Kernrechtsfrage
Whether the planned building project was compatible with the residential semi-extensive zone R3
Extrahierter Entscheid
The company did not show that the cantonal court acted arbitrarily in finding the plant predominantly industrial and therefore incompatible with the zone.
Extrahierte Begründung
Federal review was limited to arbitrariness. The appellant merely opposed the cantonal findings, but did not demonstrate that the characterization of the activity as chiefly industrial was manifestly unsustainable or that the municipal zoning rule had been applied arbitrarily.