Filed 4/15/26 Friends of New Helvetia Public Housing v. City of Sacramento CA3
NOT TO BE PUBLISHED
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
THIRD APPELLATE DISTRICT
(Sacramento)
----

FRIENDS OF NEW HELVETIA PUBLIC C102468
HOUSING,
(Super. Ct. No.
Plaintiff and Appellant, 34202080003490CUWMGDS)

v.

CITY OF SACRAMENTO et al.,

Defendants and Respondents.

Appellant Friends of New Helvetia Public Housing (Friends) appeals a judgment
denying their petition for writ of mandate under the California Environmental Quality Act
(CEQA) (Pub. Resources Code, § 21000 et seq.).1 Friends challenge the Final

1 Undesignated statutory references are to the Public Resources Code. References to the
“Guidelines” are to the CEQA Guidelines (Cal. Code Regs., tit. 14, § 15000 et seq.). “In
interpreting CEQA, we accord the Guidelines great weight except where they are clearly

1
Environmental Impact Report (EIR) for the West Broadway Specific Plan (specific plan),
as certified by the City of Sacramento (City) as lead agency. Friends argue the EIR was
inadequate for failing to study or adopt their proposal for an alternative design that would
avoid or reduce the specific plan’s impacts on historic resources, and the City’s “approval
findings” were not supported by substantial evidence. We will reject these arguments and
affirm the judgment.
I. BACKGROUND
A. The Specific Plan Area
The specific plan addresses an area covering approximately 244 acres near
downtown Sacramento (the specific plan area). The specific plan area is “bounded by the
Sacramento River on the west, the centerline of Broadway on the north, Muir Way and
5th Street on the east, and 4th Avenue and Merkley Way on the south.” It encompasses
several distinct subareas, ranging from the Sacramento Marina and Miller Regional Park
to subareas historically associated with heavy and light industrial uses. It also
encompasses residential subareas, including two public housing communities owned by
the Sacramento Housing and Redevelopment Agency (SHRA): Alder Grove and Marina
Vista. This case principally concerns Alder Grove, the City’s first major public housing
project.
Alder Grove is located on the south side of Broadway between Muir Way and 5th
Street. Built in 1942, Alder Grove consists of 360 multi-family units within 61 apartment
buildings, laid out in a rectilinear grid with streets, pedestrian walkways, and a large
central open space area. Portions of Alder Grove have been listed on the National
Register of Historic Places (NRHP) and the California Register of Historic Resources
(CRHR) as the New Helvetia Historic District (New Helvetia). New Helvetia is

unauthorized or erroneous.” (Vineyard Area Citizens for Responsible Growth, Inc. v. City
of Rancho Cordova (2007) 40 Cal.4th 412, 428, fn. 5 (Vineyard).)

2
historically significant for several reasons, including its association with Nathanial S.
Colley, “a prominent African American civil rights attorney who advocated for fair
housing in Sacramento and nationally during the 1960s and 1970s.” 2
The specific plan area evolved in ad hoc fashion, resulting in a patchwork of
disparate land uses. This organic growth pattern can be seen in its irregular street layout,
which features “dead-end roadways and driveways that serve discrete land uses and do
not connect with the surrounding street grid.” The specific plan proposes to revitalize the
specific plan area—and make it more accessible to surrounding areas—by providing “a
framework for re-stitching the disconnected circulation patterns and disparate land uses
that exist today into a cohesive, contemporary neighborhood.”
B. The Specific Plan
“Every city is required to adopt a comprehensive, long-term general plan for the
physical development of the city.” (Beck Development Co. v. Southern Pacific
Transportation Co. (1996) 44 Cal.App.4th 1160, 1195 (Beck Development).) The general
plan becomes “a ‘ “constitution” for future development’ [citation], located at the top of
‘the hierarchy of local government law regulating land use.’ ” (DeVita v. County of Napa
(1995) 9 Cal.4th 763, 773.) The City’s general plan was adopted in March 2015 (the
general plan) and serves as “a 20-year policy guide for the physical, economic, and
environmental growth and renewal of the city, and it is the principal tool for the City to
use in evaluating public and private building projects and municipal-service
improvements.”

2 New Helvetia also represents “an important local attempt to improve the housing
conditions of African Americans through public housing,” and “the collaborative product
of a number of prominent Sacramento architects.”

