CourtListener 9507674•Lusardi Construction Co. v. Dept. of Industrial Relations CA4/1
Lusardi Construction Co. v. Dept. of Industrial Relations CA4/1
CourtListener 9507674Calctapp28.05.2024
Gesamter Gesetzestext
Filed 5/28/24 Lusardi Construction Co. v. Dept. of Industrial Relations CA4/1
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.
COURT OF APPEAL, FOURTH APPELLATE DISTRICT
DIVISION ONE
STATE OF CALIFORNIA
LUSARDI CONSTRUCTION D081704
COMPANY,
Plaintiff and Appellant,
(Super. Ct. No.
v. 37-2020-00021750-CU-WM-NC)
DEPARTMENT OF INDUSTRIAL
RELATIONS et al.,
Defendants and Respondents,
DIVISION OF LABOR STANDARDS
ENFORCEMENT,
Real Party in Interest and
Respondent.
APPEAL from an order of the Superior Court of San Diego County,
Robert P. Dahlquist, Judge. Affirmed.
Herold & Sager and Nicholas B. Salerno for Plaintiff and Appellant.
No appearance for Defendants and Respondents Department of
Industrial Relations and Katrina S. Hagen.
Lance A. Grucela for Real Party in Interest and Respondent.
Plaintiff and appellant Lusardi Construction Company’s (Lusardi)
subcontractor, Pro Works Contracting Inc. (Pro Works), violated certain
Labor Code1 provisions by failing to hire apprentices for construction of the
San Marcos K-8 School Project (the Project). Defendants and respondents
Department of Industrial Relations, its director Katrina S. Hagen (the
Director), and real party in interest and respondent, Division of Labor
Standards Enforcement (DLSE) cited Pro Works for those violations.
Following an investigation, DLSE ordered Lusardi to pay penalties for the
violations. Lusardi’s administrative appeal was unsuccessful, and it
thereafter filed a petition for writ of administrative mandamus under Code of
Civil Procedure section 1094.5, which the superior court denied.
Lusardi contends the superior court erroneously concluded that: (1) the
Director’s interpretation of former section 1777.7 subdivision (d) was proper;
(2) substantial evidence supported a finding Lusardi knew of Pro Works’s
violations; (3) section 1743, subdivision (a)’s joint and several liability
provision applied; (4) substantial evidence supported the amount of the
penalty assessed against Pro Works; and (5) Lusardi was not denied due
process. We affirm.
FACTUAL AND PROCEDURAL BACKGROUND
In 2014, San Marcos Unified School District (the District) awarded
Lusardi a contract to construct the Project. Lusardi subcontracted with Pro
Works to install the iron reinforcing work for the Project.
1 Undesignated statutory references are to the 2014 versions of the
Labor Code. We grant the parties’ separate requests to take judicial notice of
different items of legislative history under Evidence Code section 452;
however, we deny the portion of Lusardi’s request seeking judicial notice of a
decision of the Department of Industrial Relations because that decision is
not necessary for our disposition of this appeal.
2
The DLSE Investigation
In 2015, DLSE opened an investigation into a complaint that Pro
Works violated former section 1777.5 by failing to: (1) provide contract award
information; (2) request dispatch of apprentices from applicable apprentice
committees; (3) employ registered apprentices in compliance with a required
apprentice to journeyperson ratio; and (4) make certain required training
fund contributions to an approved apprenticeship program.
Deputy Labor Commissioner Kari Anderson served the following
documents on Lusardi and Pro Works: a “notice of investigation,” a “request
for payroll records,” a “statement of employer payments” form, and a “notice
of apprenticeship compliance” form, which in turn sought Department of
Apprenticeship Standards (DAS) forms2 and “accounting and proof of
2 The notice of apprenticeship compliance form states that a DAS 140
form relates to “contract award information (or equivalent) with proof of
submission to applicable apprenticeship committees,” and a DAS 142 form
relates to a “request for dispatch of an apprentice (or equivalent) with proof of
submission to applicable apprenticeship committees.” (Some capitalization
omitted.)
The documents sought are routinely used by contractors who are
awarded public contracts. Former section 1777.5 subdivision (e) provided:
“Before commencing work on a contract for public works, every contractor
shall submit contract award information to an applicable apprenticeship
program that can supply apprentices to the site of the public work. The
information submitted shall include an estimate of journey[person] hours to
be performed under the contract, the number of apprentices proposed to be
employed, and the approximate dates the apprentices would be employed. A
copy of this information shall also be submitted to the awarding body, if
requested by the awarding body. Within 60 days after concluding work on
the contract, each contractor and subcontractor shall submit to the awarding
body, if requested, and to the apprenticeship program a verified statement of
the journey[person] and apprentice hours performed on the contract. The
information under this subdivision shall be public. The apprenticeship
programs shall retain this information for 12 months.”
3
payment of the training fund contributions to California Apprenticeship
Council or approved apprenticeship program.” (Some capitalization omitted.)
The entities responded differently to Anderson’s documents request.
