Kernrechtsfrage
Whether the appellant had standing to challenge the temporary expropriation in the federal public-law appeal.
Extrahierter Entscheid
No standing existed because the expropriation of the drilling site and access rights did not directly and personally affect the appellant; its concerns arose only from the future drilling and possible extraction activities.
Extrahierte Begründung
Art. 89(1) BGG requires a specific and direct impact plus a protected interest. The appellant was only a neighbor of the planned project, while the expropriated parcels belonged to the municipality, and the contested easement itself did not directly alter its legal or factual situation. Any objections to the drilling belong in the later planning and forestry authorization procedures.