3
“After adoption of a general plan, a city may adopt, by resolution or ordinance, a
specific plan or plans for the systematic implementation of the general plan for all or part
of the city. [Citations.] A specific plan must be consistent with the city’s general plan.
[Citation.] Among other things, a specific plan must contain standards and criteria by
which development will proceed, and a program of implementation including regulations,
programs, public works projects, and financing measures.” (Beck Development, supra,
44 Cal.App.4th at p. 1196.)
The specific plan at issue here was developed over several years, in a process that
involved neighborhood meetings, community workshops, and meetings of the City’s
planning and design commission, parks and community enrichment commission, active
transportation commission, and city council. The specific plan “describes the long-term
vision and land use, circulation, infrastructure, and urban design framework to guide
future growth within the [specific plan] area.” The specific plan’s objectives include: (1)
promoting new infill residential development and redevelopment that supports a variety
of housing choices, from market rate to affordable housing for low-income households;
(2) facilitating new mixed-use development and redevelopment within industrial
subareas; (3) enhancing bike and pedestrian travel ways through the specific plan area;
and (4) providing “a gridded street network that improves connectivity and access within
the [s]pecific [p]lan [a]rea to surrounding uses and neighborhoods.” The present dispute
focuses on the last of these objectives.
The specific plan does not propose any particular project or development in Alder
Grove. It instead “provides flexibility for a range of options for the Alder Grove subarea,
from infill development that supports the retention and adaptive reuse of historic
properties to significant or complete demolition and development of the Alder Grove site
into a mixed-income community.” Within that range, the specific plan assumes an
increase of 570 housing units, three acres of new parks and open space land, 34,000
square feet of commercial development, and a new community building spanning 6,000

4
square feet. It also calls for “the establishment of a coordinated and cohesive street grid
system through the entire West Broadway area.”
C. The EIR
An EIR was prepared for the specific plan. A draft EIR was circulated for public
comment between December 2019 and February 2020. The final EIR was released in
April 2020. The final EIR includes revisions to the draft EIR, responses to public
comments, a mitigation monitoring plan for the specific plan, and various appendices.3
(Guidelines, § 15132.)
The EIR is a program EIR, rather than a project EIR. “A program EIR is an EIR
which may be prepared on a series of actions that can be characterized as one large
project and are related either: [¶] (1) Geographically, [¶] (2) As logical parts in the chain
of contemplated actions, [¶] (3) In connection with issuance of rules, regulations, plans,
or other general criteria to govern the conduct of a continuing program, or [¶] (4) As
individual activities carried out under the same authorizing statutory or regulatory
authority and having generally similar environmental effects which can be mitigated in
similar ways.” (Guidelines, § 15168.) “A ‘program’ EIR allows an agency to ‘first
analyze[] “general matters contained in a broader [initial] EIR . . . with later EIRs . . .
[analyzing] narrow projects.” ’ ” (Make UC a Good Neighbor v. Regents of University of
California (2024) 16 Cal.5th 43, 50, fn. 7.)
The EIR identifies and analyzes potential environmental impacts of the specific
plan, including impacts to historic resources. (See generally Eureka Citizens for
Responsible Government v. City of Eureka (2007) 147 Cal.App.4th 357, 374 [“A
‘historical resource’ is one listed in, or eligible for listing in the California register of
historical resources; a resource included in a local register of historical resources (unless

3 Unless otherwise indicated, we refer to the draft EIR and final EIR collectively as the
EIR.

5
the preponderance of the evidence demonstrates that it is not historically or culturally
significant); any object, building, structure, site, area, place, record, or manuscript which
a lead agency determines to be historically significant, if the lead agency’s determination
is supported by substantial evidence”]; see also Guidelines, § 15064.5, subd. (b) [“A
project with an effect that may cause a substantial adverse change in the significance of
[a] historical resource is a project that may have a significant effect on the
environment”].) It is undisputed that New Helvetia qualifies as a historical resource.
The EIR acknowledges that redevelopment of Alder Grove could involve
“demolition of buildings” and “result in significant effects to historical resources.” “For
example,” the EIR says, “the realignment of Muir Way to 8th Street (north of Broadway)
would likely result in the removal of existing structures within Alder Grove.”
Furthermore, the EIR continues, “[d]amage to or destruction of a building or structure
that is a designated historical resource, eligible for listing as a historical resource, or a
potential historical resource that has not yet been evaluated, could result in the change in
its historical significance.” “Therefore,” the EIR concludes, the specific plan’s “impact
to historical resources would be potentially significant.”
“Once a significant environmental effect has been identified, ‘the EIR must
propose and describe mitigation measures that will minimize the significant
environmental effects that the EIR has identified.’ ” (Center for Biological Diversity v.
County of Los Angeles (2025) 112 Cal.App.5th 317, 352 (Center for Biological
Diversity).) The EIR proposes several measures to reduce the specific plan’s impacts on
historical resources, which are collectively designated as “[m]itigation [m]easure 4.4-1.”
Mitigation measure 4.4-1 requires that the City consult an architectural historian
and “consider measures that would enable the project to avoid direct or indirect impacts”
before altering or otherwise affecting a district or building that has already been
designated as a historical resource, such as New Helvetia or buildings within New
Helvetia. Such future measures could include “preserving a building on the margin of the