The District provided some information but stated Lusardi “holds all certified
payroll [records (CPR’s)] on sub-contractors.” Pro Works provided some
CPR’s but only after the Project was completed, claiming the tardy
submission was due to staff turnover. Lusardi provided no information, and
Anderson testified she did not hear from or communicate with any Lusardi
representative during her investigation.
Anderson issued a “Penalty Review” summarizing her findings. She
concluded that in February 2015, Pro Works violated the statutes and
regulations relating to apprenticeships by failing to submit compliant DAS
140 and 142 forms and other required information. Anderson found that Pro
Works “failed to hire any apprentices.” She also concluded Pro Works had a
“history” of apprentice violations, and specifically listed their dates and
descriptions. Anderson concluded the penalty should be assessed based on
Pro Works’s failure to comply with four out of the five factors set forth in
former section 1777.7, subdivision (f).3 Anderson testified that Senior
Deputy Labor Commissioner Michael Nagtalon reviewed her report and
3 Former section 1777.7, subdivision (f) listed five factors the Labor
Commissioner “shall consider” in calculating the monetary penalty.
“Whether the party has committed other violations of section 1777.5. [¶]
Whether, upon notice of the violation, the party took steps to voluntarily
remedy the violation. [¶] Whether, and to what extent, the violation resulted
in lost training opportunities for apprentices. [And] [¶] Whether, and to
what extent, the violation otherwise harmed apprentices or apprenticeship
programs.” The fifth factor, and the one Anderson did not find applicable
here, was “whether the violation was intentional.”
4
assessed penalties in the amount of $30,800, consisting of $200 per each of
154 days of section 1777.5 violations.
Lusardi timely filed a request for review of Anderson’s decision with
the Director.
Before the review hearing started, the hearing officer ruled the 2014
version of the relevant Labor Code provisions and regulations would apply,
based on the Project’s bid advertisement date. He also ruled regarding the
burden of proof that “DLSE will have to come forward with sufficient
evidence to provide prima facie support for the penalty assessment, including
evidence of Lusardi’s knowledge of the alleged violation by the subcontractor
or Lusardi’s alleged failure to comply with the requirements of [former
section] 1777.7[, subdivision] (d).[4] If this is done, Lusardi will have . . . the
4 Former section 1777.7, subdivision (d) provided: “If a subcontractor is
found to have violated Section 1777.5, the prime contractor of the project is
not liable for any penalties under subdivision (a), unless the prime contractor
had knowledge of the subcontractor’s failure to comply with the provisions of
Section 1777.5 or unless the prime contractor fails to comply with any of the
following requirements: [¶] (1) The contract executed between the contractor
and the subcontractor or the performance of work on the public works project
shall include a copy of the provisions of Sections 1771, 1775, 1776, 1777.5,
1813, and 1815. [¶] (2) The contractor shall continually monitor a
subcontractor’s use of apprentices required to be employed on the public
works project pursuant to subdivision (d) of Section 1777.5, including, but not
limited to, periodic review of the certified payroll of the subcontractor. [¶] (3)
Upon becoming aware of a failure of the subcontractor to employ the required
number of apprentices, the contractor shall take corrective action, including,
but not limited to, retaining funds due the subcontractor for work performed
on the public works project until the failure is corrected. [¶] (4) Prior to
making the final payment to the subcontractor for work performed on the
public works project, the contractor shall obtain a declaration signed under
penalty of perjury from the subcontractor that the subcontractor has
employed the required number of apprentices on the public works project.”
5
burden of proof set forth in [California Code of Regulations, title 8, section]
232.50[, subdivision] (b).”5
On the first day of the hearing, Lusardi’s counsel initially stated three
of its representatives as well as Nagtalon would testify. Counsel stated
Nagtalon was a necessary witness. But Nagtalon was not available. DLSE’s
sole witness, Anderson, was the only person who testified that day.
On the second and last day of the hearing, Lusardi’s counsel sought the
testimony of Nagtalon, who was under subpoena. DLSE’s counsel explained
Nagtalon was unavailable as he was outside of the country, but he offered to
produce Nagtalon for a rescheduled hearing. However, Lusardi elected not to
request a continuance to obtain Nagtalon’s testimony or to put on its case.
Instead, its counsel stated, “Lusardi will rest without presenting any further
evidence and will not move any of Lusardi’s exhibits into evidence in this
matter.” Counsel explained: “We are not going to present any evidence
because we feel very strongly the Labor Commissioner has failed to meet its
burden in this matter.”
The Director’s Review
The Director affirmed the hearing officer’s findings, concluding DLSE
met its burden to present evidence showing prima facie support for the
penalty assessment, including that Lusardi knew of Pro Works’s violations
and was liable for the penalties. The Director summarized Anderson’s
testimony at length. In concluding Pro Works violated the apprentice
requirements, the Director explained that former section 1777.5 and the
applicable regulations required an employer who had obtained certain public
work contracts to hire apprentices to perform one hour of work for every five
5 California Code of Regulations, title 8, section 232.50, subdivision (b)
was subsequently repealed.
6
hours of work performed by journeypersons in the applicable craft or trade.
