S. EMANUEL LIN (doing business as Aptus Company) v. United States

2005-5030Court of Appeals for the Federal Circuit04.08.2005

Gesamter Gesetzestext

NOTE: Pursuant to Fed. Cir. R. 47.6, this disposition
is not citable as precedent. It is a public record.
United States Court of Appeals for the Federal Circuit
05-5030
S. EMANUEL LIN
(doing business as Aptus Company),
Plaintiff-Appellant,
v.
UNITED STATES,
Defendant-Appellee.
___________________________
DECIDED: August 4, 2005
___________________________
Before RADER, BRYSON, and LINN, Circuit Judges.
RADER, Circuit Judge.
Mr. S. Emanuel Lin d/b/a Aptus Company (Mr. Lin) appeals the decision of the
United States Court of Federal Claims denying Mr. Lin’s claim of wrongful termination of
a contract with the United States Army Corps of Engineers (Government). Because
substantial evidence supports the Court of Federal Claims’ finding that the Government
terminated Mr. Lin for default, this court affirms.
I
Mr. Lin won a contract to update and automate hydroelectric power equipment at
the Saulte Ste. Marie Hydroelectric Power Plant in Michigan for $1,225,110. Aptus Co.
v. United States, No. 01-362C, slip op. at 3 (Fed. Cl. Aug. 30, 2004) (Decision).

-- 1 of 5 --

Although Mr. Lin was the lowest bidder during the contract solicitation, the Government
became concerned that Mr. Lin, as a single-man operation, did not have the expertise
and staff required to complete the contract. Id. at 4. Mr. Lin allayed the Government’s
concerns by providing written assurances that he would recruit workers with the
necessary experience to complete the contract. Id. Consequently, Mr. Lin won the bid
and received the contract.
The contract required Mr. Lin to install government-furnished equipment (GFE)
including governor, excitation, Supervisory Control and Data Acquisition (SCADA)
equipment, and to design and install a neutral grounding system, a new switchboard
and switchgear for Unit 10, a 125 VDC distribution panel, and several other smaller
items. Id. at 3 & n.5. The contract required completion within 450 days after the
Government issued a Notice to Proceed, which issued on December 9, 1998. Id. at 4.
The parties executed a bilateral agreement on November 24, 1999, extending the
deadline by 150 days due to the Government’s delay in delivering the GFE, thereby
moving the deadline to July 31, 2000. Id. at 4 n.7.
On January 14, 2000, the Government issued a cure notice to Mr. Lin because
he “was unable to make sufficient progress under the contract, failed to comply with
required submittals, failed to provide a realistic work schedule, and had inadequate
staffing to perform the work required under the contract.” Id. at 4. Mr. Lin responded
and the cure notice did not mature into a termination for default at that time. Id. at 6.
However, the Government requested the Hydroelectric Design Center (HDC) to inspect
Mr. Lin’s work. Id. The HDC prepared a full report of its findings and recommended
terminating Mr. Lin for default. Id.
05-5030 2

-- 2 of 5 --

The Government issued a show cause notice to Mr. Lin on May 1, 2000, noting
the findings of the HDC and Mr. Lin’s failure to cure the conditions in the January 14,
2000 cure notice. Id. After allowing Mr. Lin an opportunity to cure the conditions in the
show cause notice, the Government terminated the contract for cause on June 30,
2000. Id. at 7.
Mr. Lin, acting pro se, filed suit in the Court of Federal Claims alleging wrongful
termination and modification of the contract. Id. at 2. The trial court upheld the
Government’s termination for cause based on Mr. Lin’s lack of satisfactory progress
under the contract, id. at 34, and violations of contract requirements, id. at 37. Mr. Lin
appeals to this court, which has jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
II
This court reviews issues of contract interpretation de novo. Galaxy, Inc. v.
United States, 998 F.2d 953, 957 (Fed. Cir. 1993). This court reviews factual findings
for clear error. Merck & Co. v. Teva Pharms., Inc., 395 F.3d 1364, 1368 (Fed. Cir.
2005). A factual finding is clearly erroneous when “the reviewing court on the entire
evidence is left with the definite and firm conviction that a mistake has been committed.”
Id. (quoting United States v. U.S. Gypsum Co., 333 U.S. 364, 395 (1948)).
Mr. Lin argues that the trial court applied the wrong standard in reviewing the
Government’s decision to terminate the contract for cause. The trial court, citing
Seaboard Lumber Co. v. United States, 903 F.2d 1560, 1562 (Fed. Cir. 1990), properly
stated that it was reviewing the termination for default de novo. Decision at 11. The
trial court went on to provide a forty-page opinion thoroughly analyzing the facts and
05-5030 3

-- 3 of 5 --

issues under a de novo standard. This court finds that the trial court applied the correct
standard of review.
Mr. Lin next argues that the Government did not carry its burden of proof to
establish default termination. As regards default termination for lack of progress, the
trial court found in favor of the Government based on (1) the percentage of work
completed and the amount of time remaining under the contract, (2) the problems with
subcontractors and suppliers, (3) the failure to meet goals for progress of the work, and
(4) the over-all evidence of Mr. Lin’s failure to prosecute his work under the contract. Id.
at 31. Specifically, the trial court found that “(i) approximately 68% of the work
remained to be completed under the contract at the termination date, and, at best, a
mere 23.33% of the construction time remained, (ii) [Mr. Lin] experienced significant
difficulties with subcontractors, [ ] (iii) Mr. Lin was unable to conform to the scheduling
representations he made,” and (iv) Mr. Lin’s efforts frequently resulted in work that was
unsatisfactory. Id. Much of the evidence supporting these factual findings was
introduced by and through Mr. Lin. These findings are not clearly erroneous.
The Court of Federal Claims also ruled against Mr. Lin’s defense of excusable
delay. Specifically, the trial court did not consider the Government’s delay in delivering
the GFE as creating excusable delay because the parties agreed to extend the contract
deadline by 150 days as compensation for that delay. Id. at 32. The trial court also did
not consider delays caused by late delivery of the SCADA equipment because the
termination decision did not rely on the non-completion of the SCADA installation. Id.
The trial court considered, and rejected, Mr. Lin’s argument that the GFE was
05-5030 4

-- 4 of 5 --

incomplete and had defective parts upon delivery, thereby causing excusable delay. Id.
at 33.
Mr. Lin had the burden to demonstrate that the defects in the GFE delayed
activities on the critical path to the completion of the contract. The trial court found that
defects of the GFE did not affect the critical path because Mr. Lin “had ample design
work that was able to be completed without reference to the GFE.” Id. Mr. Lin also
represented to the Government that his updated schedules were achievable despite the
problems with the GFE. Because substantial evidence supports these facts, this court
affirms the Court of Federal Claims’ finding that Mr. Lin’s delay was not excusable.
Because this court upholds the Government’s default termination for lack of
sufficient progress, this court does not reach the additional grounds upon which the
Court of Federal Claims sustained the Government’s default termination.
05-5030 5

-- 5 of 5 --