6
project site, using it ‘as is,’ or other measures that would not alter the building or
substantially affect the overall integrity of the historical resource.”
If the project cannot avoid modifications to a historic resource, the EIR requires
that the City call for the implementation of three additional measures, “to the extent
feasible.” First, if a building or structure can be preserved on site, but remodeling or
other alterations are required, the EIR requires that the work be conducted in compliance
with the Secretary of the Interior’s Standards for the Treatment of Historic Properties
(Secretary’s Standards). (See 36 C.F.R. ch. I, part 68; see also Guidelines, § 15064.5,
subd. (b)(3) [a project that follows the Secretary’s Standards “shall be considered as
mitigated to a level of less than a significant impact on the historical resource”].)
Second, if a significant historic building or structure is proposed for major alteration or
renovation, or to be moved or demolished, the EIR requires that the City ensure that an
architectural historian thoroughly document the building and associated landscaping and
setting. Third, if preservation and reuse at the site are infeasible, the EIR requires that the
building be documented as described above and, “when physically and financially
feasible,” moved and preserved or reused in a manner consistent with the Secretary’s
Standards.
The EIR concludes that mitigation measure 4.4-1 would “reduce potentially
significant impacts to historical resources because actions would be taken to record,
evaluate, avoid, or otherwise treat the resource appropriately, in accordance with
pertinent laws and regulations.” At the same time, the EIR recognizes that
“documentation of [a] historical resource will not mitigate the effects of demolition of
that resource to a less-than-significant level because the historical resources would no
longer exist.” What’s more, the EIR acknowledges, if buildings listed on the National
Register of Historic Places or California Register of Historic Resources are altered or
demolished, such resources “would be unavoidably impacted.” “Therefore,” the EIR

7
concludes, “because the potential for permanent loss of a historical resource or its
integrity cannot be precluded, impacts would remain significant and unavoidable.”
The EIR analyzes three alternatives to the specific plan, each intended to minimize
or avoid the specific plan’s potentially significant adverse impacts. (See generally In re
Bay-Delta etc. (2008) 43 Cal.4th 1143, 1163 (Bay-Delta) [“CEQA requires that an EIR,
in addition to analyzing the environmental effects of a proposed project, also consider
and analyze project alternatives that would reduce adverse environmental impacts”]; see
also Guidelines, § 15126.6, subd. (a) [An EIR must “describe a range of reasonable
alternatives to the project . . . which would feasibly attain most of the basic objectives of
the project but would avoid or substantially lessen any of the significant effects of the
project”].) The first alternative, known as “Alternative 1” or the “No Project-Existing
General Plan Alternative” (no project alternative), assumes that no specific plan would be
adopted for the specific plan area. Under the no project alternative, “[e]xisting structures
would be maintained in their current condition and would only modified in response to
specific developments proposed by individual landowners within the [s]pecific [p]lan
[a]rea,” consistent with the general plan.
The second alternative, known as “Alternative 2” or the “Historic Preservation
Alternative” (historic preservation alternative), contemplates that “historic structures
within the [s]pecific [p]lan [a]rea would be preserved and retained, with some
modernization.” Under the historic preservation alternative, “planned roadway network
improvements within Alder Grove and Marina Vista, including the realignment of Muir
Way, would not occur.”
The third alternative, known as “Alternative 3” or the “Lesser Density
Development Alternative” (lesser density alternative), assumes that most of the specific
plan area would be developed at a lower population density, with approximately 30 units
per acre of residential units and 1,000 square feet per acre of retail commercial building

