CASE
On February 16, 2026, LOD, Ltd. d/b/a Lawnscape of Dallas (“Employer”) filed a Form
ETA-9142B, Application for Temporary Employment Certification (“Application”), seeking 10
Landscape Laborers from May 2, 2026, through December 1, 2026, based on an alleged peakload
need. Appeal File (“AF”) 112.
On May 11, 2026, the CO issued a Notice of Deficiency (“NOD”) because Employer had
another application pending (Case No. H-400-26004-532655) for the same position in the same
area of intended employment in violation of 20 C.F.R. § 655.15(f). The CO directed Employer to
either: withdraw one of the applications; demonstrate that the job opportunities are not the same;
or provide support that it needs a total of 20 Landscape Laborers. AF 109. On May 15, 2026,
Employer provided a response, clarifying that it previously received certification in Case No. H-
400-26004-532655 but was unable to utilize the certification due to the H2-B visa cap being met.
AF 102-03. Accordingly, Employer withdrew the application associated with Case No. H-400-
26004-532655. Id.
On May 28, 2026, the CO issued a second NOD. AF 94. Employer’s response to the first
NOD remained under review, but in the interim, the CO had determined that there were additional
deficiencies with the Application. AF 98. Namely, the CO found that Employer failed to establish
a peak load need under 20 C.F.R. §§ 655.6(a) & (b) or the need for the number of workers requested
under 20 C.F.R. §§ 655.11(e)(3)-(4), 655.1(a)(1), and 655.6. AF 98-101. The CO directed
Employer to submit additional information and supporting documentation to rectify the
deficiencies cited.
- 3 -
On June 10, 2026, Employer responded to the second NOD. AF 15. Employer explained
that its primary services include lawn mowing and maintenance, with additional services of
installation, irrigation service, fertilization, spring clean-up, pruning, and mulching. Id. According
to Employer, its services more than double from the winter season to its peak period between April
1st and December 1st, necessitating the need for temporary labor. Id. Employer stated: “[W]e are
in desperate need of the 10 peak-load workers to service our 2026 contractual obligations. We
have attempted to hire U.S. workers for these positions and have been unable to meet our peak-
load needs.” Id. Employer attached service agreements for 2026 to support its need for temporary
workers. AF 17-92.
On June 15, 2026, the CO issued a Final Determination, finding that Employer failed to
overcome the two deficiencies identified in the May 28, 2026 NOD and denying certification. AF
4-14. Employer timely requested administrative review of the CO’s denial of certification. AF
1-3. On June 29, 2026, the matter was referred to BALCA and assigned to me. On June 30, 2026,
upon receipt of the Appeal File from the CO, I issued a Notice of Docketing and Expedited Briefing
Schedule. On July 13, 2026, Employer filed an appellate brief; the CO declined to file any briefing.
II. LEGAL STANDARD
The standard of review in H-2B temporary labor certification appeals is limited. A
reviewing judge may consider only “the Appeal File, the request for review, and any legal briefs
submitted.” 20 C.F.R. § 655.61(e). The request for review may contain only legal arguments and
evidence that was previously submitted to the CO prior to issuance of the final determination. Id.
§ 655.61(a)(5). After considering the evidence, the judge must affirm, reverse, or modify the CO’s
determination, or remand the case to the CO for further action. Id. § 655.61(e).
The employer bears the burden of establishing entitlement to labor certification under the
H-2B program. 8 U.S.C. § 1361; Alter & Son Gen. Eng’g, 2013-TLN-00003, PDF at 4 (Nov. 9,
2012); BMGR Harvesting, 2017-TLN-00015, PDF at 4 (Jan. 23, 2017). BALCA will affirm the
CO’s determination unless the employer establishes that the determination was arbitrary,
capricious, or otherwise not in accordance with the law. See The Yard Experts, Inc., 2017-TLN-
00024, PDF at 6 (Mar. 24, 2017).
III. DISCUSSION
An employer seeking temporary labor certification under the H-2B program must establish
its need for non-agricultural services is temporary in nature, by establishing its need for the services
- 4 -
or labor qualifies under one of the four standards of temporary need: a one-time occurrence, a
seasonal need, a peakload need, or an intermittent need, as defined by the Department of Homeland
Security (“DHS”) regulations. 20 C.F.R. §§ 655.6(a), (b). Employer in this case alleges a peakload
need. To qualify for peakload need, an employer must establish that (1) “it regularly employs
permanent workers to perform the services or labor at the place of employment”; (2) “it needs to
supplement its permanent staff at the place of employment on a temporary basis due to a seasonal
or short-term demand”; and (3) “the temporary additions to staff will not become a part of the
petitioner’s regular operation.” 8 C.F.R. § 214.2(h)(6)(ii)(B)(3); see, e.g., Masse Contracting,
2015-TLN-00026 (Apr. 2, 2015); Natron Wood Prods., 2014-TLN-00015 (Mar. 11, 2014);
Jamaican Me Clean, LLC, 2014-TLN-00008 (Feb. 5, 2014).
The CO in this matter determined, in the second NOD, that there was insufficient
information in the Application to support a finding of a temporary, peakload need, and to correct
the deficiency, the CO required supporting documentation, including but not limited to, monthly
invoices for the previous calendar year, signed service contracts for the previous calendar year,
and monthly payroll reports for the past two calendar years. AF 99. Employer did not submit any
of the required documentation identified in the NOD; instead, Employer provided its current
service agreements for the 2026 calendar year without an explanation of how the service contracts
established a peakload need for the dates requested, or why it failed to provide the specific
evidence required by the CO.