She stated that under the applicable regulation, “a contractor shall not be
considered in violation of the 1:5 ratio requirement if it has properly
requested the dispatch of apprentices and no apprenticeship committee in the
geographic are[a] of the public works project dispatches apprentices during
the pendency of the project, provided the contractor made the request in
enough time to meet the required ratio.” The Director concluded, “There is no
dispute that Pro Works failed to employ any apprentices on the Project.”
The Director also concluded Pro Works violated former section 1777.5,
subdivision (e) and the applicable regulations, including by failing to submit
proper contract award information to an apprenticeship program. The
Director summarized Pro Works’s violations: “Pro Works had first assigned
an Iron Worker journeyperson to work on the Project on December 23, 2014.
In light of that evidence, it was reasonable for DLSE to infer that Pro Works
knew of its apprentice needs by February 23, 2015. Indeed, given all the
facts in the record, it is also reasonable to infer that Pro Works never had any
intention of employing apprentices on this Project in December of 2014, in
February of 2015, or even in May of 2015 when it finally submitted a
complete and valid DAS 140 form. That Anderson did not directly inquire of
Pro Works or make a finding as to the state of Pro Works’[s] knowledge of
apprentice needs does not detract from the record of Pro Works’[s] violations
in this case.”
The Director further concluded Pro Works failed to properly request
dispatch of apprentices, adding: “Pro Works’[s] violations of apprentice
requirements are deemed to be ‘knowing’ within the meaning of [former]
7
section 1777.7, subdivision (a)(1).6 This is so because, as reflected in DLSE
records, Pro Works had previously been found to have violated [former]
section 1777.5.”
The Director stated DLSE presented prima facie support for the
calculation of penalty days. The Director further pointed out Anderson
checked four of the boxes on a pre-printed form corresponding to the former
section 1777.7, subdivision (f) factors. The Director reasoned: “According to
Anderson’s testimony and the penalty review, Nagtalon considered the five
penalty factors, approved the penalty review prepared by Anderson, and set
the penalty rate at $200.00 per violation ‘due to the nature of the violations,’
before returning the penalty review to Anderson for preparation of the
assessment. These facts establish a prima facie showing that Nagtalon
reviewed the summary of the investigation prepared by Anderson, considered
the statutory factors, and properly exercised his discretion in setting the
penalty rate.” (Some capitalization omitted.)
6 Former section 1777.7, subdivision (a)(1) provided that a contractor or
subcontractor that is determined by the Labor Commissioner to have
knowingly violated former section 1777.5 shall forfeit as a civil penalty $100
per day of noncompliance, but if there are subsequent violations within a
three-year period, the penalty shall be not more than $300 for each full
calendar day of noncompliance.
8
The Director concluded the penalty rate per violation was appropriately
high.7 She pointed out that Pro Works’s violations were intentional and it
had a history of other apprentice violations. Moreover, Pro Works took few
meaningful steps to voluntarily remedy its violations upon its receipt of the
initial packet, which occurred before the end of the Project.
The Director made a specific finding Lusardi was liable for the penalty
assessed because under former section 1777.7 subdivision (a)’s first prong,
“DLSE produced evidence that Lusardi knew about the ongoing apprentice
violations by Pro Works, and that it possessed this knowledge while the
Project was still underway and while Pro Works was using ironworker
journeypersons on the Project. DLSE’s initial investigation packet, received
by Lusardi on April 24, 2015, placed Lusardi on notice that DLSE had a
7 The Director concluded: “DLSE properly calculated the number of days
that Pro Works was in violation of the apprenticeship requirements. . . .
DLSE could have extended the penalty period back to ten days from the
execution of the subcontract, but instead DLSE took the more conservative
course and counted 135 penalty days from the day after the first day Pro
Works had workers on the Project (December 22, 2014) to the May 7, 2015
date of the first valid DAS 140 form that Pro Works submitted. To those 135
penalty days, DLSE properly added another 19 days’ worth of ratio
violations, representing the number of work days that Pro Works had
journeypersons on the Project with no apprentices between May 7, 2015, and
June 23, 2015, Pro Works’[s] last day on the Project. [¶] The best evidence
for the duration of both penalties would have been a complete set of CPR[’]s.
However, the copy admitted into evidence at the hearing ends on March 28,
2015, and is therefore incomplete, in and of itself. . . . The gap in the
evidentiary record between March 28, 2015, and June 23, 2015, was bridged
by Anderson’s oral testimony, the penalty review Anderson prepared, and the
DAS 142 forms prepared by Pro Works in May and June 2015. Altogether,
this evidence provides prima facie support for the duration of the penalty
period as calculated by DLSE, even in the absence of a complete set of Pro
Works’[s] CPR[’]s. Lusardi presented no evidence to carry its burden to
disprove the basis for, or the accuracy of, DLSE’s showing as to the number of
penalty days.” (Footnote and some capitalization omitted.)
9
complaint that Pro Works was not in compliance with section 1777.5. DLSE’s
packet specified the nature of the alleged violations, most notably on the
notice of apprenticeship compliance, where Lusardi and this Project were
identified. On April 29, 2015, Pro Works’s principal Gary Lane informed
Anderson that Lusardi was withholding a retention from Pro Works in
connection with the complaint about apprentice violations.” (Some
capitalization omitted.)
