Kernrechtsfrage
Whether the appellants had standing to challenge the Küssnacht segment despite the federal office's view that no final permit existed there yet.
Extrahierter Entscheid
Standing existed because the permit had in fact been granted for the disputed segment, and the appellants faced a concrete risk of legal prejudice.
Extrahierte Begründung
The dispositive and reasoning of the permit showed that the Freileitung was approved, subject only to a future study-linked obligation. The appellants needed legal certainty and could not be deprived of review by treating the clause as if no permit existed.