8
area, resulting in a potential net change of 2,700 new residential units and a decrease in
commercial/industrial building area of 313,000 square feet.
The EIR concludes that all of the analyzed alternatives would achieve most of the
specific plan’s objectives, but “they would not achieve many of the objectives to the
extent of the [specific plan], including the provision of a variety of housing choices,
enhancing the West Broadway corridor as a gateway to the City, and improving the street
grid connections within the [s]pecific [p]lan [a]rea. Therefore, when considering
objectives,” the EIR concludes the specific plan “would best meet the purpose and need
for the plan.”
D. The CAW Plan
An organization called the Nathaniel S. Colley, Sr. Civil Rights Coalition (the
Coalition) transmitted a letter to the City in June 2020, some two months after the final
EIR was released. The letter argues the EIR fails to consider a reasonable range of
alternatives to the specific plan (then still in draft form), and asks the City to amend the
plan to “provide an alternative to the needless destruction of the New Helvetia Historic
District (aka Alder Grove).”
The letter encloses what appears to be a slide presentation by architecture firm
Cody Anderson & Wasney (CAW) Architects entitled, “New Helvetia Historic District
Development Study.” The parties call the enclosure the “CAW Plan,” and we will follow
their lead.
The CAW Plan opines that the specific plan calls for the demolition of New
Helvetia and the new street grid would require “demolition of the entire historical site.”
The CAW Plan proposes an alternative approach to development of the Alder Grove
subarea, which would increase housing density through the use of “podium buildings”
(i.e., newly constructed buildings added to what are now open space areas between
existing buildings). The CAW Plan also proposes to “extend[] existing streets to protect
historic buildings” and provide “new street connectivity to Broadway, Muir Way and

9
west edge.” The CAW Plan declares that all of these objectives could be achieved with
less demolition than contemplated by the specific plan. The Coalition’s letter urges the
City to consider the CAW Plan in a recirculated EIR.
E. Response to the CAW Plan
City staff prepared a response to the CAW Plan, which was attached to a staff
report to the planning and design commission in July 2020 (the response). The response
summarizes the previously described alternatives to the specific plan, focusing on the
historic preservation alternative.
The response allows that the CAW Plan would produce greater housing density
and require less demolition than the historic preservation alternative. However, the
response notes both would entail some demolition of historic buildings, and neither
would accomplish the objective of providing “a gridded street network that improves the
connection and access within the [s]pecific [p]lan [a]rea to surrounding uses and
neighborhoods.” Furthermore, the response explains, the CAW Plan’s use of podium
buildings could “dramatically redefine the spatial relationships” that characterize New
Helvetia, and compromise “the design integrity of the district as a whole (e.g., the
relationship of built elements to one another with respect to vistas, open space integration
and circulation, as well as the direct losses of landscape features),” such that “the
continued listing of the property on the NRHP might be called into question by the
Keeper of the Register.” Accordingly, the response concludes the CAW Plan “would
likely result in significant, unavoidable impacts to historic resources.” The response
further concludes the CAW Plan “does not propose any potential environmental effects
that were not already considered in an analyzed alternative” and “recirculation of the EIR
is not required.”
These conclusions aside, the response recognizes that some members of the public
may have understood the then-current draft of the specific plan to call for demolition and
redevelopment of New Helvetia. The response observes that the specific plan could be

10
revised to clarify that no such demolition is required. The response explains: “The intent
of the Specific Plan is to provide a long-term vision for this area and therefore, provides a
plan that acknowledges that SHRA may choose to demolish the Alder Grove site.
However, SHRA could choose to pursue a plan, such as that presented by the Colley
Coalition. The Specific Plan retains flexibility for a range of future options and does not
require SHRA to commit to a future action at this time. A concept, such as the one
presented by the Colley Coalition could be accommodated under the [s]pecific [p]lan.”
F. Revisions to the Specific Plan
The specific plan was revised in July 2020. According to a city council report
dated August 25, 2020 (the report), the revisions were intended to “[c]larify” “that the
[s]pecific [p]lan does not require demolition of the New Helvetia Historic District[,] and
[¶] . . . that the [s]pecific [p]lan policies, guidelines, and standards apply to a range of
potential outcomes for the Alder Grove subarea from preservation and refurbishment of
historic structures (and preservation of the New Helvetia Historic District) to complete
demolition of the existing site and development of a mixed-income community
(including the potential demolition of the New Helvetia Historic District).” The report
adds, “revisions have been made to the [s]pecific [p]lan, however, these do not constitute
significant new information for the purposes of CEQA Guidelines section 15088.5 and
therefore recirculation is not required.”
G. The City Approves the Specific Plan and Certifies the EIR
The City approved the specific plan and certified the EIR in August 2020. The
City adopted a statement of overriding considerations, findings of fact and a mitigation
monitoring plan as part of the approval process. With respect to the specific plan’s
impacts on historic resources, the City found the required mitigation measures “would
not be sufficient to reduce the impact to less than significant.” Nevertheless, the City
determined the specific plan’s “social, economic, and environmental benefits”
outweighed any unavoidable significant impacts. Accordingly, the City adopted a