Employer’s failure to submit any of the required documentation delineated in the second
NOD is a valid basis for denial. See 20 C.F.R.§ 655.32(a) (“The employer’s failure to comply with
a Notice of Deficiency, including . . . not providing all required documentation, will result in a
denial of the Application for Temporary Employment Certification.”); Saigon Restaurant, 2016-
TLN-00053 (July 8, 2016); Munoz Enterprises, 2017-TLN-00016 (Jan. 19, 2017); Carolina
Contracting and Management, LLC, 2017-TLN-00026 (Apr. 4, 2017). The CO nonetheless
considered the alternative evidence provided by Employer (the 2026 service agreements) and
reasonably concluded that such evidence, without any specific dates of service, did not establish a
peakload need. AF 11.
On appeal, Employer does not present any arguments in support of a peakload need. Rather,
Employer’s sole argument for reversal is that the CO, in denying certification, failed to follow the
Department of Labor’s own guidance announced on September 1, 2016. AF 1-2; Er. Br. 1, 5;
- 5 -
Employment & Training Admin., U.S. Dep’t of Labor, Announcement of Procedural Change to
Streamline the H-2B Process for Non-Agricultural Employers: Submission of Documentation
Demonstrating “Temporary Need” (Sept. 1, 2016) (“9/1/16 Guidance”).4 Employer avers that in
accordance with the 9/1/16 Guidance, the CO should have accepted its Application “on its face,”
without requiring any additional supporting evidence on temporary need, based on its previous
labor certifications, including its recent certification in Case No. H-400-26004-532655. Er. Br. at
6.
Reviewing the 9/1/16 Guidance in its entirety belies Employer’s position. The 9/1/16
Guidance states the following:
To reduce paperwork and streamline the adjudication of temporary need . . . an
employer need not submit additional documentation at the time of filing the Form
ETA-9142B to justify its temporary need. It may satisfy this filing requirement
more simply by completing Section B “Temporary Need Information,” Field 9
“Statement of Temporary Need” of the Form ETA-9142B …. Other documentation
or evidence demonstrating temporary need is not required to be filed with the H-
2B application. Instead, it must be retained by the employer and provided to the
Chicago NPC in the event a Notice of Deficiency (NOD) is issued by the CO.
See 9/1/16 Guidance (emphasis added). Although employers are not required to submit supporting
documentation when filing their application, the 9/1/16 Guidance unequivocally states that
employers must provide such documentation “in the event a Notice of Deficiency (NOD) is issued
by the CO.” Id.
Moreover, the fact that an employer may have previously received certification for the
same temporary need does not preclude the CO from issuing a NOD requiring additional
documentation under the 9/1/16 Guidance:
The CO will review the employer’s statement of temporary need as well as its
recent filing history (if applicable) to determine whether the nature of the
employer’s temporary need on the current application meets the standard for
temporary need under the regulations. If the job offer has changed or is unclear, or
other employer information about the nature of its need requires further
explanation, a NOD requesting an additional explanation or supporting
documentation will be issued…. The issuance of prior certifications to the
employer does not preclude the CO from issuing a NOD to determine whether the
employer’s current need is temporary in nature.
4 Available at: FINAL_Announcement_H-2B_Submission_of_Documentation_Temporary_Need_082016.pdf.
- 6 -
See 9/1/16 Guidance (emphasis added).
The 9/1/16 Guidance further states that employers must include, in every application, a
“written statement…clearly explain[ing] the nature of the employer’s business or operations, why
the job opportunity and number of workers being requested for certification reflect a temporary
need, and how the request for the services or labor to be performed meets one of the four DHS
regulatory standards of temporary need,” and emphasizes that it is “the quality, consistency and
probative value of the information provided on the Form ETA 9142B itself that will be
determinative in the CO’s assessment of temporary need.” 9/1/16 Guidance (emphasis added). In
this case, Employer did not provide any justification for its peakload need in its Form ETA 9142B.
In its Statement of Need, Employer merely wrote: “Our start date is normally April 1st[; ] however,
we are submitting this application due to the cap being met. Therefore, we are requesting our
workers from May 02, 2026 to December 1, 2026, this year.” AF 112. The complete lack of
“probative” information in the Application supports the CO’s decision to seek further information
in a NOD.
Contrary to the Employer’s assertions, I find that it was within the CO’s discretion under
the 9/1/16 Guidance to assess temporary need and issue a second NOD requiring supporting
documentation, notwithstanding Employers’ alleged prior certifications.5 See Delta Centrifugal
LLC d/b/a Delta Centrifugal, 2022-TLN-00006 (Nov. 16, 2022) (rejecting Employer’s argument
that it was not required to submit supporting documentation to the CO regarding its temporary
need pursuant to the 9/1/16 Guidance and its history of prior successful applications); Brightview
Landscapes, LLC, 2023-TLN-00043, PDF at 13 (Mar. 16, 2023) (“An employer must file an
application eligible on its own merits. The fact that the CO may have previously approved similar
applications does not require the CO to grant subsequent applications…. An employer is required
to substantively respond to a notice of deficiency.”).
Because Employer failed to provide adequate documentation in response to the CO’s
second NOD, I find that the CO’s denial of certification for failure to establish a peakload need
under 20 C.F.R. §§ 655.6(a) & (b) was neither arbitrary or capricious, or otherwise not in
accordance with the law. Accordingly, the denial of certification is affirmed.
5 The administrative record does not contain evidence of the prior certifications or the documentation relied on in prior
certifications to support a peakload need.
- 7 -
ORDER
Accordingly, it is ORDERED that the Certifying Officer’s Final Determination denying
Employer’s Application for Temporary Employment Certification is AFFIRMED.
SO ORDERED.
For the Board:
JONATHAN C. CALIANOS
Administrative Law Judge
Boston, Massachusetts