The Director added: “In this case, DLSE produced prima facie evidence
that Lusardi had knowledge of Pro Works’[s] apprentice violations, thus
satisfying the first prong of [former section 1777.7,] subdivision (d). This
conclusion could have conceivably been rebutted by Lusardi, but Lusardi did
not deny it had knowledge. Had Lusardi denied knowledge, evidence may
have been explored as to whether Lusardi failed to comply with the second
prong of subdivision (d). However, in the absence of such evidence, it is
reasonable to infer that Lusardi possessed knowledge, thereby depriving
Lusardi of the safe harbor from liability for Pro Works’[s] violations.”
The Director rejected Lusardi’s claim of due process violations: “Given
DLSE’s evidence supporting a prima facie showing of Lusardi’s knowledge of
actual and ongoing apprentice violations by Pro Works during the course of
the Project, and given the opportunity to be heard in the form of the hearing,
Lusardi was not deprived of its due process rights. Lusardi was put on notice
by the contents of DLSE’s initial packet, and it cannot plausibly assert that
its potential liability was not manifest from the start of DLSE’s investigation.
. . . Further, by virtue of section 1743 and former section 1777.7, Lusardi was
on notice that its liability was at issue.” (Footnote omitted.)
10
Writ Proceedings
Lusardi filed a petition for writ of administrative mandate arguing the
Director’s decision should be invalidated: “[DLSE] acted in excess of its
authority and contrary to [former] sections 1777.5 and 1777.7 in issuing an
excessive and unsupported civil wage and penalty assessment against [Pro
Works] for alleged apprentice employment violations. In turn, the [Director]
improperly affirmed the assessment and, in direct contravention to the rule of
law set forth in [former] section 1777.7 subdivision (d) that a prime
contractor is not liable for the apprentice violations of a subcontractor, found
that Lusardi is liable for the assessment against its subcontractor without
sufficient evidence to show that Lusardi either had knowledge of Pro
Works’[s] alleged violation or that Lusardi failed to comply with any of the
requirements of [former section 1777.7] subdivision (d)(1)-(4). In doing so,
the [Director] proceeded in excess of her jurisdiction, without affording
Lusardi a fair hearing, and prejudicially abused her discretion.”
Lusardi further argued, “The DLSE failed to produce . . . Nagtalon
pursuant to a timely served subpoena to compel his attendance at the
hearing on merits in order to allow Lusardi to examine him as to how the
daily penalty rate assessed against Pro Works was determined pursuant to
[former] section 1777.7, subdivision (f).” (Some capitalization omitted.)
Lusardi also sought declaratory relief “as to the legality of the decision
and order and the DLSE’s enforcement against [it] under section[ ] 1743 and
[former section] 1777.7[,] including a determination of the question of
validity.” (Some capitalization omitted.)
The superior court denied Lusardi’s writ petition, interpreting former
section 1777.7 subdivision (d) in the disjunctive: “Based on the plain
language of the statute, the [c]ourt believes that the Legislature intended for
11
the [Director] to have the burden of establishing that petitioner had
knowledge of the subcontractor’s failure to comply with [former section]
1777.5 or that petitioner failed to comply with any [of] the requirements set
forth in [former section 1777.7 subdivision] (d)(1)-(4). [¶] . . . [¶] The
Director focused on the first prong of [former section] 1777.7[,subdivision] (d),
and made a finding that Lusardi had knowledge of the subcontractor’s
apprentice violations.”
The court further found that substantial evidence supported the
findings “relating to the amount of the penalty assessment” based on the
Director’s independent review of the penalty amount. It also found the CPR’s
provided substantial evidence showing Lusardi knew of Pro Works’s failure to
hire any apprentices.
The court rejected Lusardi’s claim it was denied due process: “[A]s a
result of the notices given to Lusardi, and the applicable provisions of the law
pertaining to public works projects, the [c]ourt is satisfied that Lusardi was
on notice of the potential for being held jointly and severally liable for Pro
Works’[s] apprentice hiring violations.”
The court also ruled: “[T]he Director had the obligation to, and did,
conduct a de novo consideration of any penalties to be assessed. As such, . . .
Nagtalon was not the ultimate decision-maker concerning the amount of the
penalty. While the [c]ourt believes that the better practice for the DLSE
would have been to produce . . . Nagtalon for examination at the
administrative hearing, the [c]ourt is not persuaded that the failure to
produce . . . Nagtalon resulted in a violation of Lusardi’s due process rights.”
12
DISCUSSION
I. Interpretation of Former Section 1777.7, Subdivision (d)
Lusardi contends the court erroneously adopted the Director’s
“interpretation and unprecedented application of the two prongs of [former]
section 1777.7, subdivision (d)(1)-(4).” (Bold and capitalization omitted.)
A. Standard of Review
“Statutory construction is a question of law we decide de novo.
[Citation.] Our primary objective in interpreting a statute is to determine
and give effect to the underlying legislative intent. [Citation.] Intent is
determined foremost by the plain meaning of the statutory language. If the
language is clear and unambiguous, there is no need for judicial construction.