11
statement of overriding considerations declaring, in part: “Having reduced the effects of
the project by adopting all feasible mitigation measures, and balanced the benefits of the
project against the project’s significant and unavoidable adverse environmental impacts,
the City . . . hereby determines that the specific overriding housing, transportation access,
sustainability, or other benefits of the project set forth above outweigh the potential
unavoidable adverse effects of the project.”
H. Trial Court Proceedings
Friends, an unincorporated association formed in September 2020, filed a petition
for writ of mandate that same month. The petition asserts a single cause of action for
violations of CEQA, alleging the City abused its discretion by certifying the EIR “with
inadequate project objectives; insufficient analysis of significant project impacts;
insufficient identification and analysis of potentially feasible mitigations; and insufficient
identification and analysis of a reasonable range of alternatives.” The petition also
alleges the City’s statement of overriding considerations and findings of fact as to the
feasibility of mitigation measures and project alternatives are not supported by substantial
evidence.
The trial court denied the petition in a tentative ruling issued July 15, 2024.
Following argument, the trial court affirmed the tentative ruling and entered judgment for
the City. This appeal timely followed.
II. DISCUSSION
Before we begin, a word on the briefing. Although Friends are represented by
experienced CEQA counsel, their arguments are conspicuously underdeveloped and
difficult to discern. Rather than explain how CEQA might have been violated, Friends’
opening brief offers lengthy excerpts from the administrative record followed by
formulaic recitations of black letter law. The opening brief makes little effort to apply the
law to the facts or support any argument with meaningful legal analysis. Some of
Friends’ arguments are not tethered to any legal doctrine at all, leaving us to speculate

12
what the ground for reversal might be. Other arguments are scattered throughout the
briefs but nowhere set forth “under a separate heading or subheading summarizing the
point.” (Cal. Rules of Court, rule 8.204(a)(1)(B).) We need not consider these
arguments. (See generally In re S.C. (2006) 138 Cal.App.4th 396, 408 [“When a point is
asserted without argument and authority for the proposition, ‘it is deemed to be without
foundation and requires no discussion by the reviewing court’ ”]; and see Pizarro v.
Reynoso (2017) 10 Cal.App.5th 172, 179 [“Failure to provide proper headings forfeits
issues that may be discussed in the brief but are not clearly identified by a heading”].)
Accordingly, we decline to consider Friends’ argument that the specific plan violates
CEQA by streamlining demolition of New Helvetia or end-running CEQA’s requirement
that the City make infeasibility findings before adopting a statement of overriding
conditions. (§ 21081, subd. (a).)
Reading the opening brief generously, we discern two cognizable arguments: (1)
that the EIR fails to adequately study and adopt feasible mitigation measures or project
alternatives (namely, the CAW Plan); and (2) that the City’s “approval findings” are not
supported by substantial evidence. Neither argument succeeds, as we next explain.
A. CEQA Overview and Standard of Review
“CEQA is a comprehensive scheme designed to provide long-term protection to
the environment.” (Mountain Lion Foundation v. Fish & Game Commission (1997) 16
Cal.4th 105, 112 (Mountain Lion).) “CEQA contains a ‘substantive mandate’ requiring
public agencies to refrain from approving projects with significant environmental effects
if ‘there are feasible alternatives or mitigation measures’ that can substantially lessen or
avoid those effects.” (County of San Diego v. Grossmont-Cuyamaca Community College
Dist. (2006) 141 Cal.App.4th 86, 98 (italics omitted).) However, “[a] public agency may
approve a project that will have a significant effect on the environment if the agency finds
that: (1) ‘[s]pecific economic, legal, social, technological, or other considerations . . .
make infeasible the mitigation measures or alternatives identified in the [EIR],’ and (2)

