ASBCA 62694•Passaran Noori Construction Company
Gesamter Gesetzestext
ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Passaran Noori Construction Company ) ) ) APPEARANCE FOR THE APPELLANT: Mr. Jaweed Sharifi CEO APPEARANCES FOR THE GOVERNMENT: Scott N. Flesch, Esq. Army Chief Trial Attorney CPT Carlos S. Pedraza, JA Trial Attorney OPINION BY ADMINISTRATIVE JUDGE PAUL ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT This is an appeal of a contracting officer’s (CO) decision terminating appellant, Passaran Noori Construction Company (PNCC) contract with the U.S. Army for the convenience of the government. The Army has filed a motion for summary judgment, contending that appellant’s claim is barred by the applicable statute of limitations, 41 U.S.C. § 7103(a)(4)(A). The Contracts Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, is applicable. We grant the government’s motion. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION* 1. On August 9, 2007, the Kabul Regional Contracting Center, Camp Phoenix, Afghanistan, awarded Contract No. W91B4M-07-C-7144 to PNCC at a fixed – price amount of $567,037.51. The contractual efforts encompassed phase 3 of minor construction as Camp Phoenix. (R4, tab 1 at 1-3) 2. The contract stated: “Work is to begin no later than 15 days after demining is completed.” It also provided: “The Contractor shall begin performance within 70 calendar days and complete if within 90 calendar days after receiving . . . notice to proceed. (Id. at 1) The contractual performance period extended from October 11, 2007, to January 10, 2008 (id. at 3). * We cite these facts solely for purposes of resolving the government’s motion. ASBCA No. 62694 Under Contract No. W91B4M-07-C-7144
2 3. There is no evidence that appellant commenced work on the project (R4, tab 2 at 1). In October 2009, the CO informed appellant of his intent to terminate the contract at no cost to the government (R4, tab 8 at 1, tab 9 at 1). 4. On April 19, 2010, the CO terminated the contract for the convenience of the government. The CO issued a final decision on this date, which informed appellant of its appeal rights. (R4, tab 4) 5. On July 22, 2020, over 10 years after the final decision terminating the contract was issued, appellant filed a certified claim, in a total amount of $452,347, with the CO. In so doing, it acknowledged the CO’s decision to terminate the contract. (R4, tab 8 at 1) 6. In October 26, 2020, the CO issued another final decision in which he rejected appellant’s claim in its entirety. The CO stated, in part: “PNCC submitted its claim for this contract 13 years after contract award, and 10 years after the termination for convenience was issued. The [six]-year [s]tatute of limitations for submitting claims ran out several years ago.” (R4, tab 9 at 1-2) This appeal followed. DECISION Summary Judgment is appropriate where there is no genuine dispute of material facts and the moving party is entitled to judgment as a matter of law. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed. Cir. 1989). Here, there is no genuine factual dispute. The applicable statute of limitations, 41 U.S.C § 7103 (a)(4)(A), requires that claims under the CDA must be filed within six years after their accrual. This guidance is reiterated in FAR 33.206, INITIATION OF A CLAIM (OCT 1995). Here, the CO issued a final decision terminating the contract on a no-cost basis in April 2010 (SOF ¶¶ 3-4). Yet, appellant did not file its certified claim until July 2020 (SOF ¶ 5). In its reply brief, appellant contends that the CO never informed it regarding where and how it could file an appeal from his final decision terminating the contract. Appellant is mistaken. The CO’s decision clearly informed it of its appeal rights (SOF ¶ 4). Accordingly, appellant’s appeal must fail.
3 CONCLUSION The government’s motion for summary judgment is granted. The appeal is denied. Dated: July 29, 2021 MICHAEL T. PAUL Administrative Judge Armed Services Board of Contract Appeals I concur I concur RICHARD SHACKLEFORD Administrative Judge Acting Chairman Armed Services Board of Contract Appeals OWEN C. WILSON Administrative Judge Vice Chairman Armed Services Board of Contract Appeals I certify that the foregoing is a true copy of the Opinion and Decision of the Armed Services Board of Contract Appeals in ASBCA No. 62694, Appeal of Passaran Noori Construction Company, rendered in conformance with the Board’s Charter. Dated: July 29, 2021 PAULLA K. GATES-LEWIS Recorder, Armed Services Board of Contract Appeals
Was bedeutet dieser Text für Ihre Situation?
Kostenlose und unverbindliche Beratung
Schildern Sie uns Ihre Situation. Unser Team meldet sich per E-Mail bei Ihnen für Ihre Beratung.
Setzen Sie Ihre Recherche in ChatGPT oder Claude fort
Verbinden Sie Omnilex, um den Rechtskorpus über Ihren KI-Assistenten zu durchsuchen.