When the language is reasonably susceptible of more than one meaning, it is
proper to examine a variety of extrinsic aids in an effort to discern the
intended meaning. We may consider, for example, the statutory scheme, the
apparent purposes underlying the statute and the presence (or absence) of
instructive legislative history.” (Starving Students, Inc. v. Department of
Industrial Relations (2005) 125 Cal.App.4th 1357, 1363.)
The California Supreme Court has stated: “The conditions of
employment on construction projects financed in whole or in part by public
funds are governed by the prevailing wage law [set forth in sections 1720
through 1861].” (Lusardi Construction Co. v. Aubrey (1992) 1 Cal.4th 976,
985.) “This statutory scheme also governs the employment of apprentices.
Section 1777.5 requires the employment of apprentices on public works
projects under the terms of a statutory formula, and mandates that the
awarding body insert stipulations in the construction contract requiring
compliance with the apprenticeship provisions of the prevailing wage law.
Section 1777.7 specifies sanctions for failure to comply with the
13
apprenticeship requirements, including debarment from public works
contracting and monetary penalties.” (Lusardi v. Aubry, supra, at p. 986, &
fn. 2.)
In interpreting the disjunctive parts of former section 1777.7,
subdivision (d), we turn to one court’s discussion of the challenges in
interpreting the conjunction “or”: “ ‘The fact is that there is nothing very
plain about the use of the connective “or” in legal drafting.’ [Citation.]
‘ “Sometimes it joins alternatives; sometimes it doesn’t. Sometimes or means
and; sometimes it doesn’t[ ].” ’ [Citation.] Additionally, if ‘or’ is a disjunctive
connector, sometimes it connects words in the inclusive sense (i.e., A or B, or
both); other times, it connects words in the exclusive sense (i.e., A or B, but
not both). [Citation.] Thus, the potential ambiguity created by ‘or’ is not one
dimensional.” (Dow v. Honey Lake Valley Resource Conservation Dist. (2021)
63 Cal.App.5th 901, 903-904.)
“ ‘ “Legal sources differ on which meaning of ‘or’ [(as inclusive or
exclusive)] is authoritative. In the realm of symbolic logic, the exclusive ‘or,’
otherwise known as the exclusive disjunction, means that only one of the
propositions or terms joined by the disjunction can be true. ‘Jim is eight or
nine years old’ is exemplary of an exclusive disjunction because only one
proposition in the disjunction can be true. On the other hand, an inclusive
disjunction assumes that either one or both of the terms or propositions on
either side of the disjunction are true. A sentence like, ‘X will call or e[-]mail
Y,’ does not necessarily denote an exclusive disjunction, but rather, it leaves
open the possibility that X could call and e[-]mail Y. Essentially, an inclusive
disjunction allows the possibility of either option, or both, which is also the
literal meaning of and/or.” ’ [Citation.] ‘[I]t has been asserted that, in legal
drafting, it is more often the case that the connective “or” is used in the
14
inclusive sense’ [citation] and ‘[i]n ordinary English, the phrase “P or Q” on
its own often suggests the inclusive sense of “or.” ’ ” (Dow v. Honey Lake
Valley Resource Conservation Dist., supra, 63 Cal.App.5th at pp. 913-914.)
We conclude the court did not err in interpreting former section 1777.7,
subdivision (d). The statute’s plain language provides two inclusive and
alternative ways for imposing liability on a prime contractor for penalties
resulting from the subcontractor’s violations of former section 1777.5.
Specifically, first, the prime contractor is not liable for the penalties “unless
[it] had knowledge of the subcontractor’s failure to comply” with the statute;
or, second, it is not liable for the penalties “unless the prime contractor fails
to comply with any of the” requirements set forth in the remainder of section
(d). (Former § 1777.7, subd. (d).) The DLSE properly determined that under
former section 1777.7 subdivision (d)’s first prong, Lusardi had knowledge of
Pro Works’s failure to comply with the applicable apprentice provisions set
forth in former section 1777.5. That finding sufficed for the court to conclude
Lusardi was liable for Pro Works’s violations of former section 1777.7,
subdivision (d).
Our conclusion regarding the proper interpretation of former section
1777.7, subdivision (d) is bolstered by another court, which interpreted a
15
parallel provision in section 1775, subdivision (b),8 that is also phrased in the
disjunctive, as follows: “[T]he prime contractor is not liable for any monetary
penalties unless the prime contractor knew the subcontractor had not paid
prevailing wages to the subcontractor’s workers or unless the prime
contractor fails to provide for the payment of prevailing wage in its contract
with the subcontractor; to monitor such payments by reviewing the payroll
records of the subcontractor; to undertake withholding, if necessary; and to
obtain an affidavit from the subcontractor asserting payment was made.”
