CourtListener 5596359•McGuire v. Quintana
Gesamter Gesetzestext
The offered evidence should have been received. It tended to show that nothing was due to the contractor, the Bridge Company. (Pomroy’s Rem. Rights, sec. 700; Frisch v. Caler, 21 Cal. 71; Fairchild v. Amshaugh, 22 Cal. 575.)
*428Harrison & McMu/rtry, for the Respondent.
A breach of contract and damages under it must be specially pleaded. (Blethen v. Blalce, 44 Cal. 117; Piercy v. ¿Sabin, 10 Cal. 22; Philips on Mechanics’ Liens, sec. 424.)
By the Court :
The answer of the defendant was a general denial—nothing more. It was not competent for him to prove, under an answer of that character, “ that the buildings- were not finished by the contractor according to the contract,” etc. (Blethen v. Blake, 44 Cal. 117.)
Judgment affirmed. Remittitur forthwith.
Was bedeutet dieser Text für Ihre Situation?
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.