13
the significant effects on the environment are outweighed by ‘specific overriding
economic, legal, social, technological, or other benefits of the project.’ ” (Los Angeles
Conservancy v. City of West Hollywood (2017) 18 Cal.App.5th 1031, 1041.)
The EIR is often described as “ ‘the heart of CEQA.’ ” (See, e.g., Laurel Heights
Improvement Assn. v. Regents of University of California (1988) 47 Cal.3d 376, 392; see
also Cleveland National Forest Foundation v. San Diego Assn. of Governments (2017) 3
Cal.5th 497, 511 (Cleveland National Forest); and see Bay-Delta, supra, 43 Cal.4th at p.
1162.) “ ‘A public agency must prepare an EIR or cause an EIR to be prepared for any
project that it proposes to carry out or approve that may have a significant effect on the
environment’ [Citation.] ‘The EIR must describe the proposed project and its
environmental setting, state the objectives sought to be achieved, identify and analyze the
significant effects on the environment, state how those impacts can be mitigated or
avoided, and identify alternatives to the project, among other requirements.’ ”
(California Native Plant Society v. City of Santa Cruz (2009) 177 Cal.App.4th 957, 979
(California Native Plant).)
“When an EIR identifies significant effects on the environment if a project is
approved, the agency must make specific findings regarding potential mitigation
measures or alternatives and their feasibility. [Citation.] ‘A “mitigation measure” is a
suggestion or change that would reduce or minimize significant adverse impacts on the
environment caused by the project as proposed.’ [Citation.] ‘Mitigation measures are
modifications of the proposed design and implementation of a project imposed by the
lead agency to reduce the project’s adverse environmental effects. If an EIR identifies
significant environmental effects, CEQA requires the adoption of mitigation measures
when “it is feasible to do so.” ’ ” (Center for Biological Diversity, supra, 112
Cal.App.5th at p. 333.)
“CEQA findings are ‘required under . . . section 21081, subdivision (a), for each
significant effect noted in the draft.’ [Citation.] Specifically, ‘the agency must find that

14
the project’s significant environmental effects have been mitigated or avoided [citation],
that the measures necessary for mitigation “are within the responsibility and jurisdiction
of another public agency and have been, or can and should be, adopted by that other
agency” [citation], and/or that “specific economic, legal, social, technological, or other
considerations” render mitigation “infeasible.” ’ [Citation.] To move forward with a
project where mitigation is infeasible, the lead agency must find that ‘ “specific
overriding economic, legal, social, technological, or other benefits of the project
outweigh the significant effects on the environment.” ’ [Citations.] A statement of
overriding considerations ‘is required in CEQA approved projects to show that the
Project’s significant environmental effects have been identified, and avoided or mitigated,
or that unmitigated effects will be outweighed by the Project’s benefits.’ ” (Center for
Biological Diversity, supra, 112 Cal.App.5th at pp. 333-334.)
“ ‘An appellate court’s review of the administrative record for legal error and
substantial evidence in a CEQA case . . . is the same as the trial court’s: The appellate
court reviews the agency’s action, not the trial court’s decision’ to determine whether the
agency prejudicially abused its discretion. [Citations.] The agency abuses its discretion
if it has not proceeded in a manner required by law or if its factual determinations or
decision are not supported by substantial evidence.” (Center for Biological Diversity,
supra, 112 Cal.App.5th at p. 334.)
“In reviewing an agency’s decision for compliance with CEQA, we determine de
novo whether the agency employed proper procedures, and we review the agency’s
factual findings and statement of overriding considerations for substantial evidence.
[Citations.] ‘In evaluating an EIR for CEQA compliance, . . . a reviewing court must
adjust its scrutiny to the nature of the alleged defect, depending on whether the claim is
predominantly one of improper procedure or a dispute over the facts.’ ” (Center for
Biological Diversity, supra, 112 Cal.App.5th at p. 334.) “While we determine de novo
whether the agency has employed the correct procedures, ‘scrupulously enforc[ing] all

15
legislatively mandated CEQA requirements’ [citation], we accord greater deference to the
agency’s substantive factual conclusions.” (Vineyard, supra, 40 Cal.4th at p. 435.)
B. The City Was Not Required to Study or Adopt the CAW Plan
Friends argue the EIR violates CEQA by failing to study or adopt feasible
mitigation measures or alternatives to the specific plan. Friends are coy about which
mitigation measures or project alternatives they believe should have been considered.
They repeatedly suggest the CAW Plan was one of several suggestions for reducing or
avoiding demolition in New Helvetia. But they do not identify any other suggestion that
should have been considered. Accordingly, we understand Friends to argue the EIR
violates CEQA by failing to study or adopt the CAW Plan as an alternative or mitigation
measure. That argument fails for any number of reasons. We will focus on two of them.
First, we note that Friends view project alternatives and mitigation measures as
interchangeable or, in their words, “a distinction without meaningful difference.” That
perspective is not unreasonable, given that project alternatives and mitigation measures
generally serve similar purposes. For example, reduced demolition (such as that
contemplated by the CAW Plan) may sometimes be characterized as an alternative and
other times as a mitigation measure, depending on the circumstances. As always, labels
are less important than substance. (See generally City of Rancho Palos Verdes v. City
Council (1976) 59 Cal.App.3d 869, 893 [“The description of the option [of constructing a
smaller commercial area than originally proposed] as a ‘mitigating measure,’ rather than
an ‘alternative,’ is not significant”]; see also Dusek v. Redevelopment Agency (1985) 173
Cal.App.3d 1029, 1044 [“we look to substance rather than labels” when examining
compliance with CEQA].)4