(Violante v. Communities Southwest Development & Construction Co. (2006)
138 Cal.App.4th 972, 979, bold added.)
8 Section 1775, subdivision (b) provides: “If a worker employed by a
subcontractor on a public works project is not paid the general prevailing rate
of per diem wages by the subcontractor, the prime contractor of the project is
not liable for any penalties under subdivision (a) unless the prime contractor
had knowledge of that failure of the subcontractor to pay the specified
prevailing rate of wages to those workers or unless the prime contractor fails
to comply with all of the following requirements: [¶] (1) The contract
executed between the contractor and the subcontractor for the performance of
work on the public works project shall include a copy of the provisions of this
section and Sections 1771, 1776, 1777.5, 1813, and 1815. [¶] (2) The
contractor shall monitor the payment of the specified general prevailing rate
of per diem wages by the subcontractor to the employees, by periodic review
of the certified payroll records of the subcontractor. [¶] (3) Upon becoming
aware of the failure of the subcontractor to pay his or her workers the
specified prevailing rate of wages, the contractor shall diligently take
corrective action to halt or rectify the failure, including, but not limited to,
retaining sufficient funds due the subcontractor for work performed on the
public works project. [¶] (4) Prior to making final payment to the
subcontractor for work performed on the public works project, the contractor
shall obtain an affidavit signed under penalty of perjury from the
subcontractor that the subcontractor has paid the specified general prevailing
rate of per diem wages to his or her employees on the public works project
and any amounts due pursuant to Section 1813.” (Italics added.)
16
In Lusardi’s alternative interpretation of former section 1777.7,
subdivision (d), that provision “is intended to preclude the prime contractor’s
liability for a subcontractor’s apprentice violation unless the prime contractor
possessed knowledge of the subcontractor’s apprentice violations or, if so,
failed to comply with the requirements set forth in subsection[s] (1)-(4).”
(Italics added, bold and some capitalization omitted.) Lusardi’s addition of
those two words, “if so,” completely alters the meaning of the statute in a way
that the Legislature did not contemplate, and that we therefore cannot
accept. “In the construction of a statute or instrument, the office of the Judge
is simply to ascertain and declare what is in terms or in substance contained
therein, not to insert what has been omitted, or to omit what has been
inserted.” (Code Civ. Proc., § 1858; Vikco Ins. Services, Inc. v. Ohio Indemnity
Co. (1999) 70 Cal.App.4th 55, 61.) “Thus, ‘ “. . . ‘[i]n construing . . . statutory
provisions a court is not authorized to insert qualifying provisions not
included and may not rewrite the statute to conform to an assumed intention
which does not appear from its language.’ ” ’ ” (Vikco, at p. 62.)
II. Substantial Evidence that Lusardi Knew of Pro Works’s Violations
Lusardi contends the superior court erroneously concluded that
substantial evidence supported the Director’s finding Lusardi had knowledge
of Pro Works’s apprentice violations. It specifically contends that no evidence
showed Lusardi was provided the CPR’s that Pro Works produced at trial.
Lusardi further contends the CPR’s do not facially demonstrate whether Pro
Works’s failure to employ apprentices on the project was a violation of any
apprentice requirements, and those records have no bearing on whether Pro
Works submitted contract award information to an applicable apprentice
program. Finally, Lusardi contends Anderson’s testimony and case notes
17
cannot support the finding Lusardi withheld a retention from Pro Works in
connection with the complaint about apprentice violations.
A superior court’s review of an agency’s adjudicatory administrative
decision under Code of Civil Procedure section 1094.5 is subject to two
possible standards depending on the nature of the rights involved. (Mann v.
Department of Motor Vehicles (1999) 76 Cal.App.4th 312, 320.) If the
administrative decision involved or substantially affected a “fundamental
vested right,” the superior court exercises its independent judgment upon the
evidence disclosed in a limited trial de novo in which the court must examine
the administrative record for errors of law and exercise its independent
judgment upon the evidence. (Bixby v. Pierno (1971) 4 Cal.3d 130, 143-144
(Bixby); Code Civ. Proc., § 1094.5, subd. (c).) The theory behind this kind of
review is that abrogation of a fundamental vested right “is too important to
the individual to relegate it to exclusive administrative extinction.” (Bixby,
at p. 144.) Where no fundamental vested right is involved, the superior
court’s review is limited to examining the administrative record to determine
whether the adjudicatory decision and its findings are supported by
substantial evidence in light of the whole record. (Bixby, at pp. 143-144.)
Substantial evidence must be “ ‘of ponderable legal significance,’ ” which is
reasonable in nature, credible and of solid value. (Kuhn v. Department of
General Services (1994) 22 Cal.App.4th 1627, 1633.)
“Regardless of the nature of the right involved or the standard of
judicial review applied in the trial court, an appellate court reviewing the
superior court’s administrative mandamus decision always applies a
substantial evidence standard. [Citations.] But depending on whether the
trial court exercised independent judgment or applied the substantial
evidence test, the appellate court will review the record to determine whether
18
either the trial court’s judgment or the agency’s findings, respectively, are
supported by substantial evidence. [Citation.] If a fundamental vested right
was involved and the trial court therefore exercised independent judgment, it
is the trial court’s judgment that is the subject of appellate court review.
[Citations.] On the other hand, if the superior court properly applied
substantial evidence review because no fundamental vested right was
involved, then the appellate court’s function is identical to that of the trial
court. It reviews the administrative record to determine whether the
agency’s findings were supported by substantial evidence, resolving all
conflicts in the evidence and drawing all inferences in support of them.
