Filed 11/20/25 Pacific Carpets v. Shanghai Commercial Bank CA4/3

NOT TO BE PUBLISHED IN OFFICIAL REPORTS

California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FOURTH APPELLATE DISTRICT

DIVISION THREE

PACIFIC CARPETS, LLC,

Plaintiff and Appellant, G063689

v. (Super. Ct. No. 30-2022-
01245791)
SHANGHAI COMMERCIAL BANK,
LTD., OPINION

Defendant and Respondent.

Appeal from a judgment of the Superior Court of Orange County,
John C. Gastelum, Judge. Affirmed.
Lanak & Hanna and Mac W. Cabal for Plaintiff and Appellant.
Pierce Kavcioglu Espinosa & Cesar, Tyler J. Cesar, Armenak
Kavcioglu, and Aren Kavcioglu for Defendant and Respondent.
* * *
Plaintiff Pacific Carpets, LLC (the LLC) appeals from a judgment
entered in favor of defendant Shanghai Commercial Bank, Ltd. (the Bank).
The court granted a motion for summary judgment filed by other defendants
and held the LLC’s entire complaint was barred.
On appeal, the LLC contends the court erred by entering
judgment for the Bank because it did not file its own summary judgment
motion. We conclude the court did not err and affirm the judgment.
STATEMENT OF FACTS
I.
THE PARTIES AND UNDERLYING DISPUTE
The LLC is a subcontractor that performed work on an
apartment construction project. The Bank was the construction lender on the
project.
After a payment dispute arose between the LLC and the property
owner, the LLC recorded a mechanic’s lien against the property and served a
bonded stop payment notice on the Bank.
II.
THE COMPLAINT AND CROSS-COMPLAINT
The LLC later filed a complaint against the Bank and four other
entities, which are not parties to this appeal. The complaint alleged the four
entity defendants owed over $500,000 to the LLC for its work, labor, and
materials. The complaint also alleged a single cause of action against the
Bank to enforce the bonded stop payment notice.
In response, one of the entity defendants, 2525 Main Apartment,
LP (2525 Main), filed a cross-complaint and asserted causes of action for:
(1) breach of contract; and (2) recovery of compensation paid to an unlicensed

2
contractor.
III.
THE MOTION FOR SUMMARY JUDGMENT AND THE LAMBERT MOTION
In 2023, the four entity defendants moved for summary judgment
or, in the alternative, summary adjudication. The Bank did not file the
motion, which is central to the instant appeal.
Among other things, the entity defendants argued the complaint
was barred under Business and Professions Code section 7031, subdivision
(a)1 because the LLC was not licensed at all times during the construction
work. They further argued the LLC did not qualify for the substantial
compliance exception under section 7031, subdivision (e).
Soon after, 2525 Main filed a motion pursuant to Lambert v.
Superior Court (1991) 228 Cal.App.3d 383 (Lambert) to remove or reduce the
LLC’s mechanic’s lien and stop payment notice.
IV.
THE COURT’S SUMMARY JUDGMENT RULING
The court granted the summary judgment motion and held the
complaint was barred under section 7031, subdivision (a) because the LLC
was not properly licensed when it began working on the project. The court
also concluded the LLC did not qualify for protection under the safe harbor
rules for license renewals or the statutory substantial compliance doctrine.
Finally, the court granted summary adjudication on the cross-complaint’s
second cause of action for disgorgement of over $2 million paid to the LLC.

1
All further statutory references are to the Business and
Professions Code unless otherwise stated.

3
V.
THE BANK’S NOTICE OF LODGING AND THE JUDGMENT
A week later, the Bank filed a notice of lodging of proposed
judgment. In its notice, the Bank emphasized the court held all of the LLC’s
claims were barred when it granted summary judgment. The Bank
accordingly argued the LLC’s sole cause of action against the Bank for
enforcement of the bonded stop payment notice was moot and requested
judgment in its favor.
A few months later, the court granted 2525 Main’s Lambert
motion and released the mechanic’s lien as well as the stop payment notice.
Given the summary judgment ruling, the court emphasized the LLC’s “stop
payment notice” was “ineffective.” (Capitalization omitted.)2

