Kernrechtsfrage
Whether the engineer's liability for the alleged planning error is governed by contract for services or work contract rules.
Extrahierter Entscheid
The contract was a mixed agreement, but the specific planning error concerning reinforcement requirements was subject to work-contract rules.
Extrahierte Begründung
The decisive performance was an objectively measurable planning result; Swiss case law treats such engineer tasks under work-contract rules, even within a mixed contract.