4 Given the elusive nature of the distinction between mitigation measures and project
alternatives, we reject the City’s contention that Friends failed to exhaust administrative

16
But the differences between project alternatives and mitigation measures become
important where, as here, the proffered alternative addresses only one part of the project.
As the City observes, and Friends appropriately concede, CEQA requires that the lead
agency consider alternatives to the project as a whole, not components thereof. (See
California Native Plant, supra, 177 Cal.App.4th at p. 993; see also Big Rock Mesas
Property Owners Assn. v. Board of Supervisors (1977) 73 Cal.App.3d 218, 227 [“The
pertinent statute and EIR guidelines require that an EIR describe alternatives to the
proposed project. [Citation.] We interpret such requirement as applicable only to the
project as a whole, not to the various facets thereof”].) The CAW Plan only addresses
New Helvetia, not the specific plan area as a whole and thus does not constitute an
alternative to the specific plan. Consequently, the City was not required to consider the
CAW Plan as an alternative in the EIR. (1 Kostka & Zischke, Practice Under the
California Environmental Quality Act (Cont.Ed.Bar 2d ed. 2015 supp.) § 15.15, p. 15-23
(1 Kostka & Zischke) [“An EIR . . . need not consider an alternative addressed to an
ancillary facet of a project”].)
Second, we observe the CAW Plan was transmitted to the City in June 2020, after
the close of the public comment period in February 2020. Although neither party
addresses the issue, ample authority exists for the proposition that lead agencies need not
respond to late comments. (See, e.g., Gray v. County of Madera (2008) 167 Cal.App.4th
1099, 1110 [“Under CEQA, the lead agency may, but is not required to, respond to late
comments”]; Chico Advocates for a Responsible Economy v. City of Chico (2019) 40
Cal.App.5th 839, 852, fn. 9 [“CEQA does not require an agency to respond to comments
that are received after close of the designated public review period”]; see also Guidelines,
§ 15207 [“Although the lead agency need not respond to late comments, the lead agency

remedies with respect to their argument that the City should have considered the CAW
Plan as a mitigation measure.

17
may choose to respond to them”]; and see 1 Kostka & Zischke, supra, § 15.42, at p. 15-
49 [“Although a lead agency may respond to comments after the close of the period for
comment on the draft EIR, it is not required to do so”].)
Applying these authorities, we conclude the City had no obligation to consider or
respond to the CAW Plan. (Gray v. County of Madera, supra, 167 Cal.App.4th at p.
1111.) That being so, the EIR could not have been inadequate for failing to analyze or
respond to the CAW Plan. (Ibid. [“because the Board never had a legal duty to respond
to late comments, the inadequacy of the Board’s responses to the late comments is not
sufficient to render approval of the CEQA project ineffective or contrary to law”]; see
also 2 Kostka & Zischke, Practice Under the California Environmental Quality Act
(Cont.Ed.Bar 2d ed. 2015 supp.) § 16.12, at p. 16-15 (2 Kostka & Zischke) [“Given that
there is no legal duty to respond to late comments, the claimed inadequacy of responses
to late comments cannot be a basis for challenging the legal adequacy of an EIR”].) We
therefore reject Friends’ first argument—that the City violated CEQA by failing to study
or adopt the CAW Plan as an alternative to the specific plan or mitigation measure.
In any event, the City considered the CAW Plan in the response, which was
referenced in the City’s findings of fact and incorporated into the administrative record.
(See Citizens of Goleta Valley v. Board of Supervisors (1990) 52 Cal.3d 553, 567
[reviewing court may appropriately consult administrative record as a whole to assess
agency’s response to late comments]; 2 Kostka & Zischke, supra, § 16.12, at p. 16-15
[responses to late comments “may be included in a staff report, in staff testimony, or a
consultant’s report”].) That brings us to Friends’ second argument, to which we now
turn.
C. Friends’ Challenge to the City’s “Approval” Findings Fails
Friends next argues the City’s “approval findings” were not supported by
substantial evidence. Friends are characteristically vague as to which findings
supposedly lack support. Their opening brief suggests only one possibility: the City’s