In December 2023, the court entered a judgment that the LLC
“take nothing” from the Bank.
DISCUSSION
The LLC contends the court erred by entering judgment in favor
of the Bank based on a summary judgment motion that was filed by other
defendants. According to the LLC, the court effectively allowed the Bank to
“join” in the summary judgment motion even though the Bank did not comply
with the summary judgment statute. The LLC further claims the judgment
contravenes Code of Civil Procedure section 437c’s plain language, which
authorizes summary judgment only in favor of a moving party.
At the outset, we note the LLC did not raise these arguments in
its objections to the proposed judgment. Regardless, we exercise our

2
The court’s ruling on the Lambert motion is the subject of the
nonpublished companion appeal, Pacific Carpets, LLC v. Panku, Inc. (Nov.
20, 2025, G063243) [nonpub.opn.].
4
discretion to consider the arguments. For the reasons infra, the court did not
err by entering judgment in the Bank’s favor.
I.
APPLICABLE LAW
A stop payment notice is designed to secure payment to a
contractor or subcontractor who is owed money for its work on a project. (Civ.
Code, § 8500 et seq.) If a subcontractor serves a stop payment notice on the
construction lender, the lender “shall withhold from the borrower or other
person to whom the lender or the owner is obligated to make payments or
advancement out of the construction fund sufficient funds to pay the claim
stated in the notice.” (Id., § 8536, subd. (a).) A subcontractor cannot recover
any of the funds if it is not legally entitled to payment. (See id., § 8542, subd.
(a) [“the direct contractor or subcontractor may recover only the net amount
due the direct contractor or subcontractor”].)
II.
ANALYSIS
Here, the trial court’s summary judgment ruling eliminated any
grounds for relief against the Bank. The court specifically held the LLC was
not properly licensed so its entire complaint, including the cause of action
against the Bank, was barred. (§ 7031, subd. (a) [a contractor who was not
“duly licensed . . . at all times during the performance of” its contracting work
cannot bring an action to collect compensation for any of its work, including
work performed while licensed].)
In a companion appeal, we affirmed the court’s summary
judgment ruling. (Pacific Carpets, LLC v. 2525 Main Apartment, L.P. (Nov.
20, 2025, G064438) [nonpub. opn.].) Because the LLC’s stop payment notice

5
claim against the Bank depends on an underlying right to payment, the trial
court did not err by finding the claim was barred. Once the court determined
the LLC was not entitled to any compensation, there was nothing left to
adjudicate on the stop payment notice cause of action. The judgment merely
reflects that legal reality. (See Belio v. Panorama Optics, Inc. (1995) 33
Cal.App.4th 1096, 1101–1102 [summary adjudication on a cause of action
“effectively disposed of the entire case”]; § 7031, subd. (c) [“[a] security
interest taken to secure any payment for the performance of any act or
contract for which a license is required . . . is unenforceable if the person
performing the act or contract was not a duly licensed contractor”].)
The LLC’s reliance on Frazee v. Seely (2002) 95 Cal.App.4th 627
and Lerma v. County of Orange (2004) 120 Cal.App.4th 709 is misplaced. In
Frazee, another panel of this court held a party could not join a summary
judgment motion by merely filing a notice of joinder. (Frazee, at pp. 635–647.)
Likewise, in Lerma, another panel of this court held the trial court erred by
allowing an untimely joinder to a summary judgment motion. (Lerma, at
pp. 718–719.) In the instant case, the trial court never allowed the Bank to
“join” in a summary judgment motion it had not filed. Instead, the court
determined the LLC’s complaint was barred under section 7031, subdivision
(a). It reaffirmed that conclusion when it granted the Lambert motion and
released the stop payment notice. Under these circumstances, the judgment
reflected the court’s logical application of its rulings.
Even assuming the Bank had to file a separate motion for
summary judgment, reversing the judgment on this ground would serve no
practical purpose. On remand, the Bank would file a motion, and the trial
court would consider the same issue it already resolved. Indeed, before the

6
court entered judgment in the Bank’s favor, the court granted the Lambert
motion and released the stop payment notice. In doing so, the court explained
it had already determined the LLC was precluded from recovery on summary
judgment. Under these circumstances, there is no reason to disturb the
judgment.
DISPOSITION
The judgment is affirmed. The Bank shall recover its costs
incurred on appeal.

SANCHEZ, J.

WE CONCUR:

MOTOIKE, ACTING P. J.

MOORE, J.