[Citations.] [¶] If the administrative findings are supported by substantial
evidence, the next question is one of law—whether those findings support the
agency’s legal conclusions or its ultimate determination. [Citation.] If the
administrative record reveals the theory upon which the agency has arrived
at its ultimate decision, the decision should be upheld so long as the agency
found those facts that as a matter of law are essential to sustain the
decision.” (JKH Enterprises, Inc. v. Department of Industrial Relations (2006)
142 Cal.App.4th 1046, 1058, fn. omitted.) Here, as the trial court reviewed
the administrative record for substantial evidence, we apply that same
standard to the agency’s findings.
Former section 1777.5, subdivision (d) provides: “When the contractor
to whom the contract is awarded by the state or any political subdivision, in
performing any of the work under the contract, employs workers in any
apprenticeable craft or trade, the contractor shall employ apprentices in at
least the ratio set forth in this section and may apply to any apprenticeship
program in the craft or trade that can provide apprentices to the site of the
public work for a certificate approving the contractor under the
19
apprenticeship standards for the employment and training of apprentices in
the area or industry affected.” Former section 1777.5, subdivision (g)
specifies: “The ratio of work performed by apprentices to journey[persons]
employed in a particular craft or trade on the public work may be no higher
than the ratio stipulated in the apprenticeship standards under which the
apprenticeship program operates where the contractor agrees to be bound by
those standards, but, except as otherwise provided in this section, in no case
shall the ratio be less than one hour of apprentice work for every five hours of
journey[person] work.”
The record establishes that the District reported to Anderson that
Lusardi kept the CPR’s for the Project. That would be consistent with former
section 1776, subdivision (a)’s requirement: “Each contractor and
subcontractor shall keep accurate payroll records, showing the name,
address, social security number, work classification, straight time and
overtime hours worked each day and week, and the actual per diem wages
paid to each journey[person], apprentice, worker, or other employee employed
by him or her in connection with the public work. Each payroll record shall
contain or be verified by a written declaration that it is made under penalty
of perjury, stating both of the following: [¶] (1) The information contained in
the payroll record is true and correct. [¶] (2) The employer has complied
with the requirements of Sections 1771, 1811, and 1815 for any work
performed by his or her employees on the public works project.”
Anderson concluded the CPR’s did not show that Pro Works recorded
any apprentice hours worked. It follows that Pro Works failed to comply with
the ratio of apprentice journeypersons ratio set forth in former section 1777.5,
subdivision (a). As nothing in the record contradicts Andersons’s finding, the
20
Director did not err by concluding that Lusardi knew, based on the CPR’s it
retained, that Pro Works did not hire any apprentices.
III. Section 1743’s Joint and Several Liability Provision
Lusardi contends, “Although it is not clear whether the Superior Court
relied on the application of any joint and several provisions contained in
section 1743[, subdivision] (a) in any meaningful way, the appellant is merely
advising the court that it does not apply to create any sort of presumption
that must be overcome by operation of [former section] 1777.7 [, subdivision]
(d).” (Some capitalization omitted.) Lusardi relies on a case issued by the
Director of Industrial Relations (Matter of W.A. Thomas Company, Inc.,
Director of Industrial Relations (July 26, 2017) No. 12-0106-PWH) and
argues that “any analysis of the legislative intent behind [former section]
1777.7[,subdivision] (d) should begin with a presumption that a prime
contractor is not liable for a subcontractor’s apprentice violations unless the
exceptions to this rule are found to apply.”
The DLSE counters that the legislative history of section 1743
demonstrates its applicability. It also argues Lusardi’s reliance on the
administrative decision is misplaced as it is not precedential and, in any
event, it does not state the conclusion for which Lusardi cites it, namely that
section 1743, subdivision (a) “applies to penalties for wage violations” and not
to penalties for violations of the Labor Code’s apprenticeship provisions.
Section 1743, subdivision (a)’s language is plain. It provides: “The
contractor and subcontractor shall be jointly and severally liable for all
amounts due pursuant to a final order under this chapter or a judgment
thereon. The Labor Commissioner shall first exhaust all reasonable remedies
to collect the amount due from the subcontractor before pursuing the claim
against the contractor.” Under this statue, both the contractor and
21
subcontractor are jointly and severally liable for the penalties due. The
Director’s order here is a final order under the prevailing laws, and is
encompassed by this statute.
In light of the above, we need not rely on section 1743’s legislative
history. But even if we did, it supports our conclusion that the Legislature
intended for contractors and subcontractors to be held jointly and severally
liable for penalties imposed by the Labor Commissioner. An analysis of the
proposed section 1743 legislation stated: “Existing law, . . . [s]ection 1775[,
subdivision] (d), provides that ‘the contractor and subcontractor shall be
jointly and severally liable in the enforcement action for any wages due,’ and
specifies that the contractor is liable for collection only after enforcement of
all reasonable remedies against the subcontractor has been exhausted.
