Kernrechtsfrage
Whether relocation and rental expenses caused by the delay in building were compensable under Art. 14 para. 2 LEspr
Extrahierter Entscheid
No; those expenses were not adequately causally linked to the expropriation and the later house differed materially from the initial project.
Extrahierte Begründung
The initial project did not provide comparable space for the therapeutic activity, and the later rentals began before the expropriation procedure or when the owner still had no final building permit. The owner also had a duty to mitigate damage.