Kernrechtsfrage
Whether the tender documents had to be interpreted as requiring an own construction schedule and more detailed comments on deadlines
Extrahierter Entscheid
The cantonal courts' interpretation was not arbitrary; X AG could reasonably be expected to submit its own construction programme and address the timetable.
Extrahierte Begründung
Item 221 of the tender documents expressly requested a construction programme and an assessment of the prescribed schedule. Even if the wording could have been clearer, the interpretation was still defensible; X AG could have clarified the requirement by inquiry with the listed contact office.