18
claim in the statement of overriding considerations to have “reduced the effects of the
project by adopting all feasible mitigation measures.” Although not entirely clear from
their briefing, we understand Friends to argue the statement of overriding considerations
was not supported by substantial evidence because the City failed to adopt the CAW Plan,
which they say was feasible. Stated another way, we understand Friends to challenge the
City’s implied finding that the CAW Plan was infeasible. That argument, to the extent we
understand it, goes nowhere.
“Under CEQA, the public agency bears the burden of affirmatively demonstrating
that, notwithstanding a project’s impact on the environment, the agency’s approval of the
proposed project followed meaningful consideration of alternatives and mitigation
measures.” (Mountain Lion, supra, 16 Cal.4th at p. 134.) The agency may not approve a
project with significant environmental impacts “if there are feasible alternatives or
feasible mitigation measures available which would substantially lessen” the project’s
significant environmental impacts. (§ 21002.) “ ‘Feasible’ means capable of being
accomplished in a successful manner within a reasonable period of time, taking into
account economic, environmental, social, and technological factors.” (§ 21061.1; see
Guidelines, § 15364.)
Having determined that the specific plan would have significant impacts on
historic resources, the City was required to identify and discuss feasible mitigation
measures and project alternatives. (§ 21002; Center for Biological Diversity, supra, 112
Cal.App.5th at p. 352.) As previously discussed, the EIR proposes mitigation measure
4.4-1, which requires compliance with the Secretary’s Standards, documentation of
historic resources, and the relocation and preservation of historic buildings, “when
physically and financially feasible.” The EIR also considers three project alternatives,
including the historic preservation alternative, which would preserve historic structures
within the specific plan area and retain the existing street grid, much as the CAW Plan
proposes. Again, Friends do not identify any additional mitigation measure or project

19
alternative the EIR should have considered or discussed, other than the untimely CAW
Plan.
The City considered the CAW Plan in the response. The response acknowledges
the CAW Plan would require less demolition than the specific plan. However, the
response determines the CAW Plan would still require some demolition and the
introduction of new podium buildings into existing open spaces would compromise New
Helvetia’s design integrity and raise questions about its continued listing on the NRHP.
The response also determines the CAW Plan would not accomplish the specific plan’s
objective of providing “a gridded street network that improves the connection and access
within the Specific Plan Area to surrounding uses and neighborhoods.” These
determinations are referenced in the City’s findings of fact and support the implied
finding that the CAW Plan was infeasible. (See, e.g., Foundation for San Francisco’s
Architectural Heritage v. City and County of San Francisco (1980) 106 Cal.App.3d 893,
913 [alternative proposed after close of comment period impliedly found infeasible].)
An agency may reject mitigation measures or project alternatives that are
infeasible, so long as the finding of infeasibility is supported by substantial evidence in
the record. (Town of Atherton v. California High-Speed Rail Authority (2014) 228
Cal.App.4th 314, 353 (Town of Atherton).) An agency’s infeasibility findings “are
entitled to great deference and are presumed correct.” (Ibid.) “ ‘The parties seeking
mandamus bear the burden of proving otherwise, and the reviewing court must resolve
reasonable doubts in favor of the administrative findings and determination.’ ” (Ibid.)
Friends do not come close to carrying that burden.
Friends suggest the City’s infeasibility findings are conclusory. Their argument
amounts to an instance of the pot calling the kettle black. Friends do not address the
City’s determination that the CAW Plan would entail demolition of historic structures in
New Helvetia. They do not challenge the City’s determination that the CAW Plan would
so dramatically change New Helvetia as to threaten its continued listing on the NHRP.

20
Nor do they challenge the City’s determination that the CAW Plan would not achieve the
objective of providing a gridded street network in the specific plan area. Ignoring their
burden, Friends simply cut and paste the discussion of the CAW Plan from the resolution
adopting the specific plan and declare it inadequate. This approach to appellate advocacy
is itself inadequate. (See Town of Atherton, supra, 228 Cal.App.4th at p. 353.) We reject
Friends’ substantial evidence challenge to the City’s implied finding that the CAW Plan
was infeasible.
III. DISPOSITION
The judgment denying the petition for writ of mandate is affirmed. Respondents
are entitled to recover their reasonable costs on appeal. (Cal. Rules of Court, rule
8.278(a)(1) & (2).)

/S/

RENNER, Acting P. J.

We concur:

/S/

BOULWARE EURIE, J.

/S/

FEINBERG, J.

21