Kernrechtsfrage
Whether the appeal against the opposition decision remained live after the fund issued a corrective replacement decision.
Extrahierter Entscheid
The dispute had become moot because the new decision of 30 June 2010 fully granted the appellant's requested recalculation and replaced the challenged decision.
Extrahierte Begründung
Under Art. 53(3) LPGA and Art. 83 LPA-VD, the insurer could reconsider its decision before submitting its observations; by issuing the corrective decision, it fully complied with the appellant's conclusions, leaving no live controversy.