Section 1775[, subdivision] (b) makes a prime contractor liable for penalties
for a subcontractor’s violation of the law when the contractor either knows of
the subcontractor’s violation or fails to follow specific procedures to require
the subcontractor to comply with the prevailing wage law and to monitor
compliance. [¶] This bill would expressly hold a contractor jointly and
severally liable for all amounts due (including penalties) pursuant to a final
assessment of the commissioner or a judgment thereon.” (Sen. Floor Analysis
of Sen. Bill No. 1646 (1999-2000 Reg. Sess.)
IV. Substantial Evidence Supported the Penalty Assessment Imposed
Lusardi contends the superior court erroneously found that substantial
evidence supported the penalty assessment: “Neither the certified payroll
records nor any other evidence presented by the DLSE support the 154
penalty day calculation assessed against Pro Works. Accordingly, there is no
substantial evidence in the record to support the penalty assessment of
$30,800 based on 154 penalty days.” Lusardi contends: “The [Director’s]
22
purported de novo review of the penalty amount is not based on substantial
evidence.” (Bold and some capitalization omitted.)
The record shows that Anderson checked the four boxes corresponding
to the applicable former section 1777.7, subdivision (f) factors supporting her
determination that penalties should be imposed. She testified regarding how
she computed the number of days of violation, based on 154 days, 4,355 hours
and zero apprentice hours. Anderson further testified Nagtalon reviewed her
report and calculated the amount of penalty to be imposed for each day of
violation.
The Director exercised her de novo authority in reviewing the penalty,
and concluded “DLSE properly calculated the number of days that Pro
Works was in violation of the apprenticeship requirements.” For the reasons
stated in Anderson’s report and the Director’s independent review, we
conclude substantial evidence supported the penalty imposed. “[W]here, as
here, our review is limited to examining the whole administrative record to
determine if the [Labor Commissioner’s] findings and order are supported by
substantial evidence, it is not our function to reweigh the evidence or the
particular factors cited by the [Labor Commissioner] in support of [the]
decision . . . . Once we conclude, as we have here, that the [Labor
Commissioner’s] findings are indeed supported by substantial evidence, and
that those findings in turn support the . . . legal conclusion or ultimate
determination, our analysis is at an end.” (JKH Enterprises, Inc. v.
Department of Industrial Relations, supra, 142 Cal.App.4th at p. 1066.)
V. Claims of Due Process Violation
Due process has been identified as requiring notice, an opportunity to
be heard in a meaningful way, and an impartial adjudicator. (Today’s Fresh
23
Start, Inc. v. Los Angeles County Office of Education (2013) 57 Cal.4th 197,
212.)
Lusardi contends the court erroneously found there was no due process
violation; rather, the DLSE’s “Notice of apprentice compliance provided to
Lusardi with the notice of investigation is addressed only to Pro Works and
includes no indication that the DLSE is investigating whether Lusardi should
be liable for Pro Works’s alleged violations. . . . [N]or did the DLSE request
any information from Lusardi as part of its investigation. . . . Instead, the
DLSE’s actions suggested no intent to hold Lusardi liable and an
understanding that Lusardi is provided safe harbor under [former] section
1777.7[, subdivision] (d)(1)-(4).” (Some capitalization omitted.)
The DLSE notices that were sent to Lusardi complied with due process
by identifying Lusardi as the prime contractor and Pro Works as its
subcontractor. The notice of investigation was addressed to Lusardi directly
and advised it that the Labor Commissioner would issue an assessment
pursuant to it under section 17419 if violations were found. The notice of
apprenticeship compliance specifically states, “Non-compliance will result in
civil penalties . . . per . . . [former] section 1777.7.” We conclude the DLSE
notices adequately provided Lusardi notice of the potential to be held jointly
and severally liable.
Lusardi also contends it was denied its due process right to confront
Nagtalon at a hearing “to examine whether the DLSE could satisfy its burden
to show that all the circumstances set forth in [former] section 1777.7,
9 Section 1741, subdivision (a) provides: “If the Labor Commissioner or
his or her designee determines after an investigation that there has been a
violation of this chapter, the Labor Commissioner shall with reasonable
promptness issue a civil wage and penalty assessment to the contractor or
subcontractor, or both.”
24
subdivision (f), subparagraphs (1)-(4) were considered in the setting of the
penalty assessment.”
The record of the second hearing shows Lusardi elected not to request a
continuance to obtain Nagtalon’s testimony. Rather, it decided to rest its
case at the end of the DLSE’s case-in-chief. It therefore cannot be heard to
complain of a due process violation when it refused to enforce its subpoena or
ask for a continuance to secure the witness’s attendance. (Accord, Monaghan
v. Department of Motor Vehicles (1995) 35 Cal.App.4th 1621, 1626.)
Moreover, the Director reviewed the penalty imposed by Nagtalon de novo,
and in so doing applied the statutory factors set forth in former section
1777.7 subdivision (f). Any testimony regarding the penalty that Lusardi
sought to obtain from Nagtalon was not binding on the Director, and
therefore, Lusardi’s failure to secure Nagtalon’s testimony did not deprive it
of due process.
DISPOSITION
The order is affirmed. Costs are awarded to Real Party in Interest and
Respondent.
O’ROURKE, J.
WE CONCUR:
McCONNELL, P. J.
BUCHANAN, J.
25
Was bedeutet dieser Text für Ihre Situation?
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.