Kernrechtsfrage
Whether the access road and site access were sufficiently approved and still valid for the planned project.
Extrahierter Entscheid
The existing 2002 approval covered only the first stage of the access road and had lapsed; the second stage was never validly approved, so the project lacked secured access.
Extrahierte Begründung
The court held that the earlier permit expressly concerned only the first stage, that the road had not been completed as approved, and that expired permits could not be relied on to complete the access. A private easement contract could not replace a public building permit.